Public Payment Bond Claims--McGregor Act Flashcards

1
Q

If no written contract, what does claimant need to include is SS?

A

1) identify the party who employed the cliamant;
2) date of performance;
3) description of the labor/materials;
4) amount of claim;
5) copies of invoices.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

If Written Contract exists, what must be in SS?

A

1) attached contract;
2) with SS;
3) unpaid invoices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Notice of retainage for bond claim

A

Send notice no later than 90 days from completion of overall project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Is there another notice that must be sent by a Second tier subcontractor?

A

Yes, to the GC by the 15th of the second month for each month.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

60 day investigation period

A

before fling a lawsuit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What must be i n the Sworn Statement of Account?

A

1) that “the amount claimed is just and correct and that all just and lawful offsets, payments, and credits known to the affiant have been allowed.”

2) principal or Surety must receive the origianl;
3) written notice is required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Is actual delivery of materials and labor required on government projects?

A

Yes.Must show actual consumption of materials and labor. This is a higher burden than for a lien claim.