Project Methodology Flashcards

1
Q

Rolling Wave Planning

A

An iterative planning technique in which the work to be accomplished in the near term is planned in detail, while work further in the future is planned at a higher level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Progressive Elaboration

A

The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Predictive Life Cycle

A

Determine project scope, time, and cost in the early phases of this life cycle.