Quantification and Costing Flashcards
What Rules of Measurement do you know of?
- NRM 1: Order of cost estimating and cost planning for capital building works
- NRM 2: Detailed measurement for building works
- NRM 3: Order of cost estimating and cost planning for building maintenance works
- Highways method of measurement
- CESMM
Why were the New Rules of Measurement introduced?
Previous Standard Method of Measurements. (SMM7) was purely designed for the production of bill of quantities for tender purposes.
This resulted in a lack of guidance and uniformity around preparing cost estimates and cost plans when using SMM7.
NRM was introduced to provide a common and consistent basis for the production of order of cost estimates and cost plans and to give employers more confidence around their inclusions
What is the structure of the NRM 1?
Part 1: General introduction explaining the purpose of the document and how it should be used
Part 2: Measurement rules for the production of order of cost estimates
Part 3: Measurement rules for the production of elemental cost plans
Part 4: Tabulated rules of measurement for elemental cost planning
Why should you use the New Rules of Measurement?
- The NRM provides a common and consistent basis for the production of cost estimates and cost plans and this add confidence to the clients
- In the event that a QS is pursued for negligence, the use of NRM would provide a means of defence as it represents best practise
What is the purpose of the Code of Measuring Practice?
The code of Measuring Practise provides precise defintions to permit the accurate and consistent measurement of buildings
What would you expect the percentage of NIA to GIA to be?
The percentage depends on the type of project being undertaken for example a school or office.
What is the purpose of a BoQ?
The purpose of a BoQ is to provide the estimator with an accurate picture of the scope of works and to provide a common and consistent basis for pricing
Furthermore a BoQ allows a tender analysis to be carried out by comparing each item against each other
How would you prepare a BoQ?
- I would meet witht he design team to establish when the necessary information will be available, it is important to ensure the information provided is full and final to avoid abortive
- I would then look ti compile all information necessary from the Design Team, including:
- drawings, specifications, schedules
- Following receipt of the information I would check if the information is sufficient to allow the BoQ to be compiled. This will depend on the form of contract
- I would discuss with the client the measuement method to be adopted
- Prior to commencment of measurement and taking off quantities, I would conisder the size of the Project and break the works down into sections and areas:
- Substructures
- Superstructures
- External Works
- I would then commence take-off work from the substructure upwards
- When measuring is complete I would look to address the general items
- Following
How would you structure a BoQ?
In accordance with NRM I would include the following:
Prelims
Facilitating works
Substructure
Internal finishes
Fittings, furnishing and equipment
What information is required to measure preliminaries?
Contract duration
Location
Size of project
How would you describe the preliminaries section in a Bill of Quantities?
The preliminaries detail items of work that are required to enable the construction but are not associated within the permanent works items
This would include things such as:
Site setup
Management and supervision
Insurances
If it was found that a Bill rate was blatantly wrong for example £100 was included as a rate instead of £1, how would this be resolved?
The works would be valued in accordance with the agreed rate contained within the contract
If identified within the tender document prior to the contract being agreed then trhe rate could be amended in accordance witht he tendering rules, but otherwise both parties would have to stand by the rate
How do you evaluate a variation which is based on a BQ item which contains an error?
Assumming the same nature & conditions are applicable, the variation would be based on the BoQ rate within the contract
Unless both parties agreed to amend the rate to one that is fair and reasonable
What is a Provisional Sum?
A Provisional Sum is an allowance included within the BQ for works to be carried out where the extent and design of the work is not yet know meaning the cost cannot be established at the time of agreeing the contract sum
What is the difference between defined and undefined provisional sums?
- A defined provisional sum is one that relates to works that cannot be accurately measured, but there is sufficient information about the works including their nature, method, location, quantity, limitations to allow planning, programming & pricing of preliminaries to take place. The contractor would therefore only be entitled to claim for any increase in the cost of the physical works.
- Where there is insufficient information, the works are classed under an undefined provisional sum entitling the contractor to costs for prelims and an extension to the programme.
How did you check that the items measured for the BoQ were accurate?
I would utilise the junior team to carry out spot checks on the quantities to check they’re accurate