Pumps Chapter 5 Flashcards

1
Q

From the Pump Manual:

How many types of service tests are used for Class A pumpers?

A

Three

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

From the Pump Manual:

The three hour test conducted by Underwriter’s Laboratories at a manufacturer’s plant is called a _______ test.

A

Listing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

From the Pump Manual:

When is the Acceptance test conducted?

A

When new apparatus is received by the purchaser

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

From the Pump Manual:

What is the duration of the standard Acceptance test?

A

Three hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

From the Pump Manual:

During the standard Acceptance test, what is the duration of the full capacity testing portion?

A

Two hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

From the Pump Manual:

What are the two capacities tested in half hour portions during the standard Acceptance test?

A

7/10 capacity and 1/2 capacity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

From the Pump Manual:

The DCFD requires the standard ______ hour Acceptance test when writing the specifications for the purchase of pumping apparatus.

A

Three

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

From the Pump Manual:

All pumping apparatus in service or reserve shall be tested at least ______ each year and after ______ ______ ______, to determine their condition.

A

once, any extensive repairs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

From the Pump Manual:

Annual service tests shall consist of drafting with a lift of no more than ______ feet.

A

Ten

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

From the Pump Manual:

What is the annual service test net pump pressure and duration of the full capacity portion?

A

150 psi, 20 minutes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

From the Pump Manual:

What is the annual service test net pump pressure and duration of the 7/10 capacity portion?

A

200 psi, 10 minutes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

From the Pump Manual:

What is the annual service test net pump pressure and duration for the 1/2 capacity portion?

A

250 psi, 10 minutes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

From the Pump Manual:

Where are annual service tests conducted?

A

Training Academy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

From the Pump Manual:

Annual service tests are conducted under the supervision of members of which two Divisions?

A

Training Division and Fleet Maintenance Division

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

From the Pump Manual:

Testing after extensive repairs will be conducted where and by whom?

A

At Fleet Maintenance by personnel from the Fleet Maintenance Division

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

From the Pump Manual:

When positioning apparatus for the annual service test, the pump control panel should face ______ from the cistern.

A

Away

17
Q

From the Pump Manual:

When the blind caps are removed from the apparatus, they should be examined to ensure that ______ and ______.

A

The gasket is in place, they are free of foreign matter

18
Q

From the Pump Manual:

What measure is taken to ensure the hard suction sleeves are tight enough together and tight enough to the apparatus?

A

Hammering the couplings with a rubber mallet

19
Q

From the Pump Manual:

Automatic relief valves and pressure regulators fhould be ______ during the test.

A

Disengaged

20
Q

From the Pump Manual:

The priming device on your apparatus should be able to prime the pump within ______.

A

45 seconds

21
Q

From the Pump Manual:

What instrument is used to determine if the required amount of water is being discharged for the test?

A

Pitot gauge

22
Q

From the Pump Manual:

For the full capacity service test, all munipulations to the flow of water must be accomplished without exceeding ______% of the peak engine speed.

A

80

23
Q

From the Pump Manual:

On two stage pumps, the ______ ______ must be placed in the ______ position for the 200 psi test.

A

Transfer valve, pressure

24
Q

From the Pump Manual:

All of the department’s fire hose shall be tested under the guidelines of NFPA ______.

A

1962

25
Q

From the Pump Manual:

Fire hose manufactured after ____, ____ will have the service test pressure stenciled on the hose.

A

July, 1987

26
Q

From the Pump Manual:

Any hose that has been repaired shall be tested by ______ ______.

A

Fleet Maintenance

27
Q

From the Pump Manual:

The total length of any hose line to be tested shall not exceed ______ feet and be secured at the end with a hose rope ______-______ inches behind the end coupling.

A

300 feet, 10-15 inches

28
Q

From the Pump Manual:

To begin the hose test, fill hose to ______ psi and check for leakage.

A

45 psi

29
Q

From the Pump Manual:

After ______ minutes at the service test pressure, the pump shall be shut down.

A

Five