Q Flashcards

1
Q

Which of the following is the model form of contract for construction which is recommended by World Bank?

A) ITC
B) JCT
C) CIPS
D) FIDIC

A

Answer(s): D

Explanation:
FIDIC is the International Federation of Consulting Engineers (or Fédération Internationale des Ingénieurs Conseils in French). FIDIC has produced many publications, including the model form contracts, best practice guidances, research on sustainability, integrity and risk management. FIDIC model form contracts have been developed by this organisation since 1999, now they consist of several different books which are marked by colours. Thus, FIDIC model contracts also have the nickname “Rainbow suite of contracts”. Basically, the “Rainbow Suite” include the following books:

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which of the following are likely to feature within an outcome-specification?
1. Dimension
2. Performance requirement
3. Input material
4. Product function

A) 2 and 4 only
B) 3 and 4 only
C) 1 and 2 only
D) 1 and 3 only

A

Answer(s): A

Explanation:
There are two main types of specification: performance specification and conformance specification (sometimes called prescriptive or technical specifications).
Performance specifications have following features:
- Focus on outputs
- Set out result to be achieved
- The ‘what’, not the ‘how’
- Give supplier flexibility to present solutions that the buyer may not have considered

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

XYZ Ltd is negotiating a long-term supply contract of important parts with a supplier. Dave, procurement manager teams up with Alla, legal manager to construct a service level agreement. Dave is concerned that poor performance of supplier may cause damages to the operations of the organisation.
Which of the following can be used in conjunction with SLA to compensate the buying organisation in case of supplier’s poor performance?
1. Warranties
2. Force majeure clauses
3. Penalty clauses
4. Service credits

A) 1 and 3 only
B) 3 and 4 only
C) 1 and 2 only
D) 4 and 2 only

A

Answer(s): B

Explanation:
Service level agreement often sets out the minimum quality standards of the services provided, remedies if that standards are not met, consequences if the targets are exceeded. Penalty clauses and service credits are remedies that are often used in conjunction with service level agreement to ensure the performance and to compensate the purchaser if targets are not met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In which of the following section of a specification, requirements for training to use the equipment will be set out?

A) Performance
B) Consultation requirements
C) Implementation
D) Issue reference

A

Answer(s): C

Explanation:
Implementation is a substantive requirement which covers the following areas:
- Will there be a need to train the staff to use the equipment?
- Are there integration requirements with other systems or processes?
- How will this work?
- What are the timescales?
- Are detailed method statements required?
Consultation requirements regards to explicitness of compliance with any national or local legal requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

In common law, which of the following documents is legally binding without the need for consideration?

A) One-off contract
B) Hire purchase agreement
C) Deed
D) Blanket order

A

Answer(s): C

Explanation:
In common law (the legal system in which most rules come from case law or precedents, such as UK, US, Australia, etc), the contract is legally binding if it has the following requirements:
- Offer
- Acceptance
- Certainty & Intention to Create Legal Relations
- Consideration & Promissory Estoppel
- Legal capacity
According to these rules, ‘Blanket order’, ‘One-off purchase’, and ‘Hire purchase agreement’ are contractually binding. One of the reason is that they have consideration. However, there is a type of legal instruments that does not need consideration to be legally binding. They are called ‘Deeds’. A deed (anciently “an evidence”) is any legal instrument in writing which passes, affirms or confirms an interest, right, or property and that is signed, attested, delivered, and in some jurisdictions, sealed. It is commonly associated with transferring (conveyancing) title to property. At common law, to be valid and enforceable, a deed must meet several requirements:

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

If service level agreement is used as a schedule that makes up the contract, it will be most likely to be a part of…?

A) Pricing arrangement
B) Performance management framework
C) Exclusion of liabilities
D) Specifications

A

Answer(s): B

Explanation:
If a service level agreement is used as a schedule to a contract, it will generally have the following contents:
- Service definitions. If the service information is provided by the specification, SLA should only refer to the specification to avoid any inconsistencies.
- Details on how to measure KPIs, who will measure KPIs

  • Minimum requirements or targets
  • Remedies if the minimum requirements are not met

    Since SLA often lists out the KPI targets, consequences for not meeting the KPI targets and remedies to situation of poor performance, it is a part of performance management.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A construction company often subcontracts approximately 50% of the project works because of unpredictable customer’s demand. Although larger corporate customers require quick response to RFQ, the time lapse between tender bid submission and contract commencement is usually long.
Which of the following arrangement would benefit both the contractor and customer?

A) Collateral contract
B) Bilateral contract
C) Indemnity agreement
D) Framework agreement

A

Answer(s): D

Explanation:
According to the scenario, customers’ demand changes regularly but the construction project commencement often delays. If the contractor and the customer mutually sign a legally binding contract too soon long before the commencement, the contractor may suffer poor cash flow (it must buy the materials first but has to wait for long time to be paid). A framework agreement may help both parties.
A framework agreement is a formal agreement between two organisations that is intended to become legally binding in the event that a contract is created. A framework agreement could benefit the both parties in the following ways:
- At the time of signing, the framework agreement has not yet become a legally binding contract. The contractor and client only agree on the principles of future contracts (such as whether the work can be subcontracted or how payment will be proceeded). A well structured framework agreement will allow both parties to apply changes before contract commencement, especially regarding price and quality.
- The framework agreement assures a certainty between the contractor and client.

  • The administrative works is reduced under a framework agreement.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which of the following should be taken to avoid the conflicts between orally negotiated terms before the conclusion of contract and the final written contract?

A) Finding signs of misrepresentation of the other contracting party
B) Prevailing orally negotiated terms over the final written contract
C) Embedding a term excluding all prior oral discussions that are not mentioned in the final written contract
D) Avoiding long negotiation

A

Answer(s): C

Explanation:
When a written contract is based on oral negotiation, to avoid the conflicts between orally negotiated terms and final written contract, the contract should include an express term that specifically excludes all prior oral discussion. However, orally negotiated terms can be used to interpret the final contract.
This practice (excluding prior discussion) is so common in international commercial contract that UNIDROIT Principles of International Commercial Contracts have an article (2.1.17) dealing with this.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which of the following documents are likely to have legal standing? Select TWO that apply:

A) Quotation
B) Request for information
C) Tender
D) Requisition
E) Estimate

A

Answer(s): A,C

Explanation:
A quotation and a tender are both firm offers which have legal standing to the offeror. Tenders are more detailed than quotations and will include quality aspects as well as prices. LO 1, AC 1.1 & AC 1.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A company is considering entering a new market.
Which of the following are the external factors that influence the difference between cost and price of this company? Select THREE that apply

A) Procurement policy
B) Process efficiency
C) Business strategy
D) Threat of substitution
E) Competitiveness of the market
F) Relative bargaining power of supplier and purchaser

A

Answer(s): D,E,F

Explanation:
The difference between cost and price is profit. According to Michael E. Porter, the profitability of an industry is shaped by five forces:
1. Competition in the industry
2. Potential of new entrants into the industry
3. Power of suppliers
4. Power of customers
5. Threat of substitute products

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The pricing arrangement in which markup is added into cost base to calculate the final price is known as…?

A) Fixed Price approach
B) Market based approach
C) Price indices
D) Cost plus pricing

A

Answer(s): D

Explanation:
The market approach is a method of determining the value of an asset based on the selling price of similar assets.
A fixed-price strategy means you set a price and keep it constant for an extended period of time. Cost-plus pricing is also known as markup pricing. It’s a pricing method where a fixed percentage is added on top of the cost to produce
A price index (PI) is a measure of how prices change over a period of time, or in other words, it is a way to measure inflation. There are multiple methods on how to calculate inflation (or deflation).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which of the following will be included in a conformance specification?
1. Brand names
2. Description of the operating environments

  1. Chemical formulae
  2. Required safety level

A) 1 and 2 only
B) 1 and 3 only
C) 1 and 4 only
D) 2 and 3 only

A

Answer(s): D

Explanation:
According to CIPS, there are two main types of specification:
- Conformance specification ­ is more output driven as it outlines the product details exactly which may include the material, dimensions, tolerances, source, ingredients, packaging, storage of the part or material.
- Performance specification ­ is more output driven in terms of what the part or material must achieve.
Among the four options, only 2. ‘Description of the operating environments’ and 3. ‘Chemical formulae’ are possible components of a conformance specification. Brand names can be a part of a performance specification, according to a document published by CIPS and NIGP.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cleveland Insurance (Cleveland) offers a range of insurance services. The main software used in the call centre is a customer relationship management (CRM) system. Cleveland perceived an urgent need to replace the existing CRM system to deal with the increasing number of customers and services.
Urgent Digital Ltd (Digital) is one of the bidders of Cleveland’s ITT for designing, building and managing the new CRM system. Its bid team is led by Hank Irvine, its technical director. Hank realises that winning the Cleveland contract (valued at approximately £50M) will enhance his career. During discussions with Cleveland, Hank offers certain assurances regarding timescales for the project. He has not carried out any investigations into the viability of the timescales. Hank has little idea whether the timescales can be met.
Cleveland decides that Digital’s bid meets with its requirements, especially given the assurances in timescale offered by Hank, and decides to proceed with it, subject to a formal contract. Eventually, a formal contract is signed by both parties. The initial assurances given by Hank about the timing of the project are never going to be achieved and are at best grossly exaggerated.

Cleveland brought the case to the court and sought rescission of contract with Digital. Is Cleveland’s claim appropriate in this case?

Yes, because Cleveland needs to seek rescission first before claiming for damages
Yes, because both parties agreed with rescission of their contract
No, because the work had been carried out which could not be returned
No, because the contract does not include any provision on rescission

A

Answer(s): C

Explanation:
Hank’s pre-contractual assurances may amount to misrepresentation. Remedies for misrepresentation could be rescission of contract or damages. Rescission will be impossible in the following instance:
- Where the innocent party has affirmed the contract; that is, acted in a way confirming that they wish it to continue
- Where the claim has not been brought within a reasonable time (this is a point of general law)
- Where restitution (returning to the pre-contractual position) is impossible (e.g. because the goods have been consumed or have deteriorated)
- Where there has been intervention of innocent third-party (e.g., if the goods have been sold on) In this case, the subject of contract is designing, building and managing the new CRM system which is impossible to be restituted. Therefore, the contract cannot be rescinded.

Reference:
CIPS study guide page 53-55 LO 1, AC 1.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which of the following is the term that describes an item bought for a single and non-recurring use or purpose?

A) Call-off purchase
B) Ad-hoc purchase
C) Operational purchase
D) Stock purchase

A

Answer(s): B

Explanation:
Ad-hoc purchase is the item bought for a single and non-recurring use or purpose. A call-off contract, also known as a blanket order, is a purchase order which enables bulk orders over a period of time.
Operational procurement refers to the procurement of goods and services that are required to sustain an organization’s day-to-day business operations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which of the following are examples of incentives which can be embedded in contract terms? Select THREE that apply

A) Gainshare
B) Indemnity
C) Contract extensions
D) Service credits
E) Liquidated damages
F) Faster payment

A

Answer(s): A,C,F

Explanation:
Gainsharing is a system of management used by a business to increase profitability by motivating suppliers to improve their performance. As their performance meets the targets, suppliers share financially in the gain (improvement). Gainshare is an incentive for cost control.
Other incentives for good performance are:
- Contract extensions: Buyer can extend the contract duration as an incentive to supplier for meeting their targets.
- Accelerated payments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

To check whether supplier actually complies with the labour standards set out in the contract, the purchaser should have…?

A) Right to penalise the supplier
B) Right to terminate the contract
C) Right of audit
D) Right to rescind the contract

A

Answer(s): C

Explanation:
Many firms have compliance policies for suppliers in place. To ensure that the supplier actually comply with the standards set out, the purchaser can employ the right to audit. The buyer usually obtains the right to examine records of a vendor to determine if a fraud or a violation of company policy has occurred through the following methods:
- Right-to-audit agreement The agreement can be printed on the back of a purchase order, contract, or other procurement form.
- A simple request If the right-to-audit agreement wasn’t included on the procurement form, and the buyer suspects irregularities, he may have to beg the vendor to allow an audit to be performed. If the buyer is a major customer of the vendor, the buyer may be able to wield a big enough stick to obtain permission to look at the records.
- Right-to-audit Pitfalls

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Is the government only source of industrial standards within a country?

