Quantification Flashcards
What is POMI
Principles of Measurement International
-Published By RICS Business service limited
-For Civil Engineering and Building works
-17 Sections & Appendix
-Section GP General Principal.
-Section A-R
CESMM3
Civil Engineers Standard Method of Measurements
-Prepared by the Institute of Civil Engineers.
-For Civil Engineering and associated small buildings.
-8 Sections and 26 Classes
-List of principal quantities provided
-Coding systems to BoQ items.
How Preliminaries Measured in POMI & CESEMM3
POMI: General Requirement.
CESSEM3: Genaral Items.
How you Measure duct works as POMI
Rectangular: By weight + FFisstings to be included ( measured center to center length)
Circular Ovel flexible- BY length, fitting to be measured separately +
Explain NRM
New rules of Mearement as 3 publication
NRM1 - Order of cost estimate
NRM2-Detail measurement of Capital building
NRM3-Maintainance and operation cost estimate.
How do you prepare a BOQ?
-Understand project parameters
- Gather all the information ( spec/ Dwg)
-Type of procurement.
-Payment mechanism.
-select the method of Measurement.
- Structure the BOQ
What are the 4 rules in CESSM3?
- Definition rule
- Measurement
- Covarage
- Additional description rule.
How To measure Pile
-Pile by length ( top to bottom of the pile)
-Boring through rock extra over
- Excavated materials by m3
-Reinforcement under section C by KG.
- Concrete Pouring by m3
- Curring top by number
-Testing Pile by item
What is the Structure of POMI BOQ
- Pricing Preamble / Rates and Measurement clauses
-General Requirements
-Works (site works/ Concrete / Masonry)
-Day works - PS sum
-Main summary