Project Finance Flashcards

1
Q

How would you create a cash flow forecast

A

/ I would need to have access to the construction programme and contract sum analysis in order to populate the cashflow
/ The values associated with each element of construction could be forecasted at times to reflect their installation within the programme
/ I would split the works into different packages as shown on the contract programme and include individual s curves for each package
/ Obtaining drawdown schedules from specialist subcontractors and professional consultants can also assist when populating the cashflow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the benefit of a cash flow forecast

A

/ A cashflow forecast allows the employer to gain an understanding of the financial requirements over the duration of the project duration and setup any funding requirements for the scheme in advance
/ It can also act as a check against valuations and provide an early indication of financial difficulties if the actual expenditure is lagging behind the forecast

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What would you include in a financial report

A

I would look to include:
/ Contract sum total
/ Value of instructed variations
/ value of potential variations
/ ongoing claims
/ provisional sum adjustments
/ the anticipated final account total
/ the total certified sums

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the purpose of a financial report

A

/ To report against budgeted values and act as a working cost check on the project budget
/ To give the client an understanding of any savings or additional monies required
/ To report contract progress compared against pre contract predictions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are variations

A

/ Alterations or modifications to the design, quality or quantity of the contract works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Why might they arise

A

/ a change to the specification
/ discrepancies between contract documents
/ discrepancies with statutory requirements
/ errors and omissions
/ deficiencies in employers requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what form must architects instructions take

A

/ it is best practice under the majority of contracts for instructions to be made in writing
/ The QS is not usually authorised to make additions to the contract sum for instructions that are not in written form

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What about Oral instructions

A

/ The validity of oral instructions depends on whether the form of contract being used has the mechanisms for them to be valid

For example within the JCT standard building contract
/ Where the Contract Administrator issues an instruction otherwise than in writing it should have no immediate effect
/ but the contract shall confirm in writing receipt of the verbal instruction in 7 days
/ If the CA does not dissent by notice to the contractor within 7 days then the instruction takes effect

Best practice is to put in writing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Can the contractor object to a variation

A

/ Some contracts allows the contractor to object to an instruction in special circumstances
/ In the JCT SBC the requirement to comply with a valid instruction is subject to the to certain exceptions

// Where the instruction might affect the efficacy of the design of the Contractors Designed Portion
// Where the instruction might affect compliance with CDM
// Where the instruction infringes patent rights

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What can the architect do if the contractor does not comply with an instruction

A

/ This depends on the form of contract being used however under JCT suites if the contractor does not follow an instruction, the architect will be required to issues a ‘notice to comply’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What 3 methods are there of obtaining a cost for variations under JCT

A

/ Agreement between the employer and contractor
/ A schedule 2 quotation
/ Valuation by the QS under the valuation rules

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the Valuation rules under JCT forms of contract

A

/ If it is of a similar character, quantity and in the same conditions as existing work then the bill should be used
/ if it is of a similar character, but different quantity or conditions, the bill rates should be used as a basis but a fair allowance should take into account the difference
/ If it is not of a similar character, fair rates and prices should be used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What about non measurable work

A

This would typically be valued by the dayworks procedure based on the cost of labour, plant and materials that have been incurred

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a star rate

A

/ A rate that is based on the bill rates but includes a fair allowance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are ‘fair rates and prices’

A

/ A market rate
/ A rate based on actual costs
/ A rate in line with current cost data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are dayworks

A

The prime cost of all the materials, labour and plant used in carrying out the work along with percentage additions as set out in the contract

17
Q

What is Quantum Merit

A

What is deserved

18
Q

What is loss and expense under JCT forms of contract

A

Loss and expense reimburses the the contractor for direct loss and expense incurred in carrying out extra works

19
Q

What are the procedures for claiming loss and expense under JCT

A

/ As soon as the regular progress of the works is affected, or is likely to be affected they should notify the architect in writing
/ The contractor should submit any further information as requested by the architect
/ The contractor should also submit any further information as requested by the Architect or QS to enable the amount of loss and expense to be ascertained

20
Q

What are Relevant Matters

A

Relevant matters are items in a JCT that allow a contractor to claim loss and expense

21
Q

What are the Relevant Matters

A

The 5 relevant matters are
/ Variations
/ Instructions
/ Execution of an approximate quantity
/ Suspension by the contractor for non payment
/ Any impediment, prevention or default by the employer

22
Q

What is the key thing to remember when assessing loss and expense claims

A

It should be the actual loss incurred by the contractors

23
Q

What are the common heads of claim in loss and expense applications

A

/ Prolongation
/ Thickening of preliminaries eg extra costs for variations
/ Disruption causing plant or labour to be unemployed
/ Increases in labour or material costs during delay
/ Head office overheads
/ loss of profit