A) No, the government can only adopt standards regarding security and defence
B) Yes, while ISO make standards for international trade, the government standardises other facets of their country
C) No, an organisation can also generate its own internal standards
D) Yes, the standards must be made by legislative branch of the country

A

Answer(s): C

Explanation:
A standard is a document that sets out requirements for a specific item, material, component, system or service, or describes in detail a particular method or procedure. Standards are established by consensus and approved by recognized standardization bodies. There are several different types of standards. Some of the most commonly-used standards set out the requirements that a particular kind of product, service or process must fulfil, in order to establish that it is `fit for purpose’. Other types of standard relate to methods of testing, terminology and definitions, information requirements, or the compatibility of connections. Standards provide individuals, businesses and all kinds of organizations with a common basis for mutual understanding. They are especially useful for communication, measurement, commerce and manufacturing.
Standards make trade easier by ensuring compatibility and interoperability of components, products and services. They bring benefits to businesses and consumers in terms of reducing costs, enhancing performance and improving safety.
Standards are voluntary, which means that businesses and other organizations are not legally obliged to apply them. However, in certain cases standards may facilitate compliance with legal requirements, such as those contained in European directives and regulations. Standards can be made by a company, a standard organisation (such as ISO or BSI) or regulatory bodies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which of the following is used to detail the complex matter that may be verbiage to the main document?

A) Contract variation
B) Schedule
C) Subcontracting
D) Standard terms and conditions

A

Answer(s): B

Explanation:
Without further explanation, a schedule may be deemed to form an integral part of the obligations of either or both parties. Obviously, the scope or binding nature of such schedule depends on the way it is referred to in the obligatory language of the main agreement. Accordingly, merely attaching the general terms and conditions of sale without explaining to which part of the sale they apply or which provisions apply does not subject a sale pursuant to the body text of the agreement to those general terms and conditions.
Subcontracting is the practice of assigning, or outsourcing, part of the obligations and tasks under a contract to another party known as a subcontractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Southwark is negotiating a contract with Orchard to provide software and IT services. Orchard will manufacture and install the products which are contractually supplied by IBM. Southwark’s procurement manager is worried that during the contract there would be some problems that they would not able to claim for damages from Orchard.
Which of the following should be included in the head contract so that Southward can sue IBM, should the need arise?

A) Negligence
B) Indemnity
C) Collateral warranty deed
D) Insurance

A

Answer(s): C

Explanation:
A Collateral Warranty is a contract under which a consultant, a building contractor or a sub- contractor warrants to a third party that is has fulfilled its obligations under its professional appointment, building contract or sub-contract. The purpose of a Collateral Warranty is to give a third party, who is not a party to the original contract, rights to enforce that original contract. In this case, IBM is the subcontractor, then purchaser can use collateral warranty deed to bind them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which of the following indicates the ratio between profit and costs?

A) Gearing
B) Margin
C) Mark-up
D) Liquidity

A

Answer(s): C

Explanation:
Mark up is the profit as a percentage of total costs. LO 3, AC 3.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which of the following encourages social and environmental criteria in public sector contracting in the UK?

A) Social Action, Responsibility and Heroism Act
B) The Public Services Act
C) Children and Social Work Act
D) Supply and Appropriation Act

A

Answer(s): B

Explanation:
Social and environmental criteria are increasingly encouraged in public sector contracting. In the UK, The Public Services (Social Value) Act 2012 encourages public organising to apply social and environmental criteria in contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

In a contract, both buyer and supplier agreed the lead time is 3 days. The contract also requires that any variation must be made in writing. Then the buyer places an order by phone call and requests delivery the next day, but the supplier delivers on the third day since the order. Can buyer refuse to pay as supplier did not deliver per time?

A) No, the supplier delivers within a reasonable time
B) Yes, late delivery is a force majeure event
C) Yes, the supplier has breached the contract
D) No, supplier has shortened lead time to 1 day

A

Answer(s): A

Explanation:
Lead time is the amount of time that passes from the start of a process until its conclusion. In procurement, lead time can be understood as the amount of time that passes from placing an order until the delivery.
In the scenario, the contract requires the supplier to make a delivery within 3 days since the order. This contract can only be amended with written consent from both parties. Therefore, there is no ground for shortening the lead time to 1 day because the new lead time is only the request of buyer. Then the supplier still makes delivery within agreed lead time. LO 1, AC 1.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

In a sale contract, a clause requires the seller to “defend, reimburse, and hold harmless” the buyer and its personnel from and against any and all damages arising in connection with some specific circumstances. This clause is an example of…?

A) Insurance
B) Liquidated damages
C) Indemnity
D) Force Majeure

A

Answer(s): C

Explanation:
An indemnity is a promise by one party to compensate another for the loss suffered as a consequence of a specific event, called the ‘‘trigger event’’. The trigger event can be anything defined by the parties, including:
- A breach of contract;
- A party’s fault or negligence;
- A specific action.
An indemnity operates as a transfer of risks between the parties, and changes what they would otherwise be liable for or entitled to under a normal damage claim. Force Majeure Provisions: A force majeure event refers to the occurrence of an event which is outside the reasonable control of a party and which prevents that party from performing its obligations under a contract.
Liquidated damages are presented in certain legal contracts as an estimate of otherwise intangible or hard-to-define losses to one of the parties. It is a provision that allows for the payment of a specified sum should one of the parties be in breach of contract. LO 3, AC 3.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Which of the following are reasons why a purchaser wants to embed a subcontracting clause into the main contract? Select TWO that apply:

A) To induce the conflicts between the main contractor and subcontractors
B) To improve supply chain transparency
C) To reduce the main contract complexity
D) To keep main contractor liable
F) To condemn whole liabilities to subcontractors

A

Answer(s): B, D

Explanation:
There are number of reasons why the purchaser will want to control the supplier’s subcontracting:
- Supply chain transparency: Normally the purchaser has invested a lot of effort into selecting the right contractor. However, the main contractor’s selection of subcontractor might not be in such careful manner, which may result in poor performance. Purchaser must know who subcontractors are. Controlling the subcontracting process can help the purchaser control the outcome.

  • Contract terms: the purchaser’s requirements must be reflected in the subcontracts. The subcontracting clauses may require the main contractor to do this.
  • Liability: the main contractor may subcontract the whole or a part of its liabilities. Subcontracting clause may bind the contractor to be liable with the work, it cannot just blame the subcontractor for any faults.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A construction company is undertaking a housing development project. They need lots of bricks and other building materials, but the construction site doesn’t have large area for storage of materials. Therefore, the company’s suppliers must deliver the building materials with fixed quantity and at fixed time intervals.
What type of contract is used between the construction company and its suppliers?

A) Framework agreement
B) Spot transaction
C) One off contract
D) Call off contract

A

Answer(s): D

Explanation:
In the scenario, the contract between the company and its suppliers is continuous rather than one- off. So it cannot be one-off contract or spot purchase. The quantity and time is well known and fixed, this type of contract is known as call-off contract or blanket order.

Reference:
CIPS study guide page 63-64 LO 1, AC 1.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which of the following is the set of principles that enables courts to determine exactly what the written contract says and what that must mean, then the court will uphold that?

A) Order of precedence
B) Rules of interpretation
C) Unfair Contract Act 1977
D) Rules of contract formation

A

Answer(s): B

Explanation:
Courts may be called upon to interpret a statute due to disputes over the meaning of a word or phrase contained within a statute. These disputes may arise through a variety of reasons. It has long been held that words are an imperfect means of communication. Omissions may have occurred at the drafting stage, word or phraseology ambiguity, etymological change through time, oversight on specific points, or a failure to adapt legislation to new developments. This may result in the judiciary providing a role in statutory interpretation. Statutory interpretation in its broadest sense is the process of determining the true meaning of a written document. In UK, the Interpretation Act 1978 provides limited scope to assist judges with statutory interpretation in that it only provides standard definitions to common provisions such as a rebuttable presumption that terminology in the masculine gender also include the feminine, and that the singular includes plural. An order of precedence clause sets out the order in which the contract documents take precedence in the event of an inconsistency.
The Unfair Contract Terms Act 1977 (c 50) is an Act of Parliament of the United Kingdom which regulates contracts by restricting the operation and legality of some contract terms. It extends to nearly all forms of contract and one of its most important functions is limiting the applicability of disclaimers of liability. The terms extend to both actual contract terms and notices that are seen to constitute a contractual obligation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which of the following is regulated by standard ISO 14001?

A) Energy management
B) Quality management systems
C) Environmental management
D) Information security management

A

Answer(s): C

Explanation:
ISO has about 22,000 international standards covering a vast range of aspects of product or service quality. Below are some of the most common ISO standards:
- ISO 9001: Quality management system
- ISO 27001: Information security management
- ISO 5001: Energy management
- ISO 14001: Environmental management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Under general legal principles of contract formation, which of the following will always automatically result in the termination of an offer?
1. Negotiation
2. Rejection
3. Failure conditionality
4. Non-disclosure

A) 3 and 4 only
B) 1 and 4 only
C) 1 and 2 only
D) 2 and 3 only

A

Answer(s): D

Explanation:
There are a number of ways for an offer to be terminated. They are events that may occur after an offer has been made which bring it to an end so that it can no longer be accepted. An offer is terminated in the following circumstances:
1. Revocation
2. Rejection

  1. Lapse of time
  2. Conditional Offer (or Failure of Conditionality)
  3. Operation of law
  4. Death
  5. Acceptance
  6. Illegality
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Which of the following are likely to be advantages of using invitation to tender? Select TWO that apply:
Short turnaround times

A) Quick implementation
B) Driving forward planning culture
C) Lower administration costs
D) Reducing risks of bribery and corruption

A

Answer(s): B,D

Explanation:
Advantages of using invitation to tender may be as below:
No Nepotism: Tenders or bids are evaluated on the basis of certain predetermined criteria, such as price, quality and value for money. In other words, the firm offering the highest quality product or service at the lowest price point would win the contract. As most tender documents are opened and evaluated in a public process, I think that there remains little room for nepotism or favoritism of any kind.
Value for Money: From the perspective of the client, tenders offer the greatest value for the amount of money spent. This is due to the fact that the client can choose from a wide pool of potential suppliers to select the ones that can produce the highest quality product or service at the lowest price point. This allows the company, establishment or organization to save money without having to compromise on quality. Therefore, despite being quite time consuming, tendering is, in my opinion, a profitable long-term process from an organization’s point of view.

Encourages Competition: The process of tendering helps promote a competitive market. This is because a number of potential contractors, firms or suppliers get a chance to bid for every project. And because selection depends on quality and price, every bidder tries to reduce operational inefficiencies and redundancies as much as possible in order to lower expenses and improve quality. This entire process encourages healthy competition in the market and prevents complacency and laziness, which in turn provides a boost to innovation and new ideas. Easier Entry: The system of tendering makes it easier and simpler for new firms to enter the market or even a particular industry. This is due to the fact that contracts under this system are awarded on the basis of predetermined, objective criteria. As a result, even a firm that is a new entrant to the market, having no connections or contacts in the industry, can win a prestigious and lucrative contract by providing the highest value for the client’s money. This process therefore helps new firms to quickly get a foothold in the market or industry, thus significantly lowering the traditional barriers to entry.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

XYZ Ltd is negotiating a long-term supply contract of important parts with a supplier. Dave, procurement manager teams up with Alla, legal manager to construct a service level agreement. Dave is concerned that poor performance of supplier may cause damages to the operations of the organisation.
Which of the following can be used in conjunction with SLA to compensate the buying organisation in case of supplier’s poor performance?
1. Warranties

  1. Force majeure clauses
  2. Penalty clauses
  3. Service credits

A) 1 and 3 only
B) 3 and 4 only
C) 1 and 2 only
D) 4 and 2 only

A

Answer(s): B

Explanation:
Service level agreement often sets out the minimum quality standards of the services provided, remedies if that standards are not met, consequences if the targets are exceeded. Penalty clauses and service credits are remedies that are often used in conjunction with service level agreement to ensure the performance and to compensate the purchaser if targets are not met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Which of the following is the model form of contract for construction which is recommended by World Bank?

