Quantification and Costing Flashcards

1
Q

Why were the New RUles of Measurement introduced

A

/ The previous standard method of measurement SMM7 was purely designed for the production of BOQ
/ This resulted in the lack of guidance and uniformity around preparing cost estimates and cost plans when using SMM7
/ The NRM was introduced to provide a common and consistent basis for the production of order of cost estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the Structure of NRM 1

A

/ Part 1 - General introduction
/ Part 2 - Measurement rules for the production of order of cost estimates
/ Part 3 - Measurement rules for the productions of elemental cost plans
/ Part 4 - Tabulated rules of measurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When should you use NRM

A

/ The NRM provides common and consistent basis for the production of order of cost estimates and cost plans
/ Provides confidence to employers
/ If negligence claim is brought NRM is best practice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is NRM 1

A

Order of Cost Estimating and elemental cost planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is GEA

A

Gross external Area

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is GIA

A

Gross internal area

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What do you measure in accordance with

A

/ NRM if a building project
/ CESMM if a civils based project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How would you measure steelwork in NRM 2

A

I would cross check the copy of NRM 2 for the correct guidance and measure in accordance the their measurement rule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the purpose of a BoQ

A

/ The purpose of a BOQ is to provide the estimator with an accurate picture of the scope of works and to provide a common and consistent basis for pricing
/ Following receipt of tender submissions, the BOQ also forms the basis for tender analysis through like for like tender
/ Basis for the valuation rules

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How would you prepare a BOQ

A

/ I would meet with the design team to establish if we have the information
/ I would compile all necessary documents - drawings, specifications, drawing registers etc
/ Check if sufficient information is present
/ agree a method of measurement
/ Commence take off and work from the substructure upwards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How would you structure a BOQ

A

In accordance to the elemental breakdown sturucture under NRM 2
/ Prelims
/ Facilitating works
/ Sub structure
Super
etc etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are included in prelim costs

A

/ Site setup
/ Management and supervision
/ Insurances
/ Task lighting
/ Protection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

If a bill rate was blatantly wrong how could this be resolved

A

works would be valued in agreement to the contract
if signed into the the contract then would have to be adhered to

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

If an item is missed from the BOQ how would you deal with it

A

Check if it is in the contract documents and should have been included
/ if not then see if still needed
/ Treat as a variation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a provisional sum

A

A provisions sum is an allowance included in the bill for works to be carried out where the extent and design of the work is unknown.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the difference between defined and undefined prov sums

A

/ Defined relate to work that can be identified but not measure ie £2000 for rotted timbers
/ Undefined relate to unseen and un quantified ie £2000 for unforeseen work under the flooring

17
Q

What is the simpson rule

A

Formula for working out the area of a curve

18
Q

How do you measure cut and fill

A

Split into a grid and work out average area to the new area

19
Q

Is quantity for excavation similar as disposal

A

Aslong as there is no allocation for bulking

20
Q

How would you measure in a different company

A

I will ensure the method of measurement used in that country

21
Q

What is a preamble

A

/ A preamble is an explanation of a document that is commonly found in contracts, specifications and bills
/ It can help with the interpretation of the document
/ It includes a description of the parties to the contract
/ The background to the document

22
Q

What are method related charges

A

/ A method charge is a one-off item related to the method of carrying out the work and does not form part of permanent works