Project Planning ad control Flashcards
What are the three Project Planning Concepts?
- Outcome-based planning
- Planning to sensible horizons at the right level of detail
- Plan and re-plan based on best available estimates
What is outcome based planning?
The Project Manager is responsible for high-level planning for the project, collaboratively planning for the incremental delivery of the business solution – the outcome required by the Business Sponsor
The Solution Development Team is responsible for planning the detail of all the work of each Timebox with team members agreeing amongst themselves who will do what work to achieve the objectives agreed at the Kick-off of that Timebox
Planning to sensible horizons at the right level of detail
Things can change as time moves on.
Plan in detail for short horizons
Plan at a higher level for long term horizons
Name three estimating techniques
Top down: estimates using requirements, tools and experience to produce an estimate
Bottom up: takes a sample of priority requirements and breaks them down into detail. Structured timeboxes are used and tasks are detailed.
Group estimating
Name 6 testing concepts
- Testing integrated throughout
- Collaborative testing
- Repeatable testing (supports regression testing)
- Prioritised testing
5 Independent testing - test driven development (Using a Test-Driven Development the design and build of the test precedes development of the solution and helps define the requirement.)