A) ITC
B) JCT
C) CIPS
D) FIDIC

A

Answer(s): D

Explanation:
FIDIC is the International Federation of Consulting Engineers (or Fédération Internationale des Ingénieurs Conseils in French). FIDIC has produced many publications, including the model form contracts, best practice guidances, research on sustainability, integrity and risk management. FIDIC model form contracts have been developed by this organisation since 1999, now they consist of several different books which are marked by colours. Thus, FIDIC model contracts also have the nickname “Rainbow suite of contracts”. Basically, the “Rainbow Suite” include the following books:
* Yellow book: Plant and Design-Build Contract (2 editions: 1999 and 2017)
* Silver book: EPC/Turnkey Contract (2 editions: 1999 and 2017)
* Red book: Construction Contracts (2 editions: 1999 and 2017)
* Emerald book: Conditions of Contract for Underground Works (1st Ed 2019)
* Blue-Green book: Dredgers Contract (2 editions: 2006 and 2016)
* Gold book: Design, Build and Operate Contract Guide
* Pink book: Construction Contract Multilateral Development Bank Harmonised Ed (2 editions: 2005 and 2010)
This type of model contract is commonly used around the world because its author, International Federation of Consulting Engineers, collaborates closely with development banks such as World Bank, Africa Development Bank, Asia Development Bank, etc. Every construction project that is financed by these institutions must adopt the FIDIC contracts. The Joint Contracts Tribunal, also known as the JCT, produces standard forms of contract for construction, guidance notes and other standard documentation for use in the construction industry in the United Kingdom. From its establishment in 1931, JCT has expanded the number of contributing organisations.
ITC (International Trade Centre) produces contracts specifically designed for small companies doing international business, covering the sale of goods, distribution, services and joint ventures. Many small companies are now engaged in international trade, but don’t have access to the necessary contract forms to protect themselves. ITC and leading legal experts developed eight generic contract templates that incorporate internationally recognized standards and laws for most small business situations.
CIPS has several model forms of contract designed specifically for IT buying and servicing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Which of the following are always included within a framework agreement? Select TWO that apply:

A) Exact quantity to be purchased
B) Call-off procedure
C) Exact price to be paid
D) Duration
E) Insurance

A

Answer(s): B,D

Explanation:
A framework agreement will set out the following:
- How call offs can be made - whether a mini-competition is required or a direct call off can be made
- How price is calculated
- The specification - this may have various options to cater for different needs
- The duration of the agreement
- Who can access the agreement
- Any limitations
- The main terms to be included in the contract or the form of contract to be used, where this is intended to be a standard form.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Which of the following are features of performance specification?
1. Method of achieving the buyer’s desired result
2.
What needs to be achieved when using the product
3. Purposes of the product
4. Technical and physical characteristics of the product

A) 2 and 4 only
B) 1 and 2 only
C) 1 and 4 only
D) 2 and 3 only

A

Answer(s): D

Explanation:
There are 2 major types of specifications:
1. Performance specifications
These are Specifications that define the purpose of the goods or services in terms of how effectively it will perform. Performance is a logical extension of function. Performance specifications define the task or desired result by focusing on what is to be achieved. They do not describe the method of achieving the desired result.
2. Technical (or conformance) specifications
These are Specifications that define the technical and physical characteristics and/or measurements of a product, such as physical aspects (e.g. dimensions, colour, and surface finish), design details, material properties, energy requirements, processes, maintenance requirements and operational requirements. They are used when functional and performance characteristics are insufficient to define the requirement and are often used for engineering and information technology requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Danielle buys a car from Aaron. Not long after, she receives an proposal from Brian, who is interested in buying the car but his budget is very constraint. Then, Brian decides to sign a hire purchase agreement with Danielle which lasts 4 years. Brian lives very far from Danielle, so he hires Charlie to deliver the car to his place. During the transport, Charlie has an accident and the car is written off. At the time of accident, who has the title of the car?

A) Charlie
B) Aaron
C) Brian
D) Danielle

A

Answer(s): D

Explanation:
Hire purchase is an arrangement for buying expensive consumer goods, where the buyer makes an initial down payment and pays the balance plus interest in installments. The ownership of the merchandise is not officially transferred to the buyer until all the payments have been made. Danielle has purchased the car from Aaron, which means its title has been transferred to her. The accident happens before the last instalment is paid. Therefore, the ownership of the car still belongs to Danielle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

A purchase order can become a contract between supplier and purchaser if it is…?

A) Received by the supplier
B) Accepted by the supplier
C) Issued by the buyer
D) Edited by the supplier

A

Answer(s): B

Explanation:
A purchase order is a document sent from a buyer to a seller, with a request to order a product. The purchase order often has its number, description and quantity of the goods, unit prices and total price, name of issuer, time of delivery, standard terms and conditions, etc. It is effectively an offer to supplier. The purchase order will become a formal contract if supplier accepted it by written notice or by performance (such as deliver the goods to the buyer’s premise).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

A large company supplies a lot of products. Their shipments are often delayed and customers are not satisfied.
Which of the following KPIs is most likely to be applied to this situation?

A) Technical support
B) OTIF delivery
C) Delay damages
D) Consignment stock availability

A

Answer(s): B

Explanation:
If the deliveries often delay, buyer should use KPI to measure how many missed deliveries there are and the percentage of total missed deliveries on total number of deliveries for period. OTIF (one- time in-full) delivery might help.
Consignment stock availability means that the supplier holds adequate range/number of units of stock to offer a reliable service
Delay damages are the consequences caused by delay of deliveries Technical support is the acceptable quality of technical information/support provided by supplier for goods supplied. LO 2, AC 2.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Which of the following statements is true about model form of contract?

A) When model contracts are employed, there are no requirements for legal advice and input
B) Model contract form’s standard clauses often contain correct legal terminology without recourse to third party experts.
C) The standard clauses of model contract forms give the offeror legal advantages over the offeree
D) Only the publishers of model forms of contract can edit the clauses of these forms

A

Answer(s): B

Explanation:
Model forms of contract are published by some industry or professional organisations such as FIDIC, ITC, CIPS,… These forms are often carefully prepared by legal professionals, with correct legal terminology. The standard clauses within these forms are based on fair and balanced risk/reward allocation between the contracting parties. The model contract forms also include standard clauses to be selected or deleted on an as required basis.
Despite being standardised to be used in any jurisdiction, legal advice may be required if the users decide to make variations to the forms.
The correct answer should be “Model contract form’s standard clauses often contain correct legal terminology without recourse to third party experts.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Rochdale Ltd is looking for a new IT system to automate some of its operations. In designing the specification, procurement manager supposes that it should be done solely by the IT department who have deep expertise on this matter. Is procurement manager’s opinion appropriate?

A) No, because challenging the user’s demand is the role of procurement
B) Yes, because designing complex specification would waste procurement manager’s time
C) Yes, because procurement professional has no expertise in IT sector
D) No, because designing complex specification could only be outsourced

A

Answer(s): A

Explanation:
Procurement professionals have a role in challenging specifications. Technical experts can get things wrong and asking naive questions can be useful in bringing these to light. The challenging may include:
- Does the organisation really need these features/functions?
- With this specification, are there many available suppliers in the market?
- How many does the organisation really need?
etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Blakenall District Hospital (BDH) is a large hospital that is a major part of the government’s health service. Purchasing staff are in the habit of placing many long-term contracts with suppliers and sub- contractors.
Whilst these contracts are usually carried out successfully, prices are often paid that are well over budget. The purchasing manager is concerned to find that, in some cases, members of staff are forcing suppliers to accept fixed price contracts. The policy has caused several problems such as some suppliers refusing to deal with BDH and a few going out of business mid-way through performing a contract with BDH. This is due to fluctuating market prices of materials. The procurement manager suggests supplier to adopt variable pricing arrangement with price index. Is this a right course of action?

A) No, variable pricing would only benefit the suppliers
B) Yes, this type of arrangement would provide absolute certainty when budgeting
C) Yes, this pricing arrangement would reimburse the fluctuation of material prices
D) No, price adjustment should be applied to short-term supply contract only (3-month duration or less)

A

Answer(s): C

Explanation:
Procurement staff in the Hospital is forcing suppliers into fixed price contract. If the costs generally rise, supplier may operate at a loss. This situation can disrupt the relationship, that is the reason why some suppliers refusing to deal with BDH and a few going out of business mid-way. Alternative methods could be variable pricing arrangement. This method would reimburse the fluctuation of market price. It will also benefit buyer if the market price drops. This type of arrangement should be applied to long-term contracts (i.e. 18 months or more).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Which of the following are among five ‘pillars’ of information assurance?
1. Recovery plan
2. Availability
3. Non-repudiation
4. Governance

A) 2 and 3 only
B) 1 and 2 only
C) 1 and 4 only
D) 3 and 4 only

A

Answer(s): A

Explanation:
Information Assurance (IA)
Information Assurance (IA) is the practice of managing information-related risks and the steps involved to protect information systems such as computer and network systems. The IA transformation is a partnership that stretches across the Department of Defense (DoD), Office of National Intelligence, Committee on National Security Systems, National Institute of Science and Technology (NIST), and the Office of Management and Budget. The US Government’s definition of information assurance is:
“measures that protect and defend information and information systems by ensuring their availability, integrity, authentication, confidentiality, and non-repudiation. These measures include providing for restoration of information systems by incorporating protection, detection, and reaction capabilities.”
Information Assurance (IA) is essentially protecting information systems, and is often associated with the following five pillars:
- Integrity
- Availability
- Authentication
- Confidentiality
- Nonrepudiation
The following pillars can be applied in a variety of ways, depending on the sensitivity of the information, or information systems within your organization. Currently, these five pillars are used at the heart of the US Governments ability to conduct safe and secure operations in a global environment.
1. Integrity
Integrity involves assurance that all information systems are protected and not tampered with. IA aims to maintain integrity through means such as anti-virus software on all computer system, and ensuring all staff with access to know how to appropriately use their systems to minimize malware, or viruses entering information systems.
2. Availability
Availability simply means those who need access to information, are allowed to access it. Information should be available to only those who are aware of the risks associated with information systems.
3. Authentication
Authentication involves ensuring those who have access to information, are who they say they are. Ways of improving authentication involve methods such as two-factor authentication, strong passwords, bio-metrics and other devices. Authentication may also be used to not only identify users, but also other devices.
4. Confidentiality
IA involves the confidentiality of information, meaning only those with authorization may view certain data. This step is closely mirrored by the six data processing principles of the General Data Protection Regulation (GDPR), where by personal data must be processed in a secure manner “using appropriate technical and organizational measures” (“integrity and confidentiality”).
5. Nonrepudiation
The final pillar simply means someone with access to your organizations information system cannot deny having completed an action within the system, as there should be methods in place to prove that they did make said action.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Which of the following is a true statement on express and implied terms?

A) Express terms always take precedent over implied terms
B) Implied terms may derive from oral negotiations
C) Express terms must always be in writing
D) Express terms must be prepared by the party with expert knowledge

A

Answer(s): B

Explanation:
Express terms are the terms of the agreement which are expressly agreed between the parties. Ideally, they will be written down in a contract between the parties but where the contract is agreed verbally, they will be the terms discussed and agreed between the parties. Implied terms are terms implied into the contract by the courts. They are not expressly set out in the contract but are taken to be as effective as if they were and as if they had been included from day one of the contract. The express terms and any implied terms together create the legally binding obligations on the parties.
The types of express terms to be found in a contract are many and varied and will depend on the type of contract. Any term written into the contract is an express term and may refer to price, time scales, warranties and indemnities, limitations on liability, conditions precedent and so on. An implied term is a term which the courts imply into a contract because it has not been expressly included by the parties. This may be because the parties did not consider it, did not think that any problem would arise in relation to it or simply omitted to include it. The courts are very reluctant to imply terms into contracts and will only do so in the following circumstances:
1. terms implied under statute
2. terms implied under common law
3. terms implied because of custom or usage
4. terms implied due to previous dealings
5. terms implied `in fact’ or to reflect the parties’ intentions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Which of the following is most likely to reduce ITT preparation time while maintaining the clarity of tendering documents?

