project scope mgmt Flashcards

1
Q

Project charter

vs

Project Scope

A

Project charter: about authorizing and starting things

Project scope: very specifi on what we’ll create

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

WBS is the decomposition of ____ (not ____)

A

DELIVERABLES (not activities)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Scope Baseline consists of:

A

1) Project scope statement
2) WBS
3) WBS dictionary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When the customer is inspecting a deliverable, what process is this?

A

Scope Validation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

QC and scope validation are both ___

What comes first - quality control (QC) or scope validation?

What is the difference between the two?

A

–both are INSPECTION DRIVEN ACTIVITIES

  • QC comes BEFORE scope validation
  • 2 different goals:
  • QC : PM/team inspect the work before the customer does / goal is to keep mistakes out of customer’s hands
  • Scope Validation : the customer inspects the work / goal is for customer to sign-off, accept what’s been created
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What 2 plans are outputs of the PLAN SCOPE MANAGEMENT process?

A
  • Scope management plan

- Requirements management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly