project scope mgmt Flashcards
1
Q
Project charter
vs
Project Scope
A
Project charter: about authorizing and starting things
Project scope: very specifi on what we’ll create
2
Q
WBS is the decomposition of ____ (not ____)
A
DELIVERABLES (not activities)
3
Q
Scope Baseline consists of:
A
1) Project scope statement
2) WBS
3) WBS dictionary
4
Q
When the customer is inspecting a deliverable, what process is this?
A
Scope Validation
5
Q
QC and scope validation are both ___
What comes first - quality control (QC) or scope validation?
What is the difference between the two?
A
–both are INSPECTION DRIVEN ACTIVITIES
- QC comes BEFORE scope validation
- 2 different goals:
- QC : PM/team inspect the work before the customer does / goal is to keep mistakes out of customer’s hands
- Scope Validation : the customer inspects the work / goal is for customer to sign-off, accept what’s been created
6
Q
What 2 plans are outputs of the PLAN SCOPE MANAGEMENT process?
A
- Scope management plan
- Requirements management plan