A) Using request for quotation
B) Standardising documentation whenever possible
C) Monitoring usage
D) Eliminating pre-qualification stage from all tendering processes

A

Answer(s): B

Explanation:
One of the major disadvantages of tendering process is that it is lengthy, bureaucratic and slow. To reduce the preparation time, buying organisation can:
- Plan forward
- Standardise tendering documents (such as notices, terms and conditions,…) whenever possible
- Train procurement staff
- Write down policies for tender-waiver
Buying organisation should not eliminate the pre-qualification stage from all tendering processes. This stage is used as a filter to select the most competent suppliers for next stage in restricted tendering. To save time in this process, you can design a model questionnaire.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What is the purpose of using key performance indicators in procurement and supply?

A) To validate the supplier’s bid or tender
B) To monitor supplier’s performance
C) To ease the termination process
D) To qualify which supplier is suitable

A

Answer(s): B

Explanation:
Procurement teams use key performance indicators (KPIs) to ensure vendors comply with (and hopefully exceed) the obligations outlined in a contract. They help us better understand suppliers’ performance, measure their output over a long period of time, and identify areas where improvement is needed.
Put simply, it’s good business sense to make sure you’re actually getting what you’ve paid for. This might be as straightforward as confirming a product or service is delivered on time, which means the KPIs you need to use will be minimal and basic.

26
Q

Infra Constructions receive a contract for construction of a building, and following terms were agreed upon. “The entire cost of the project will be reimbursed to Infra Constructions (estimated cost of the project being $ 25 million). The profits will be 20% of the entire cost of a project subject to a max of $ 5 million.” This arrangement is an example of…?

A) Incentive pricing arrangement
B) Gain-share/pain-share arrangment
C) Cost-plus pricing arrangement
D) Fixed-pricing arrangement

A

Answer(s): C

Explanation:
In the contract term, the buyer agrees to pay the contractor the cost of doing project plus a profit.
This is an example of cost-plus pricing arrangement.
On the other hand, “Fixed-pricing arrangement” often refers to lump-sum contract or supply/service contract with fixed price. “Incentive pricing arrangement” and “Gain-share/pain-share arrangement” have the same meaning. In this type of arrangement, both supplier and buyer agree on a target (it can be cost, or lead time, or quality, etc). Once the supplier reaches that target, it will be rewarded with a portion of the gain that the buyer gets, and will pay the price if it fails.

27
Q

Which of the following are most likely to be liabilities of suppliers under a guarantee clause? Select

TWO that apply
A) Repair
B) Decommissioning
C) Upgrading
D) Replacement
E) Installation

A

Answer(s): B,E

Explanation:
A guarantee is an agreement given by a trader to a consumer, without any extra charge, to repair, replace or refund goods that do not meet the specifications set out in the guarantee. A guarantee is usually issued by the manufacturer of goods or by a trader that provides goods as part of a service - replacement windows, for instance. Generally, a guarantee provider undertakes to carry out free repairs, for a set period of time, for problems that can be attributed to manufacturing defects.

28
Q

Which of the following is the international standard for labelling hazardous substances?

A) GPS
B) HSE
C) CODEX STAN 1-1985
D) GHS

A

Answer(s): D

Explanation:
GHS stands for the Globally Harmonized System of Classification and Labelling of Chemicals. GHS defines and classifies the hazards of chemical products, and communicates health and safety information on labels and safety data sheets). The goal is that the same set of rules for classifying hazards, and the same format and content for labels and safety data sheets (SDS) will be adopted and used around the world. An international team of hazard communication experts developed GHS. The Global Positioning System (GPS), originally NAVSTAR GPS, is a satellite-based radionavigation system owned by the United States government and operated by the United States Space Force. It is one of the global navigation satellite systems (GNSS) that provides geolocation and time information to a GPS receiver anywhere on or near the Earth where there is an unobstructed line of sight to four or more GPS satellites. Obstacles such as mountains and buildings block the relatively weak GPS signals.
CODEX STAN 1-1985 is general standard for the labelling of packaged goods. Environment (E), health (H) and safety (S) (together EHS) is a discipline and specialty that studies and implements practical aspects of environmental protection and safety at work. In simple terms it is what organizations must do to make sure that their activities do not cause harm to anyone.

29
Q

Which of the following can be considered as implied terms in a contract?
1. Case law
2. Statute
3. Trade custom
4. A term can never be implied, it must always be expressed by the parties

A) 1,3 and 4 only
B) 1, 2 and 3 only
C) 1, 2 and 4 only
D) 2, 3 and 4 only

A

Answer(s): B

Explanation:
An implied term is a term which the courts imply into a contract because it has not been expressly included by the parties. This may be because the parties did not consider it, did not think that any problem would arise in relation to it or simply omitted to include it. The courts are very reluctant to imply terms into contracts and will only do so in the following circumstances:
1. terms implied under statute
2. terms implied under common law
3. terms implied because of custom or usage
4. terms implied due to previous dealings
5. terms implied `in fact’ or to reflect the parties’ intentions

30
Q

Which of the following is an invitation to treat?

A) Purchase order
B) Invoice
C) Price list
D) Tender bid

A

Answer(s): C

Explanation:
An invitation to treat is an action inviting other parties to make an offer to form a contract. These actions may sometimes appear to be offers themselves, and the difference can sometimes be difficult to determine. The distinction is important because accepting an offer creates a binding contract while “accepting” an invitation to treat is actually making an offer. One simple test to distinguish an offer and an invitation to treat is to ask what this statement will become when it is accepted. Now we apply this test to four options:
- Tender bid: Tender bid is submitted by a supplier to an invitation to tender from the buyer. It states the specific quantity, price and other elements. If buyer accepts the bid, there will be a contract between them. Therefore, a tender bid is an offer.
- Purchase order: Purchase order which is sent by a buyer will state the items, the quantity, the price and terms and conditions. If supplier accepts the purchase order, there will also be a contract between two parties. It is also an offer.
- Price list: Price list is prepared by a supplier. The price list often states the items and unit price. If a buyer accepts it, the contract has not yet been formed since the contract scope has not yet been decided. It is an invitation to treat.
- Invoice: Invoice is often sent after a contract is formed. It is in fact a request for payment, neither offer nor invitation to treat.

31
Q

When a supplier signs an insurance policy with an insurance company, which of the following is transferred to insurance company?

A) Right
B) Risk
C) Legal responsibility
D) Contractual obligation

A

Answer(s): B

Explanation:
An insurance policy transfers a specific set of risks such as the fire and flood risk for a particular asset. The legal liability does not transfer to the insurance company (known as insurer).

31
Q

According to rule of contract formation, which of the following is a valid acceptance?

A) The person orally agrees to pay the offered price
B) The person states that she is able to pay the offered price
C) The person asks for a lower price
D) The person says that she will think about it overnight

A

Answer(s): A

Explanation:
Once a valid acceptance takes place, a binding contract is formed. It is therefore important to know what constitutes a valid acceptance in order to establish if the parties are bound by the agreement.
There are three main rules relating to acceptance:
1. The acceptance must be communicated to the offeree.
2. The terms of the acceptance must exactly match the terms of the offer.

  1. The agreement must be certain.
    Among the answers:
    “The person says that she will think about it overnight” does not match the terms of the offer. The offeree does not assure that she will accept the offer. “The person asks for a lower price”: This is a counter-offer. “The person states that she is able to pay the offered price” is not certain. The offeree merely provides information on her financial ability.
32
Q

Which of the following best defines an `express’ term in general contract arrangements?

A) It is a standard set of terms and conditions published by CIPS
B) It is not necessarily discussed by the parties, but nonetheless forms part of the contract
C) It is the term that is added to the contract by the law or based upon the facts of the case.
D) It is clearly agreed between the parties, and is virtually always written down in the contract

A

Answer(s): D

Explanation:
Express terms are the terms of the agreement which are expressly agreed between the parties. Ideally, they will be written down in a contract between the parties but where the contract is agreed verbally, they will be the terms discussed and agreed between the parties. Implied terms are terms implied into the contract by the courts. They are not expressly set out in the contract but are taken to be as effective as if they were and as if they had been included from day one of the contract. The express terms and any implied terms together create the legally binding obligations on the parties.

33
Q

A tire manufacturer entered into a contract with a distributor. In the contract, the distributor is prohibited from selling the tire under the price list. The distributor must pay $5 for each tire sold in breach. The amount of $5 is known as…?

A) Penalty
B) Quantum meruit
C) Liquidated damages
D) Caveat Emptor

A

Answer(s): C

Explanation:
This scenario is in fact based on a famous case law: Dunlop Pneumatic Tyre Company v New Garage & Motor co [1915] AC 79. In this case law, the House of Lords identified the clause as liquidated damages, and therefore enforceable.
However, if this case had happened in 2015 or afterwards, there would be some legal issues:
- The price agreement is prohibited by Competition Act 1998
- If the agreement is allowed by Competition Act, as in the case Cavendish Square Holding BV (Appellant) v Talal El Makdessi (Respondent), the clause can also be identified as a penalty and it is still enforceable.

33
Q

Which of the following are the ‘fundamental’ labour standards laid down by the International Labour Organisation?
1. Elimination of child labour
2. Payment of a minimum wage
3. The right to collective bargaining
4. Abolition of forced labor

A) 1, 2 and 4 only
B) 2, 3 and 4 only
C) 1, 3 and 4 only
D) 1, 2 and 3 only

A

Answer(s): C

Explanation:
ILO Declaration on Fundamental Principles and Rights at Work was adopted in 1948. The Declaration commits Member States to respect and promote principles and rights in four categories, whether or not they have ratified the relevant Conventions.
These categories are: freedom of association and the effective recognition of the right to collective bargaining, the elimination of forced or compulsory labour, the abolition of child labour and the elimination of discrimination in respect of employment and occupation.

33
Q

Which of the following is likely to reduce risks of different rules regarding when offers and acceptance become effective between legal systems?

A) Withdrawal protocol
B) Letter of intent
C) Time lapse
D) Deemed receipt protocol

A

Answer(s): D

Explanation:
Regarding rule of offer and acceptance, there are some differences among legal system around the world. For example, mailbox rule is generally applied in common law countries such as UK, US, Australia,.. while it is ignored in civil law countries. To clarify on rule of offer and acceptance in international trade, offerors may use expressed terms in their offers. These terms known as deemed receipt protocol.

34
Q

A senior procurement specialist in UK is preparing a specification in which ISO standards are used to send to global suppliers. Is this action appropriate?

A) No, the procurement specialist must use BSI standards instead
B) Yes, evert specification must have ISO standards
C) Yes, ISO standards are globally recognisable
D) No, ISO standards are unfamiliar to global suppliers

A

Answer(s): C

Explanation:
ISO standards are internationally agreed by worldwide experts. They overcome countries’ differences and facilitate global trade. If a buying organisation is sourcing globally, they should use ISO standards within the specification.

34
Q

Which of the following is the best definition of “ultra vires”?

A) Beyond powers
B) In good faith
C) From one party
D) Let the buyer beware

A

Answer(s): A

Explanation:
Ultra vires is a Latin phrase, meaning “beyond the powers.” Describes actions taken by government bodies or corporations that exceed the scope of power given to them by laws or corporate charters.
When referring to the acts of government bodies (e.g., legislatures), a constitution is most often the measuring stick of the proper scope of power.

35
Q

Company A based in Canada signed a commercial contract with Company B in Egypt. Both countries are Contracting States to Vienna Convention on Contracts for the International Sale of Goods. The contract states that “The validity, interpretation, construction and performance of this Agreement shall be governed by the laws of Canada”.
Which of the following set of rules will be applied if dispute between contracting parties occurs?

A) CISG
B) Canada’s legal system
C) WTO rules
D) Egypt’s legal system

A

Answer(s): B

Explanation:
Where the sale of goods is between two businesses in different Contracting States, then it is international and the CISG rules of law automatically apply unless they have been excluded. A contract clause stating that the contract is subject to the legal systems and courts of a particular country overrides or excludes the CISG rules, since the local rules of that country would apply instead.
So the answer should be Canada’s legal system.

