70 Acronyms Flashcards
Activity
A task or process to be accomplished in set period of time as part of working towards a larger project goal. An activity can be assigned resources and have an associated cost. Activities are ordered with logic links.
Actual cost
The real amount paid or incurred for labour or materials
Activity relationship
An ordered link between 2 activities representing the order of execution The 4 relationship types are FS finish to start SS start to start FF Finish to start SF Start to Finish
Approved change request
Documents of approved changes made to the project contract as a whole ( cost schedule plan) These are first reviewed by all stakeholders before being approved .
Arrow Diagraming Method (ADM)
Arrow diagramming method is a network diagramming technique used in Project Management in which activities are represented by arrows . ADM is also known as the activity-on-arrow (AOA) method.
ADM is used for scheduling activities in a project plan. Precedence relationships between activities are represented by circles connected by one or more arrows. The length of the arrow represents the duration of the relevant activity. ADM only shows finish- to-start (FS) relationships, where each activity is completed before the successor activity starts.
Backward pass( backwards plan)
Critical path analysis calculation process which having calculated earliest date for activities on the network. Works backwards to find activities latest start and finish dates/ float.
Budgeted cost
The amount planned ahead and placed aside to execute an activity or an entire project from start to finish.
Change estimate
An estimate evaluating a potential change to a project. Often the estimate focus on cost , schedule,and resource changes.
Change impact
The effect of a project change on project cost , schedule and resourcing.
Committed cost
A cost which has not been paid , but agreed upon ( purchase order , contract) so that the cost is no longer recoverable
Cost Breakdown Structure
Breakdown of the project into elements for costs control planning. A CBS will deconstruct a project into various cost elements or types such as area , phase , discipline or materials.
Critical activity
An activity which is on the projects critical path
Critical path
A projects critical path is a sequence of network activities which add up to the longest overall duration . This determines the shortest time possible to complete the project.
Critical path method (CPM) scheduling
A project modelling technique and algorithm for scheduling a set of projects activities. Developed in late 1950s , CPN scheduling aims to build a model of a project that contains
- A list of all activities required to complete the project (typically categorised within a end)
- The time ( duration) that each activity will take to complete
- The dependencies between activities and,
- Logical end pints such as milestones of deliverables items.
It then uses an algorithm that computes early and late dates for activity in order to determine the projects critical path.
It is also analysis of a project schedule by its critical path or longest path.
double resource estimated duration (DRED)
Measures length of an activity duration if assigned level of resource have doubled.