Constitutional Liens Flashcards
Homestead Requirements
1) must have a written contract;
2) sets forth terms of agreement;
3) executed before the material is furnished or labor performed; (4) signed by both spouses;
5) filed with the County Clerk.
Article 16, Sec 50(a)(5) and Tex Prop. Code 53.254.
Additional requirements for homestead remodeling contract Article 16, Section 50(a)(5)(A)-(D).
1) four day waiting period after application for a loan; (2) three day out period of contract; (3) contract must be signed at at the office of the lender, an attorney, or a title company.
Constructive Notice to Third Party Purchaser
When there are newly constructed improvements on the property, the purchaser is under a duty to determine whether there are any outstanding liens against the property.
Burden of Proof of notice
Burden is on the purchaser to demonstrate that he did not have notice of the lien or claim.