36
Q

A procurement professional is drafting payment terms for a commercial contract. He is considering about payment method if defective products are found.
Which of the following should be embedded in payment terms to control this issue?

A) Remedies for late payment
B) Pay-less notice
C) Invoice preparation
D) Retention clause

A

Answer(s): D

Explanation:
Retention money is the payment for a service or product that is withheld pending the completion of some specified condition. For example, buyer may withhold the amount due until the supplier replace all defective goods.
Pay-less notice is the notice under a contract which states that the invoice will only be partially paid because of some issues such as supplier has to pay the damages. Remedies for late payment are remedies that supplier may seek when a buyer pay it later than the stated payment terms. Normally, the buyer will be charged an interest rate.

36
Q

A fashion company is drafting a specification for an order in next year. The company wants to expand its supply base in low cost countries. The procurement department is considering applying standard ISO 3759 on method for the preparation, marking and measuring of textile fabrics, garments and fabric assemblies for use in tests for assessing dimensional change after a specified treatment.
Which of the following should be taken into account when embedding this standard into the specification?

A) Date of publication
B) Supplier selection
C) Type of specification
D) Legality

A

Answer(s): A

Explanation:
Standards are incorporated into specifications by simply cross-refering to the relevant standard by its number and date of publication. It is important to include the date of publication. All standards are reviewed from time to time and their content changes. The absence of the publication date will lead to disrupts over which version of the standard actually applies to the contract.

36
Q

MWB operates serviced offices in central London. Rock entered a contractual licence with MWB to occupy office space in Marble Arch and had accumulated licence fees in arrears. The original licence agreement contained a `No Oral Modification’ clause that said: ‘All variations to this licence must be agreed, set out in writing and signed on behalf of both parties before they take effect’. After 6 months, Rock director re-negotiated to extend payment period over phone call and MWB credit controller agreed his proposal. Is this agreement considered as an effective variation to the original licence agreement?

A) Yes, because parties who agree to altering the original contract orally despite a `No Oral.
B) Modification’ clause, must have intended to dispense with the clause
C) No, because the mechanism for variation has been set out in the original contract
D) Yes, because the credit controller had agreed with Rock director’s proposal
E) No, because Rock director assumed that the variation was effective and convinced credit controller to believe it

A

Answer(s): C

Explanation:
The license can be amended during its lifespan. However, in this case, it already has a clause allowing for mechanism of variation which sets out who can authorise changes and prohibits any oral variation. Therefore, the agreement between Rock’s director and MWB credit controller is not an effective variation to the license.

36
Q

Which of the following should be done by procurement professionals right after obtaining a pre- written specification for a critical item so that the added value will be the greatest?

A) Evaluate tender or quotation
B) Select the best supplier
C) Challenge the used specification
D) Issue invitation to tender or request for quotation

A

Answer(s): C

Explanation:
A previously used specification must always be robustly challenged to see how well it fits the proposed circumstances. Aspects which appear not to fit should be analysed to understand why they were included in the sample specification and whether this changes the view on whether or not they should be omitted or changed.

36
Q

Which of the following is most likely to be an one-off contract?

A) Franchise Agreement
B) Framework Agreement for supply of mono-crystalline silicon
C) Contract for construction of a power plant
D) Commercial lease agreement of an office building

A

Answer(s): C

Explanation:
One-off contracts are used where a supplier is only needed for a single activity unlikely to be repetitive, and where the need of the buyer is concrete and finite. Among the answers, only construction for power plant is one-off since the work is non-repetitive and the need is clearly defined.
A framework agreement is an agreement between one or more businesses or organisations, “the purpose of which is to establish the terms governing contracts to be awarded during a given period, in particular with regard to price and, where appropriate, the quantity envisaged”. A Commercial Lease Agreement is a contract used when renting business property to or from another individual or company. It gives the tenant (or renter) the right to use the property for business purposes during the term of the lease in exchange for payment to the landlord. A franchise agreement is a legally binding document that outlines a franchisor’s terms and conditions for a franchisee. Every franchise is governed by these terms, which are generally outlined in a written agreement between both parties.

36
Q

Which of the following may be a benefit for purchaser in using call off contract?

A) Ability to discover new potential suppliers
B) No long-term commitment required
C) Secured supply
D) Maintaining a degree of competition between suppliers

A

Answer(s): C

Explanation:
Benefits for the purchaser in using call off contract are as below:
- The benefit of a call off contract is that they allow the supply of materials, goods and services to be secured over multiple delivery dates across the length of a project.
- Agreed prices, either fixed or pre-agreed mechanism for adjustment. This helps with setting and controlling budgets.
- Simple order mechanisms at the point of need
- Schedules of rates pricing enables electronic procure-to-pay systems, which gives greater control and visibility of spend
- The value of spend ad length of contract justify the cost of proper market engagement and tender or negotiation processes resulting in better value for money
- The longer the contract, the greater the opportunities for aligning working practices to create joint efficiency.

37
Q

Royal Naval Hospital at Rockstown, Anyport manages a fleet of nine ambulance vehicles. During busy periods, it becomes very difficult to keep track of the location of each ambulance (and the nature of their journey). Continual problems lead to the proposal for a new control system (ERNS). For this ERNS project, the procurement department has drafted a specification in which only a bullet point list of basic requirements was written down. The procurement manager understands that the specification should be developed more specifically but a cross functional team from the Hospital could not do that. A senior buyer suggests that some of Hospital’s pre-qualified suppliers could support them in developing the specification.
Which of the following should be a priority approach of procurement department in developing dialogue with those suppliers about specification development?

A) Internal discussion
B) General networking
C) One-to-one meeting with the suppliers
D) Request for quotation from the suppliers

A

Answer(s): C

Explanation:
The procurement team has drafted basic requirements in the specification. They will need to develop it further and more specific. Developing market dialogue with supplier is a good solution. There are number of approaches which can be taken to engage with suppliers:
- General meetings: buyer meets supplier at a networking event (such as trade show) or social media. These discussions are unlikely to deliver very specific information.
- One-to-one meetings: This will be most likely to deliver direct input into specification development and supplier-specific product development information.
- Group visits
- Meet-the-buyer events
- Formal negotiations or competitive
The answer for this QUESTION should be One-to-one meeting.

38
Q

When a contract has been agreed on the basis of a fraudulent misrepresentation, which of the following remedies are available?

A) Damages only
B) Rescission only
C) An injunction only
D) Both damages and rescission

A

Answer(s): D

Explanation:
An untrue statement of fact or law made by Party A (or its agent) to Party B, which induces Party B to enter a contract with Party A thereby causing Party B loss. An action for misrepresentation can be brought in respect of a misrepresentation of fact or law.
There are three types of misrepresentation:
- Fraudulent misrepresentation: where a false representation has been made knowingly, or without belief in its truth, or recklessly as to its truth.
- Negligent misrepresentation: a representation made carelessly and in breach of duty owed by Party A to Party B to take reasonable care that the representation is accurate. If no “special relationship” exists, there may be a misrepresentation under section 2(1) of the Misrepresentation Act 1967 where a statement is made carelessly or without reasonable grounds for believing its truth.

  • Innocent misrepresentation: a representation that is neither fraudulent nor negligent. The remedies for misrepresentation are rescission and/or damages. For fraudulent and negligent misrepresentation, the claimant may claim rescission and damages. For innocent misrepresentation, the court has a discretion to award damages in lieu of rescission; the court cannot award both (see section 2(2) of the Misrepresentation Act 1967). For more information, see Practice note, Misrepresentation.
39
Q

Which of the following is an agreement between service provider and user that quantifies the minimum quality of service?

A) Service charter
B) Service guarantee
C) SLA
D) Service standard

A

Answer(s): C

Explanation:
A service-level agreement (SLA) is a commitment between a service provider and a client. Particular aspects of the service ­ quality, availability, responsibilities ­ are agreed between the service provider and the service user. The most common component of an SLA is that the services should be provided to the customer as agreed upon in the contract. A customer service charter is a document that outlines how an organization promises to work with its customers along with providing insights into how an organization operates. A service guarantee is a marketing tool service firms have increasingly been using to reduce consumer risk perceptions, signal quality, differentiate a service offering, and to institutionalize and professionalize their internal management of customer complaint and service recovery.

40
Q

Which of the following is the type of insurance that cover the liabilities of service provider such as legal advice, accountancy, technical designs, etc?

PII
Product liability
Employer’s liability
Public liability

A

Answer(s): A

Explanation:
The most usual forms of insurance cover are as below:
- Employer’s liability: Employers’ liability insurance, sometimes known as employment practices liability insurance (EPLI), protects employers from financial loss if a worker has a job-related injury or illness not covered by workers’ compensation. Employers’ liability insurance can be packaged with workers’ compensation insurance to further protect companies against the costs associated with workplace injuries, illnesses, and deaths. Employers’ liability insurance is also called “part 2” of a workers’ compensation policy.
- Public/product liability: Public liability insurance covers you against any claims made against your business ­ for example if you were held legally liable for personal injury, or for damage done to property. The insurance will also cover you for any legal costs associated with defending claims against your business.

  • Professional indemnity insurance (PII): Professional indemnity or liability insurance offers such coverage to professional advice or service providing individuals and companies ensuring protection against any legal costs and damages awarded as a result of claims relating to negligence.
    Whereas more general forms of liability insurance focus on direct forms of harm such as sustaining injuries, professional indemnity insurance provides a far more detailed and comprehensive form of coverage. The cover protects a firm or individual’s liability relating to any financial loss caused by errors or omissions in the service provided as well as any alleged failure to perform on behalf of a client.
  • Goods in transit coverage: Goods in transit insurance, sometimes referred to as GIT, covers goods against loss or damage while being moved from one place to another. These goods can be being carried by individuals in their own vehicle, self employed drivers or contractors or by third party carriers. The insurance can cover both domestic and international trips, with specific add-ons available for insurance within Europe.
41
Q

Standard terms and conditions should become the governing terms for which group of items?

A) Leverage items
B) Bottleneck items
C) Strategic items
D) Routine items

A

Answer(s): D

Explanation:
Standard terms and conditions are set of terms that is prepared by an organisation. These terms can become the governing terms in low-value, low-risk transactions (or Routine items according to Kraljic’s portfolio model). They can be a reference when negotiating for more important contract.

42
Q

XYZ Ltd and Engineer Corp signed a long-term supply contract in which both parties had agreed on performance targets. Recently, due to increased customer demands, XYZ Ltd realises that they should make changes to the contract with Engineer Corp with regards to performance management. These changes are approved and signed by both the buyer and seller. The changes to the contract are known as…?

A) An amendment to the prime contract
B) A stand-alone subcontract to the prime contract
C) An appendix to the prime contract
D) A separate counter-offer to the supplier

A

Answer(s): A

Explanation:
The changes are made to the prime contract. They are also signed and approved by both parties. These changes are known as amendment (variation) to the contract. A contract amendment allows the parties to make a mutually agreed-upon change to an existing contract. An amendment can add to an existing contract, delete from it, or change parts of it. The original contract remains in place, only with some terms altered by way of the amendment.

43
Q

Information assurance protects information systems and…?

A) Hard copy
B) Computers
C) Inventory
D) People

A

Answer(s): B

Explanation:
Information Assurance (IA) is the practice of managing information-related risks and the steps involved to protect information systems such as computer and network systems. The IA transformation is a partnership that stretches across the Department of Defense (DoD), Office of National Intelligence, Committee on National Security Systems, National Institute of Science and Technology (NIST), and the Office of Management and Budget. The US Government’s definition of information assurance is:
“measures that protect and defend information and information systems by ensuring their availability, integrity, authentication, confidentiality, and non-repudiation. These measures include providing for restoration of information systems by incorporating protection, detection, and reaction capabilities.”

