10 PM Knowledge Areas and 49 Processes Flashcards

1
Q

What 7 processes are performed in Integration Management ?

PMBOK 6ed, 4.1-4.7

A
1 - Develop project charter
2 - Develop project management plan
3 - Direct and manage the project work
4 - Manage project knowledge
5 - Monitor and control project work
6 - Perform integrated change control
7 - Close project or phase
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What 6 processes are performed in Scope Management ?

PMBOK 6ed, 5.1-5.6

A
1 - Plan scope management
2 - Collect requirements
3 - Define scope
4 - Create WBS
5 - Validate scope
6 - Control scope
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What 6 processes are performed in Schedule Management ?

PMBOK 6ed, 6.1-6.6

A
1 - Plan schedule management
2 - Define activities
3 - Sequence activities
4 - Estimate activity durations
5 - Develop schedule
6 - Control schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What 4 processes are performed in Cost Management ?

PMBOK 6ed, 7.1-7.4

A

1 - Plan cost management
2 - Estimate costs
3 - Determine budget
4 - Control costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What 3 processes are performed in Quality Management ?

PMBOK 6ed, 8.1-8.3

A

1 - Plan quality management
2 - Manage quality
3 - Control quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What 6 processes are performed in Resource Management ?

PMBOK 6ed, 9.1-9.6

A
1 - Plan resource management
2 - Estimate activity resources
3 - Acquire resources
4 - Develop team
5 - Manage team
6 - Control resources
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What 3 processes are performed in Communications Management ?

(PMBOK 6ed, 10.1-10.3)

A

1 - Plan communications management
2 - Manage communications
3 - Monitor communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What 7 processes are performed in Risk Management ?

PMBOK 6ed, 11.1-11.7

A
1 - Plan risk management
2 - Identify risks
3 - Perform qualitative risk analysis
4 - Perform quantitative risk analysis
5 - Plan risk responses
6 - Implement risk responses
7 - Monitor risks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What 3 processes are performed in Procurement Management ?

PMBOK 6ed, 12.1-12.3

A

1 - Plan procurement management
2 - Conduct procurements
3 - Control procurements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What 4 processes are performed in Stakeholder Management ?

PMBOK 6ed, 13.1-13.4

A

1 - Identify stakeholders
2 - Plan stakeholder engagement
3 - Manage stakeholder engagement
4 - Monitor stakeholder engagement