Quantification and Costing Flashcards

1
Q

what is the the build up for a highway construction

A

capping layer - 320mm - subbase 240mm
base 1500mm - AC32
binder course 50mm - AC20
surface course 20mm - AC6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

typical rates for a car park surface?

A

parking place - 14£/m2
aisle - £19
bus route - 45

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what would you measure for a basement construction?

A
excavate and dispose topsoil
piles (including rig, hardstanding, testing, cutting
excavate and dispose
prep excavated surface
waterproofing
blinding
concrete to basement wall and slab
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

nrm editions?

A
  1. order of cost estimating and cost planning for capital building works
  2. details measurement for building works
  3. order of cost estimating and cost planning for building maintenance works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

nrm elements?

A

fac. works - sub - super - finishes - FFE - services - prefab - works to existing - ext. works - OHP - fees - prelims other - risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

manual contract of documents for highway works

A

implementation requirements - spec for hw works - guidance for spec - BQ contract documents - departmental standards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

MMHW?

A

definitions, general principles - prep of BQ - units

100 Prelims – 200 site clearance – 300 Fencing – 400 RRS – 500 Drainage & service Ducts – 600 Earthworks – 700 pavements – 1100 Kerbs Footways and paved areas – 1200 traffic signs and road markings – 1300 Road lighting columns, CCTV – 1400 Electrical work for road lighting and traffic signs – 3000 landscape and ecology