44
Q

A company needs to source a product from overse

It wants to overcome technical barrier to cross-border trade by using standards in the specification.
Which of the following is most likely to be incorporated into that specification?
A) National standards
B) Company standards
C) Brands
D) International standards

A

Answer(s): D

Explanation:
Exporting enterprises must sometimes incur additional costs as they adapt their production to the changing legal requirements of the recipient country. Such requirements can thus create technical barriers to trade. Discrepancies between product rules adopted by different countries can involve numerous aspects: weight, size, packaging, ingredients, mandatory labeling, shelf-life conditions, testing and certification procedures etc.
One way to overcome these barriers is to adopt international standards. Overseas companies may be more familiar with international standards without looking at specific regulations of importing countries.

45
Q

A retailer prefers to display its best selling products and promotion programme on the building windows. According to rule of contract formation, this act will generally constitute…?

A) An invitation to treat
B) A legal capacity
C) An offer
D) A mailbox rule

A

Answer(s): A

Explanation:
Fisher v Bell [1960] and Pharmaceutical Society of Great Britain v Boots Cash Chemists [1953] identified that the courts will generally consider goods advertised in shop windows or those with a price tag attached to constitute an invitation to treat. An invitation to treat is a concept in contract law. It refers to an invitation for a party to make an offer enter into contractual negotiations. Invitations to treat can be anything displayed to a large number of people, as long as there is no defined way to choose who can accept. Items on display in a shop, advertisements, and catalogues are all common examples of invitations to treat.
However, there are cases in the US shows that under some circumstances an advertisement can become an offer (see Leftkowitz v Great Minneapolis Surplus Stores [1957]).

46
Q

Which of the following is the contract provision that relieves the parties from performing their contractual obligations when certain circumstances like natural disasters, terrorist attacks, etc arise?

Options:
A.
Indemnity clause

B.
Liquidated damage clause

C.
Insurance clause

D.
Exclusion clause

A

Answer:
D
Explanation:
Explanation:
The contract provision that relieves the parties from performing their contractual obligations when certain circumstances like natural disasters, terrorist attacks, etc arise is called Force majeure. Force majeure is an example of exclusion clause.

An exemption clause in a contract is a term which either limits or excludes a party’s liability for a breach of contract. In order for an exclusion clause to be binding and operable upon the parties, the clause must:

  1. The clause must be incorporated into the contract as a term.
  2. The clause must pass the test of construction.
  3. The clause must not be rendered unenforceable by the statutory provisions in the Unfair Contract Terms Act 1977 or the Consumer Rights Act 2015 (enacting the Consumer Rights Bill 2013-14).

Reference: [Reference:, - Exclusion Clauses Lecture, - CIPS study guide page 149, LO 3, AC 3.2]

47
Q

You are to do the KPIs and targets for international supplier and the following was done

  1. Delivery in an hour
  2. Return orders in an hour

Is that a good thing or not?

Options:
A.
Yes, because these targets will propel the suppliers to continuous improvement

B.
No, the local suppliers are always the best choice

C.
No, because the KPIs are not a realistic and justified

D.
Yes, the higher the targets are, the better the outcomes will be

A

Answer:
C
Explanation:
Explanation:
KPIs and the targets for supplier should be SMART:

  • Specific: What exactly do you want to achieve?
  • Measurable: How will you identify that you have achieved your goal?
  • Achievable: Is your goal really attainable?
  • Relevant: Is it relevant to you or, in other words, does it align with where you want to be?
  • Time-bound (or timely): When will you deliver your goal, and what are the key milestones?

The two KPIs (Delivery in one hour, Return orders in one hour) are not realistic and achievable for international suppliers. Therefore, you should not put such high targets for supplier.

48
Q

A procurement professional is preparing a sale & purchase contract of a machinery. Which of the following clauses should be added to the contract? Select TWO that apply

Options:
A.
Supplier selection mechanism

B.
Insurance requirements

C.
Period of hire

D.
Ratio decidendi

E.
Guarantees

A

Answer:
B, E
Explanation:
Explanation:
The complexity of the contract will reflect the complexity of the purchase. For simple, low-value purchases, standard terms and conditions may be all that is required, but do not assume that just because the purchase is one-off, the contract will be simple. It may still need to cover the following areas:

  • Warranties and guarantees if the one-off purchase has a considerable life-span and is business-critical (e.g., a back-up generator for the office which houses the national computer servers).
  • Insurance requirements: including professional indemnity, public/products liability, employer’s liability, and cover for any specific risks such as pollution or working at height.
  • Specification requirements on quality, timing and delivery
  • Minimum quality standards on the business operation (e.g., a catering provider might only be providing sandwiches for a team meeting lunch, but you still need to know its hygiene practices).
  • Built-in change process for any goods or services that are beyond very simple (e.g., works contracts always have variations procedures because of the unpredictable nature of such projects).
  • Ability to extend the scope of the contract should be minimal or none, and restrained to the single requirement.
  • Ability to extend the duration of the contract should be limited to the ability to accommodate unexpected time overruns (which itself should be subject to a damages/penalty provision where they are attributable to the supplier, and an extension to overheads costs where they are attributable to the purchaser).
  • Data security protocols need to be considered if personal data is being shared.
49
Q

Michelle contacts Hannah and asks her if she would be interested in purchasing her car for £2000. Hannah immediately takes £2000 to Michelle and says she wants to buy the car. Michelle subsequently refuses to proceed. Has the contract between Michelle and Hannah been made?

Options:
A.
No, because Michelle has rejected Hannah’s offer on buying the car

B.
Yes, because both parties have full legal capability to enter into a contract

C.
Yes, by her performance Hannah has accepted Michelle’s offer on selling the car

D.
No, because by refusing to proceed, Michelle rejects Hannah’s counter-offer

A

Answer:
A
Explanation:
Explanation:
To solve the question, you must distinguish the following notion:

  • Offer: The case of Storer v Manchester City Council [1974] 1 WLR 1403 outlines that an offer is: An expression of willingness to contract on specified terms, with the intention that it is to be binding once accepted
  • Acceptance: in order for a contract to be formed, the offer must be accepted. Acceptance represents the meeting of the minds of the parties to the contract – both agree to exchange something for the other (payment, services, goods, etc.).
  • Counter offer: is an offer made in response to a prior offer.
  • Invitation to treat: An important distinction to make in contract law is that between an offer and an invitation to treat. An invitation to treat is usually an invitation for another party to make an offer. It may also be defined as an indication that a party is open to negotiation.

Here are some key distinctions of offers and invitation to treats.

Offer:

  • Certain promise to be bound
  • Clear and specified terms
  • The conduct or words of the party show certainty
  • There is no room for negotiation

Invitation to treat:

  • There is room for negotiation
  • There is an invitation for offers
  • There is a request for information
  • Lack of certainty

In the scenario above, initially Michelle just gives an invitation to treat because she is asking whether Hannah is interested to buy her car (request for information from Hannah). Hannah may reject or go into a negotiation with Michelle. Then, Hannah makes an offer by taking the money and shows her intention to be legally bound. At this point, when Hannah’s offer is present, Michelle can accept or reject. When she rejects, the contract is not formed. The answer must be “No, because Michelle has rejected Hannah’s offer on buying the car”.

50
Q

Which of the following clauses addresses fraud, bribery and corruption?

The Company has undertaken commercially reasonable efforts to eliminate Conflict Minerals from each Company Product and any products currently proposed to be manufactured by the Company or on its behalf in the future. “Conflict Minerals” means columbite-tantalite (coltan), cassiterite, gold, wolframite, or their derivatives, which originate in the Democratic Republic of the Congo or other country the exploitation and trade of which is determined by the United States to be financing conflict in the Democratic Republic of the Congo or other country.

Options:
A.
Customer will be responsible for and shall ensure that while Service Provider employees, agents or contractors are on Customer’s premises, all proper and legal health and safety precautions are in place and fully operational to protect such persons.

B.
Nothing in this Agreement shall prevent a Party from utilizing the services of any subcontractor as it deems appropriate to perform its obligations under this Agreement; provided, however, that each Party shall require its subcontractors to comply with all applicable terms and conditions of this

C.
Agreement in providing such services and each Party shall remain primarily liable to the other Party for the performance of such subcontractor.

D.
Each Party hereby undertakes that, at the date of the entering into force of the Contract, itself, its directors, officers or employees have not offered, promised, given, authorized, solicited or accepted any undue pecuniary or other advantage of any kind in any way connected with the Contract and that it has taken reasonable measures to prevent subcontractors, agents or any other third parties, subject to its control or determining influence

A

Answer:
D
Explanation:
Explanation:
This question is intended to let students know about how contractual clauses regarding ethical issues is constructed. The exam paper may not ask about this.

“Each Party hereby undertakes that, at the date of the entering into force of the Contract, itself, its directors, officers or employees have not offered, promised, given, authorized, solicited or accepted any undue pecuniary or other advantage of any kind in any way connected with the Contract and that it has taken reasonable measures to prevent subcontractors, agents or any other third parties, subject to its control or determining influence, from doing so.”: This is a clause addressing fraud, bribery and corruption. It is created to prevent any undue act by contracting parties. You may find other anti-corruption clause samples in this document.

“Nothing in this Agreement shall prevent a Party from utilizing the services of any subcontractor as it deems appropriate to perform its obligations under this Agreement; provided, however, that each Party shall require its subcontractors to comply with all applicable terms and conditions of this Agreement in providing such services and each Party shall remain primarily liable to the other Party for the performance of such subcontractor.”: This clause is used to control the subcontracting and subcontractors.

“Customer will be responsible for and shall ensure that while Service Provider employees, agents or contractors are on Customer’s premises, all proper and legal health and safety precautions are in place and fully operational to protect such persons.”: This clause is used to ensure health and safety standards.

“The Company has undertaken commercially reasonable efforts to eliminate Conflict Minerals from each Company Product and any products currently proposed to be manufactured by the Company or on its behalf in the future. “Conflict Minerals” means columbite-tantalite (coltan), cassiterite, gold, wolframite, or their derivatives, which originate in the Democratic Republic of the Congo or other country the exploitation and trade of which is determined by the United States to be financing conflict in the Democratic Republic of the Congo or other country.”: This is a clause addressing conflict minerals.

51
Q

Nestle gave away records of “Rockin’ Shoes” or a voucher to people who sent in three wrappers from Nestle’s 6d. milk chocolate bars as well as 1s 6d. Which of the following were the consideration of Nestle’s customer? Select TWO that apply

Options:
A. Three wrappers

B. 1s 6d

C. “Rockin’ Shoes” record

D. The voucher

E. Milk chocolate bar

A

Answer:
A, B
Explanation:
Explanation:
Consideration is one thing given in exchange for another.

In this case, considerations of customers are three wrappers and 1s6d. Consideration of Nestle is Rockin’ Shoes record or a voucher.

52
Q

To expand its operation, Steel Co. decides to build a new plant. Despite of excitement, the senior management is very concerned about the complexity and risks of such project. Hugo, the procurement manager, suggests that the company can adopt a model form of contract. What is the advantage of using model form of contract?

Options:
A. It shifts the balance of power in the favour of the buyer rather than the contractor

B. The company could avoid the need to draft a complex contract from blank

C. Model form of contract eliminates the need for legal advice totally

D. The company does not need to draft the drawings as well as specification anymore

A

Answer:
B
Explanation:
Explanation:
Advantages and Disadvantages of using model form contracts.

Model form contracts save a lot of time and money. They are written by industry experts and the buyers and suppliers both understand what is included in the contract.

They are mainly used in Construction and term maintenance contacts. Typical ones are JCT and NEC.

Without the use of model form contracts the buyer and supplier will take a long time to write the terms, negotiate and finalise the contract.

This is time and money wasted.

However, model form contracts require buyers and suppliers to have training so you understand them.

Finally, if you are a buyer in a powerful position you cannot exploit that with a model form contract as these are written for mutual benefit.

53
Q

Which of the following are likely to be express terms in a contract?

  1. Legislation
  2. Custom and practice
  3. Contract particulars
  4. Terms and conditions

Options:
A. 2 and 3 only

B. 1 and 4 only

C. 3 and 4 only

D. 1 and 2 only

A

Answer:
C
Explanation:
Explanation:
Express terms are the terms of the agreement which are expressly agreed between the parties. Ideally, they will be written down in a contract between the parties but where the contract is agreed verbally, they will be the terms discussed and agreed between the parties.

