Project Procurement Flashcards

1
Q

Purpose & content of a procurement strategy

A

Purpose:
○ Ensure projects/programmes/portfolios have the right resources
○ Balance risk between organisation & supply chain

Content:
○ Make or buy
○ Payment mechanisms (how/when to pay the supplier)
○ Single/integrated/multiple suppliers
- Single preferred supplier (do everything else in-house)
- Integrated: supplier sits with project team e.g. Steve Halliday
- Multiple: spreads risk better
○ Contract and t’s & c’s:
- To include Service Level Agreement, quality, delivery timing, and payment terms
○ Supplier selection process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Different methods of supplier reimbursement

A
  • Fixed price
    ○ Defined scope
    ○ Supplier risks going over budget and losing money
    ○ Customer risks delays and poor quality if supplier tries to cut corners
  • Cost plus fee
    ○ Supplier charges their costs plus a fee (often a percentage)
    ○ Supplier doesn’t risk losing money
    ○ Customer risks not knowing the final price
  • Per unit quantity/time & material
    ○ Highest risk to customer as they don’t know scope or final price
    ○ Customer can use robust contract management to keep track of costs as incurred
  • Target cost
    ○ If final cost is cheaper, both parties share the excess. If it’s more, both fund the excess
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Explain different contractual relationships

A
  • Single supplier/turnkey
    ○ Simple to manage
    ○ May not get the best price for all commodities
  • Multiple suppliers
    ○ More complex to manage
    ○ Shop around for the best price
  • Sequential
    ○ One supplier for each stage of the project
    ○ Interactions between stages must be planned & managed
  • Parallel
    ○ Multiple suppliers working alongside one another
    ○ Customer must manage all supplier relationships
    ○ Good if each supplier has limited capabilities
  • Sub-contracts
    ○ Prime contractor holds the main contract, and sub-contracts to others to complete
    ○ Simpler for customer to manage, but can make managing quality or timings more difficult
  • Partnering/joint venture
    ○ Multiple suppliers form a partnership if the work is too complex for a single supplier to deliver (e.g. Boorley Park)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Outline a supplier selection process

A
  • Define the requirement.
    ○ Research
    ○ Pre-qualification: who will be able to do it?
    ○ How will you evaluate the bids?
  • Invitation to tender.
  • Evaluating the bids.
  • Award the contract.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly