ProjectTimeMgmt_Outputs Flashcards
1
Q
Define Activities Outputs
A
Activity list, Activity attributes, Milestone List
2
Q
Sequence Activities Outputs
A
Project schedule network diagrams, Project document updates
3
Q
Estimate Activity Resources Outputs
A
Activity resource requirements, Resource breakdown structure, Project document updates
4
Q
Estimate Activity Durations Outputs
A
Activity duration estimates, Project document updates
5
Q
Develop Schedule Outputs
A
Project schedule, Schedule baseline, Schedule data, Project document updates
6
Q
Control Schedule Outputs
A
Work performance measurements, Organizational process assets updates, Change requests, Project management plan updates, Project document updates