The types of express terms to be found in a contract are many and varied and will depend on the type of contract. Any term written into the contract is an express term and may refer to price, time scales, warranties and indemnities, limitations on liability, conditions precedent and so on.

54
Q

Which of the following is the best definition of consideration in contract law?

Options:
A. Full statement about something to provide

B. The act of thinking carefully about one thing

C. One thing given in exchange

D. Formal discussion between people who are trying to reach an agreement

A

Answer:
C
Explanation:
Explanation:
A simple definition of consideration is as follows – an exchange between the parties which results in a benefit to one party, and a detriment to the other. The case of Currie v Misa (1874) LR 10 Ex 153 provides an apt description of this:

“A valuable consideration, in the sense of the law, may consist either in some right, interest, profit, or benefit accruing to the one party, or some forbearance, detriment, loss, or responsibility, given, suffered, or undertaken by the other.”

A practical example of this can be found by examining a simple contract. Party A offers £500 to Party B, who in exchange will fit his car with a new engine. Party A receives the benefit of his car being fixed, whilst Party B incurs the detriment of having to take time, effort, and perhaps expenses to fix the car.

55
Q

Which of the following are commonly used as model forms of contracts in construction in the UK? A. Select TWO that apply

B. JCT

C. AS

D. NEC

E. CIPS

F. IET

A

Answer:
Answer:
B, D

Explanation:
Explanation:
- NEC: New Engineering Contract - a family of standard contracts primarily used in construction in the UK; includes works, consultants, services

  • JCT: Joint Contracts Tribunal - a family of standard contracts used in construction in the UK; includes works, consultants. subcontracts, services
  • AS: Australian Standards contracts - different contracts for a range of purchase types including constructions, consultancy, periodic supply of goods
  • IET: Institution of Engineering and Technology which issue jointly agreed model forms covering the design, supply and installation of electrical, electronic and mechanical plant ‘including special conditions for the ancillary development of software’
  • CIPS: Chartered Institute of Procurement and Supply - CIPS has developed its own suites of standard forms of contract for IT functions including: supply and installation of computer equipment, support and maintenance of bespoke software, servicing of computer equipment.
56
Q

In which of the following conditions, request for quotation produces the best results?

Options:
A. With an ambiguous specification

B. Under framework agreements

C. Under a complex process

D. With strategic items

A

Answer:
B
Explanation:
Explanation:
Request for quotation has valuable function when its use is properly controlled. It works the best under framework agreements where the contract terms are already fixed.

57
Q

Under which of the following scenarios an RFQ is most likely to be used?

Options:
A. Purchase of a small number of standardised products under a framework agreement

B. Purchase of complex machinery

C. Design of a unique and complex software code

D. When the buying organisation does not know the requirements in details and needs the input from suppliers

A

Answer:
A
Explanation:
Explanation:
The request for quotations is a procurement method that is used for small value procurements of readily available off-the-shelf goods, small value construction works, or small value services procurements. Request for quotations works best under a framework agreement

This procurement method is also known as invitation to quote and shopping, and it does not require the preparation of tender documents to the same extent as open tendering, request for proposals or two-stage tendering.

Among 4 options:

  • “Purchase of a small number of standardised products under a framework agreement”: the products are standardised and there is a framework agreement in place, so RFQ is the best solution.
  • “Purchase of complex machinery”: Complex machinery is often a large purchase. Furthermore, suppliers’ quality may vary. So RFQ is not suitable, instead, depending on the situation, buyer may opt ITT or RFP to purchase this type of machinery.
  • “Design of a unique and complex software code”: Unique and complex software is not off-the-shelf, thus RFQ is not suitable.
  • “When the buying organisation does not know the requirements in details and needs the input from suppliers”: When the detailed requirements are unknown, the best solution is request for proposal or developing dialogue with suppliers.
58
Q

Which of the following are NOT covered by CISG? Select TWO that apply:

Options:
A. Transfer of risks

B. Contract validity

C. Remedies for breach of contracts

D. Liability of the seller for death or personal injury

E. Liability to pay damages

A

Answer:
B, D
Explanation:
Explanation:
United Nations Convention on Contracts for the International Sale of Goods (Vienna Convention or CISG)

Vienna Convention was prepared by by the United Nations Commission on ¬International Trade Law (UNCITRAL) and adopted by a diplomatic conference on 11 April 1980. The Convention was welcomed by several countries from different geographic areas, with different legal and political systems. As of 20 August 2020, the Convention has93 Contracting States. The Convention has proved the effectiveness of an uniform text on international trade law.

What CISG covers, and what it does not

In the 6 first articles of the Convention, the authors set up the boundaries of its application.

First is about where it applies. According to UNCITRAL, the Convention applies to contracts of sale of goods between parties whose places of business are in different States and either both of those States are Contracting States or the rules of private international law lead to the law of a Contracting State. A few States have availed themselves of the authorisation in article 95 to declare that they would apply the Convention only in the former and not in the latter of these two situations. As the Convention becomes more widely adopted, the practical significance of such a declaration will diminish. Finally, the Convention may also apply as the law applicable to the contract if so chosen by the parties. In that case, the operation of the Convention will be subject to any limits on contractual stipulations set by the otherwise applicable law.

Second, the Convention has a list of goods that are not subject to its application in Article 2. Article 3 clarifies the differences between manufacturing contracts and sale contract.

Third, Article 4 and 5 clearly states what CISG does not covers, including grounds for contract invalidity and liabilities to death or injury of person caused by the the goods

Finally, the Convention respects the contractual freedom of the trading parties. Trading parties may select this convention as governing law or select other instrument, such as UPICC or domestic laws.

59
Q

Which of the following shall help the purchaser control the selection of tier 2 suppliers?

Options:
A. Subcontracting clause

B. Warranty clause

C. Guarantee clause

D. Insurance clause

A

Answer:
A
Explanation:
Explanation:
When a party takes on a contractual obligation, they are legally required to perform the obligation.

That same contracting party is still entitled to subcontract out the work to another service provider, unless the contract:

  • is a contract for personal services, such an employment contract
  • contains an express term preventing subcontracting out the work, or an implied term

Subcontracting clauses are written to control whether the contractor is entitled to subcontract, and how purchaser shall control that subcontracting process.

60
Q

Which of the following is used to detail the complex matter that may be verbiage to the main document?

Options:
A. Contract variation

B. Schedule

C. Subcontracting

D. Standard terms and conditions

A

Answer:
B
Explanation:
Explanation:
Without further explanation, a schedule may be deemed to form an integral part of the obligations of either or both parties. Obviously, the scope or binding nature of such schedule depends on the way it is referred to in the obligatory language of the main agreement. Accordingly, merely attaching the general terms and conditions of sale without explaining to which part of the sale they apply or which provisions apply does not subject a sale pursuant to the body text of the agreement to those general terms and conditions.

Subcontracting is the practice of assigning, or outsourcing, part of the obligations and tasks under a contract to another party known as a subcontractor.

61
Q

Carillion Ltd is a major construction contractor in the UK. The company commits to continuous improvement and sets out a performance management program that is integrated across the organisational, individual, and supplier levels. To ensure that the suppliers acknowledge the program, every time negotiating the contract terms with suppliers, the procurement team of Carillion appends a performance management framework to the draft document as a schedule. Is the action of procurement team appropriate?

Options:
A. No, because the framework will increase the complexity of the contract

B. No, because the performance management should be solely developed by suppliers

C. Yes, because the framework should have legal standing as a part of contract

D. Yes, because Carillion wants to implement early supplier involvement

A

Answer:
C
Explanation:
Explanation:
Performance management framework often consists of KPIs, targets and consequences that arise from achieved scores. To ensure that the framework has binding effect on contracting parties, it should be developed, appended to the main contract document and agreed by both parties. So the answer should be “Yes, because the framework should have legal standing as a part of contract”.

62
Q

Which of the following are key features of standard terms and conditions? Select TWO that apply

Options:
A. Standard terms always comply with implied terms

B. Specific to each purchase order

C. Non-disclosure

D. Non-negotiable

E. Designed to be used in repetitive transactions

A

Answer:
D, E
Explanation:
Explanation:
The key features, advantages and disadvantages of standard terms are summarised below:

  • Form: Concise, generic and designed to be attached to purchase or sales orders
  • Non-negotiable
  • Ineffective terms: may be replaced by implied terms or national legal code rules, or subject to court ‘balance of interest’ judgement.
  • Advantages: Basic contractual protection for most common circumstances; Avoid having to create new contract for repeat business.
  • User friendly
  • Usage: Low value, low risk, repetitive transactions
  • Coverage: Definitions, relationship to other contracts, formation of the contract, order of precedence, price, invoicing and payment, specification, legal compliance, warrantee and liability, ownership and risk, intellectual property, data management and ethics.
  • Disadvantages: Does not allow for specific circumstances; Risk for creating battle of the forms; Can create contractual uncertainty if used with purchase orders under call-off contracts.
63
Q

CMS Corp goes into a gainshare agreement with the contractor, EIP Ltd. Both parties agree that the final fee will be calculated on target cost - target fee basis. Which of the following will affect the final fee payable in this gainshare agreement? Select TWO that apply:

Options:
A. Accrual expense

B. Final price

C. Purchaser goodwill

D. Supplier share

E. Actual cost

A

Answer:
D, E
Explanation:
Explanation:
An incentive contract is a sub-segment of a fixed-price or cost-reimbursement contract when there are specific cost or time commitments that are desired for a project. The standard incentive contract will allow for a fixed price to be paid for work to be completed by a specific deadline and at a specific cost.

There are two major types of incentive contracts: Cost-plus-incentive fee and Fixed-price incentive (firm target) contracts. Both types have the same formula for calculating final fee and final price.

The target fee is the amount that will be paid if the actual costs (which can be proven) match the target costs

The actual fee will be adjusted in proportion to the difference between the target cost and the actual cost. The usual calculation is:

Target fee + ((target cost - actual cost) x Supplier share) = final fee

The final price then becomes:

Actual cost + final fee = final price

64
Q

In order to monitor supplier’s performance, an organization decides to draft performance management frameworks. Which of the following are the components of a performance management framework? Select THREE that apply:

Options:
A. Targets

B. KPIs

C. Consequences

D. Indemnity

E. Force majeure

F. Justification

A

Answer:
A, B, C
Explanation:
Explanation:
There are three key components of a performance management framework:

  • Key performance indicators (KPIs) - What you are measuring
  • Targets - the performance level to be achieved
  • Consequences - what happens if the measures are not achieved and/or if they are exceeded
65
Q

Which of the following will always give rise to a claim of misrepresentation?

  1. Silence
  2. False thought
  3. Statement of fact
  4. Representation by conduct

Options:
A. 1 and 2 only

B. 1 and 3 only

C. 3 and 4 only

D. 2 and 4 only

A

Answer:
C
Explanation:
Explanation:
A misrepresentation is a false statement of fact or law which induces the representee to enter a contract. Where a statement made during the course of negotiations is classed as a representation rather than a term an action for misrepresentation may be available where the statement turns out to be untrue.

For a party to claim for misrepresentation, there must be a false statement of fact or law as oppose to opinion or estimate of future events. It does not matter whether the incorrect information is given by words or takes the form of misleading conduct.

Silence will not generally amount to a misrepresentation. However, it can become a misrepresentation in some exceptional circumstances.

In the L4M3 study guide, the author states that “A statement of law is not misrepresentation”. This is untrue in both common law and civil law systems. In the UK, false statement of law will now amount to an actionable misrepresentation (see Pankhania v Hackney [2002] EWHC 2441).

66
Q

Which of the following should be used in a contract for window cleaning during the next three months?

Options:
A. Variable pricing arrangement

B. Fixed pricing arrangement

C. Standard schedule of rates

D. Cost-plus arrangement

A

Answer:
B
Explanation:
Explanation:
A contract for window cleaning during the next three months is a short-term service contract in which changes of input costs (labour, tools,…) are very unlikely to happen.

Fixed pricing arrangement is useful for small to medium scope project, with short timelines, where what is delivered can be adequately specified and the likelihood of changes to the specification, scope and input costs is limited.

