Define Activities
The process of identifying the specific actions to be performed to produce the project deliverables
Sequence Activities
The process of identifying and documenting relationships among the project activities.
Estimate Activity Resources
The process of estimating the type and quantities of material, people, equipment, or supplies required to perform each activity
Estimate Activity Durations
The process of approximating the number of work periods needed to complete individual activities with estimated resources
Develop Schedule
Theprocessofanalyzingactivitysequences,durations,resourcerequirements, and schedule constraints to create the project schedule
Control Schedule
The process of monitoring the status of the project to update project progress and managing changes to the schedule baseline