Project Planning Process Flashcards
What Project Controls would you implement to ensure successful project planning execution and delivery?
What.benefits can be realised when using a Project lifecycle?
What benefits can be applied when applying Earned value management?
What experience do you have in Primavera or any project planning software system?
What is difference between planning and scheduling?
Planning deals with why project objectives , what scope of work or basis of design , how ( project execution strategy & plan) and who ( project organisation structure & contracting strategy).
While scheduling deals with when.
True or false? Project planners define the activities to accomplish goals and objectives.
True
True or false ?
Scheduling deals with the development of progress measurement system ?
False, planning deals with development of progress measurement system while scheduling deals with implementation and operation of progress measurement systems.
Which role ( scheduling or planning ) is involved in undertaking critical path methods (CPM) & resource analyses , including the determination of critical path and producing resource histogram?
Scheduling
True or false? Planning deals with review of safety constructibility , maintain ability and operability of the plants?
True Planners involves dealing with safety , maintainable and construction of plants
While planning involves the setting of goals and objectives , scheduling deals with …..
Scheduling deals with mechanics of converting the plan into a timetable.
While scheduling is a reflection of a project plan Planning does what?
Planning provides the basis for time and resource estimation.
What are the consequence of using lag?
Lag if used abusively can impact logic of a schedule program. It can lessen the ability of the project schedule to dynamically respond to changes in status of predecessor activities, because it is static. Lags distort float calculation s.
What methods can be applied to remove unnecessary lag in finish to start relationship ?
Effort should be made to break tasks up to smaller tasks and to identify predecessor and successor activities .
What is better alternative to using leads as negative lag.
The concept of a lead is better representated by positive lag on a S-S relationship or even more straight forward in F- S relationship with no lag using smaller duration activities.
What could be a consequence of having lead longer than successor activity?
It may lead to logic failure.