67
Q

Which of the following is an example of liquidated damages clause?

  1. “In the event of a delay to the Offshore Installation Completion Date as per the Contract Schedule for which Contractor is solely responsible, Contractor shall pay to Company 0.25% per day of delay, subject to a maximum of 10% of the Initial Contract Price.”
  2. “If Seller breaches its obligation to deliver goods in accordance with the schedule provided for in this contract, Seller shall pay Buyer $x per day for each day of delay”
  3. “The Contractor shall defend and hold the Buyer, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with the performance of this Agreement, except for injuries and damages caused by the sole negligence of the Buyer.”
  4. “The contract is subjected to delay remedies. The amount will be agreed by both parties during the delivery”

Options:
A. 2 and 4 only

B. 1 and 3 only

C. 3 and 4 only

D. 1 and 2 only

A

Answer:
D
Explanation:
Explanation:
Liquidated damages, also referred to as “liquidated and ascertained damages” (LADs) are damages whose amount the parties designate during the formation of a contract[2] for the injured party to collect as compensation upon a specific breach (e.g. late performance). In supply contracts and work contracts, the liquidated damages clause often take form as known damages to be paid per day delayed. Number 1 and 2 are examples of this clause.

68
Q

Which of the following contracts would be best suited to a ‘variable pricing’ arrangement?

Options:
A. A contract for window cleaning during the next three months

B. A contract for road building estimated to take five years to complete

C. A contract for the supply of 100 printing machines to be delivered next month

D. A contract for the supply of lubricating oil for immediate delivery

A

Answer:
B
Explanation:
Explanation:
Variable pricing is suitable to situations when the cost of certain elements of the product fluctuate unpredictably. For road building, asphalt fluctuates regularly. Furthermore, 5 years are long period, then variable pricing is the most appropriate method to achieve value for money and control budget.

A contract for window cleaning during the next three months is a short-term service contract, fixed price is the most suitable method.

A contract for the supply of lubricating oil for immediate delivery is an one-off contract, only fixed price is applicable.

A contract for the supply of 100 printing machines to be delivered next month is also an one-off contract.

69
Q

A service contract is going to be expired, which data source is good to create specifications for ITT?

  1. Incumbent supplier
  2. Maintenance services
  3. Alternative supplier
  4. User’s knowledge

Options:
A. 1, 2 and 3

B. 1, 3 and 4

C. 1, 2 and 4

D. 2, 3 and 4

A

Answer:
B
Explanation:
Explanation:
There are a number of shortcuts that can be taken when drafting the specification. These include the following:

  • The use of brand names
  • The use of recognised standards
  • The use of samples
  • Information and knowledge from users/other buyers: Drafting a specification should naturally include those already used within the organisation itself, but also variants used by other companies in the same sector and other companies in different sectors
  • Information from suppliers: suppliers will always be willing to assist in specification development, as this this one way in which they can seek to influence the design to favour their own products.
70
Q

Which of the following is set down in statute as a liability that exists without any need to prove fault?

Options:
A. Strict liability

B. Current liability

C. Contingent liability

D. Non-current liability

A

Answer:
A
Explanation:
Explanation:
- Strict liability, sometimes called absolute liability, is the legal responsibility for damages, or injury, even if the person found strictly liable was not at fault or negligent. Strict liability has been applied to certain activities in tort, such as holding an employer absolutely liable for the torts of her employees, but today it is most commonly associated with defectively manufactured products. In addition, for reasons of public policy, certain activities may be conducted only if the person conducting them is willing to insure others against the harm that results from the risks the activities create.

  • Current liabilities are a company’s short-term financial obligations that are due within one year or within a normal operating cycle.
  • Non-current liabilities, also called long-term liabilities or long-term debts, are long-term financial obligations listed on a company’s balance sheet
  • Contingent liability is a potential liability that may occur, depending on the outcome of an uncertain future event.
71
Q

SFO procurement manager sent a request for quotation to Vogon International in which he determined the contract terms and specification. In SFO’s standard terms and conditions, it is stated that ‘Goods shall be delivered and Services performed by the applicable Delivery Date. Supplier must notify Buyer 3 days prior to the Delivery Date if Supplier is likely to be unable to meet a Delivery Date.’

Vogon replied with a quotation without any amendment to SFO’s terms & conditions. The SFO procurement manager found the prices were reasonable and submitted to senior management. Senior management team accepted that quotation and sent a notification to Vogon. On the Delivery Date, Vogon said they had no capacity to supply the product as the quotation due to a workers’ strike. Did Vogon breach any agreement with SFO?

Options:
A. No, because Vogon had no intention to be bound by the quotation, therefore, it didn’t constitute a contract

B.No, because the strike is a force majeur event, so Vogon did not breach any contract with SFO

C.Yes, because the contract was formed since Vogon had sent the quotation as an acceptance to SFO’s offer

D.Yes, because the contract had been formed between SFO and Vogon with the quotation as an offer and the notification as an acceptance

A

Answer:
D
Explanation:
Explanation:
SFO issued an RFQ with defined terms and condition and detailed specification. This RFQ can be considered as an invitation to treat. Vogon’s quotation is an answer to the purchaser’s RFQ and is an offer to SFO. The contract come to life at the time Vogon received the notification from SFO senior management.

The strike may be a force majeur event, depending on the contract particular clauses and jurisdiction. In common law countries, force majeur is applicable as an exclusion of liability only if the contract allows it. In many civil law countries, force majeur is an implied term. But in every jurisdiction, force majeur is only a reason for excluding liability for non-performance of a contract. In other words, the non-performance party is not liable for any breach if force majeur event occurs but the event does not exclude the breach.

72
Q

Which of the following would be useful tools to incentivise supplier innovation over the duration of the contract?

  1. Gainshare arrangement
  2. Liquidated damages
  3. Service credits
  4. Fixed bonus payments

Options:
A. 3 and 4 only

B. 2 and 4 only

C. 1 and 4 only

D. 1 and 3 only

A

Answer:
C
Explanation:
Explanation:
Gainshare is an incentive for cost control

Liquidated damage is common type of disincentive for late completion

Service credit is a remedy for not achieving targets set out in an SLA

Fixed bonus payment is an incentive for early completion

73
Q

Bandpro is a reseller of branded computer products to the private and public sector. The procurement team must purchase 500 items each day solely by multiple phone calls and emails to suppliers. Due to this practice, it takes a lot of time to track and collect relevant documents. Some important documents even get lost, which makes procurement audit more burdensome. Which of the following would increase the robustness of audit trails in procurement activities?

Options:
A. Every evidence must be recorded by paper

B. Adopt e-procurement

C. Spend less time on auditing procurement procedures

D. Rectify non-compliant activities

A

Answer:
B
Explanation:
Explanation:
Audit trail is a chronological record the sequence of events connected to a given transaction, such as a purchase of raw materials, payroll disbursements, or a detailed financial statement. The record includes all the source documents connected to the transaction, providing context and clarity in the event a review is required. The more comprehensive the documentation, the more effective the audit trail is when used to create financial reports, verify information, and ensure compliance while eliminating fraud.

In the scenario, the procurement team gets the quotation from phone calls and emails which have weak audit trails and lack of transparency. One solution may be increasing the use of e-procurement system.

74
Q

Since services are intangible, so KPIs for services must be qualitative in all circumstances. Is this statement correct?

Options:
A. No, KPIs for services must always be quantitative so that they can be measured easily

B. No, some KPIs for services are measurable by means of outcome, time and space performed

C. Yes, quantitative KPIs are limited to timeliness of supply of goods, defective rates and in-full quantities, which are applied to monitor supplier of physical goods

D. Yes, the only measure mattered to supply of services is end-users’ satisfaction

A

Answer:
B
Explanation:
Explanation:
KPIs are used to monitor supplier’s performance. They can be qualitative or quantitative. Of course, service providers can be monitored by quantitative KPIs regarding the outcome achieved (such as uptime in IT contracts), timeliness of deliveries (such as in construction contracts)…

75
Q

Which of the following are the conditions for revocation of offer to be valid?

  1. The offeree has not received the offer yet
  2. Revocation of offer must be communicated with the offeree
  3. Revocation of offer must be sent via email
  4. Offeree has not accepted the offer yet

Options:
A. 2 and 4 only

B. 1 and 4 only

C. 1 and 3 only

D. 2 and 3 only

A

Answer:
A
Explanation:
Explanation:
A revocation of offer is the withdrawal of a previous offer to engage in some sort of legally binding contract. The previous offer had to have been such that it would have immediately become legally binding if the other party had formally agreed to it.

A core ruling defining revocation of offers was established by Payne v. Cave. This case established that neither party is bound to an agreement until an offer has been made by one and formally accepted by the other.

If an offer has been made, the offering party has a right to withdraw it up to formal acceptance by the offeree. Revocation basically serves as formal, legally verifiable notice that a withdrawal was made, and it’s valid so long as it is communicated to the offeree before they accept.

The case of Byrne v. Van Tienhoven supports this by establishing that the withdrawal of an offer by telegram is only valid if the telegram is received before the offer is accepted. The case of Dickinson v. Dodds further establishes that the party making the offer can communicate the revocation through a third party.

76
Q

A procurement manager is setting KPIs measurement for user satisfaction. He also wants to encourage users to share the reason why they feel the way they do. Which of the following types of KPI should the procurement manager apply?

Options:
A. Quantitative measure

B. Numerical measure

C. Binary measure

D. Qualitative assessment

A

Answer:
D
Explanation:
Explanation:
There are 3 types of KPI measure:

  • Binary KPIs
  • Quantitative KPIs (or numerical)
  • Qualitative KPIs

User satisfaction is subjective, therefore, using qualitative assessment is the best answer.

77
Q

A supermarket purchases a new batch of house cleaner from new supplier. The supermarket is concerned about possible damage that the house cleaner may cause to consumers’ floor. What type of insurance must they cover?

Options:
A. Fire and explosion insurance

B. Product liability insurance

C. Professional indemnity insurance

D. Public liability insurance

A

Answer:
B
Explanation:
Explanation:
Product Liability Insurance is a form of general liability insurance meant to protect a business from financial and legal consequences as a result of bodily injury or property damage due to the use of the business’s sold goods or products. Situations that are typically covered by Product Liability Insurance may include:

  • A customer harms herself because of the faulty packaging on one of your products
  • A drapery set that a customer purchased from your business was highly flammable and caught on fire, eventually damaging her entire kitchen
  • A customer with a severe allergy finds trace amounts of tree nuts in your homemade gourmet muffins
  • A homemade house cleaner that you sell damaged one of your customer’s entire hardwood floor
  • A customer becomes sick with food poisoning after eating old shellfish at your restaurant, goes to the hospital, and incurs medical costs caused by your contaminated food products
  • A customer’s pet becomes ill from ingesting some lining in a pet toy product that you sell

In the scenario above, the supermarket is purchasing and reselling house cleaner, which can be covered by product liability insurance.

Public liability insurance is a type of business insurance that covers the cost of claims made by the public that happen in connection with the business activities.

Professional indemnity (PI) insurance is a commercial policy designed to protect business owners, freelancers and the self-employed if clients claim a service is inadequate.

78
Q

Social and environmental criteria are often incorporated into which of the following type of specification?

Options:
A. Design specification

B. Technical specification

C. Conformance specification

D. Output specification

A

Answer:
D
Explanation:
Explanation:
Developing and using generic specifications is as import in the sustainable procurement process as it is in the traditional procurement process. During this stage, human/labour rights and environmental performance criteria should be translated into specifications that meet specific requirements of the specified outcome, desired by the procurement action.

The specification stage is key to all types of contract. Building in environmental and social considerations at this early stage, provides a clear indication to suppliers that sustainability is important to the UN organization. Consider available alternatives which are less environmentally and socially damaging. Consider all the phases of a product’s life cycle (e.g. production, transportation, maintenance, disposal, etc) when determining its cost and environmental impact. Assess the overall environmental and social integrity of suppliers by looking at their policies and practices.

Specifications which are output-based rather than input-based can increase supplier innovation, reduce waste and minimise harmful social and environmental impacts.