Quantification and Costing Flashcards

1
Q

What Rules of Measurement do you know of?

A
  • NRM 1: Order of cost estimating and cost planning for capital building works
  • NRM 2: Detailed measurement for building works
  • NRM 3: Order of cost estimating and cost planning for building maintenance works
  • Highways method of measurement
  • CESMM
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why were the New Rules of Measurement introduced?

A

Previous Standard Method of Measurements. (SMM7) was purely designed for the production of bill of quantities for tender purposes.

This resulted in a lack of guidance and uniformity around preparing cost estimates and cost plans when using SMM7.

NRM was introduced to provide a common and consistent basis for the production of order of cost estimates and cost plans and to give employers more confidence around their inclusions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the structure of the NRM 1?

A

Part 1: General introduction explaining the purpose of the document and how it should be used

Part 2: Measurement rules for the production of order of cost estimates

Part 3: Measurement rules for the production of elemental cost plans

Part 4: Tabulated rules of measurement for elemental cost planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why should you use the New Rules of Measurement?

A
  1. The NRM provides a common and consistent basis for the production of cost estimates and cost plans and this add confidence to the clients
  2. In the event that a QS is pursued for negligence, the use of NRM would provide a means of defence as it represents best practise
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the purpose of the Code of Measuring Practice?

A

The code of Measuring Practise provides precise defintions to permit the accurate and consistent measurement of buildings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What would you expect the percentage of NIA to GIA to be?

A

The percentage depends on the type of project being undertaken for example a school or office.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the purpose of a BoQ?

A

The purpose of a BoQ is to provide the estimator with an accurate picture of the scope of works and to provide a common and consistent basis for pricing

Furthermore a BoQ allows a tender analysis to be carried out by comparing each item against each other

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How would you prepare a BoQ?

A
  1. I would meet witht he design team to establish when the necessary information will be available, it is important to ensure the information provided is full and final to avoid abortive
  2. I would then look ti compile all information necessary from the Design Team, including:
    1. drawings, specifications, schedules
  3. Following receipt of the information I would check if the information is sufficient to allow the BoQ to be compiled. This will depend on the form of contract
  4. I would discuss with the client the measuement method to be adopted
  5. Prior to commencment of measurement and taking off quantities, I would conisder the size of the Project and break the works down into sections and areas:
    1. Substructures
    2. Superstructures
    3. External Works
  6. I would then commence take-off work from the substructure upwards
  7. When measuring is complete I would look to address the general items
  8. Following
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How would you structure a BoQ?

A

In accordance with NRM I would include the following:

Prelims

Facilitating works

Substructure

Internal finishes

Fittings, furnishing and equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What information is required to measure preliminaries?

A

Contract duration

Location

Size of project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How would you describe the preliminaries section in a Bill of Quantities?

A

The preliminaries detail items of work that are required to enable the construction but are not associated within the permanent works items

This would include things such as:

Site setup

Management and supervision

Insurances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

If it was found that a Bill rate was blatantly wrong for example £100 was included as a rate instead of £1, how would this be resolved?

A

The works would be valued in accordance with the agreed rate contained within the contract

If identified within the tender document prior to the contract being agreed then trhe rate could be amended in accordance witht he tendering rules, but otherwise both parties would have to stand by the rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do you evaluate a variation which is based on a BQ item which contains an error?

A

Assumming the same nature & conditions are applicable, the variation would be based on the BoQ rate within the contract

Unless both parties agreed to amend the rate to one that is fair and reasonable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a Provisional Sum?

A

A Provisional Sum is an allowance included within the BQ for works to be carried out where the extent and design of the work is not yet know meaning the cost cannot be established at the time of agreeing the contract sum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the difference between defined and undefined provisional sums?

A
  • A defined provisional sum is one that relates to works that cannot be accurately measured, but there is sufficient information about the works including their nature, method, location, quantity, limitations to allow planning, programming & pricing of preliminaries to take place. The contractor would therefore only be entitled to claim for any increase in the cost of the physical works.
  • Where there is insufficient information, the works are classed under an undefined provisional sum entitling the contractor to costs for prelims and an extension to the programme.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How did you check that the items measured for the BoQ were accurate?

A

I would utilise the junior team to carry out spot checks on the quantities to check they’re accurate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is a Preamble?

A

A preamble is an explanation of a document that is commonly found in contracts, specifications and bill of quantities

It helps with the interpretation of the document

18
Q

Is the quantity for excavation similar as disposal?

A

Yes providing there is no backfilling required and assuming the form of contract and method of
measurement does not allow for bulking, shrinkage or waste of earthworks

19
Q

What is the floor area method?

A

Floor area method

20
Q

What is the functional unit method?

A

A functional unit method will take a prime use of a building for example a school and number of desks and multiply the number of desks by a rate to establish a high level cost estimate

21
Q

What is the elemental unit method?

A

This method is the most detailed method of setting cost limits for each element of the project and effectively it takes an element such as a window and multiplies it by a rate and then this would contribute towards the total cost of the project

22
Q

What data sources are you aware of?

A

In house data from previous tenders
BCIS
SPONS

23
Q

What is SPONS?

A

SPONS is a series of 4 pricing books that helps you calculate and check costs of projects

24
Q

What is BCIS?

A

Building cost information service

25
Q

Which source of data is your first resort?

A

In house data for rates from project of similar nature

26
Q

What is an activity schedule?

A

In essence, it relates to a programme where each activity is allocated a price and interim payments are made against completion of each activity

27
Q

What is a BoQ?

A

A bill of quantities (sometimes referred to as ‘BoQ’ or ‘BQ’) is a document generally prepared by a cost consultant that provides project-specific measured quantities of the items identified in drawings and specifications for a built asset such as a building.

28
Q

On P Programme why did you produce an activity schedule?

A
29
Q

On P Programme how did you ensure the activity schedule reflects what your client required?

A

By understanding the activities required to be undertaken, such as number of site visits, prelims, liaising with the delivery team

30
Q

On CMP what kind of rates did you collect?

A

Various different rates, such as labour of site managers and PMs, windows, scaffolding weekly cost.

31
Q

On CMP how would you use NRM to measure plastering a ceiling?

A

NRM 2 work section 28: floor, wall and ceiling finishes.

32
Q

On CMP how would you use NRM to measure UPVC windows?

A

NRM 2 Work section 23 as a unit number.

33
Q

On CMP how would you use NRM to measure scaffolding works?

A

NRM 2 states that scaffolding is part of prelims and is a fixed charge on a weekly basis

However to give myself an estimate I would look at an average square meter rate and multiply it by the size of the building.

34
Q

You mentioned tender normalisation. Can you tell me how you about using that process and it helped you provide advice?

A

I was put in a fortunate position to carry out a tender comparison on a competitive framework

35
Q

You mentioned using average quantity using tender normalisation, what else could you use?

A

The highest quantity also

36
Q

How did you use tender normalisation to negotiate contract sums?

A

Tender normalisation put me in a fortunate position to be able to carry out like for like comparisons against each item and understand quantities. Where some contractors quoted excessively for labour for example compared other contractors, this gave me a better understanding of labour required and so put me in a position to reduce that element

37
Q

On CMP why did you advise on using BoQ over an activity schedule?

A

This was because the work on site was measureable and could bq quantified against rates. My client also wanted to collect rates

38
Q

When would you use NRM 1?

A

Order of cost estimating and cost planning for capital building works

38
Q

How do you quantify risk under NRM?

A
39
Q

When would you use NRM 2?

A

Detailed measurement for building works

40
Q

When would you use NRM 3?

A

Order of cost estimating and cost planning for building maintenance works