Project management terms (6) Flashcards
Activity list
the primary output of breaking down the WBS work packages
Alternative analysis
the identification of more than one solution. consider roles, materials, tools, and approaches to the project work
analogous estimating
a somewhat unreliable estimating approach that relies on historical information to predict what current activity durations should be. analogous estimating is more reliable, however, than team member recollections. analogous estimating is also known as top-down estimating and is a form of expert judgement
Bottom- up estimating
the most accurate time-and -cost estimating approach a project manager can use. this estimating approach starts at “the bottom” of the project and considers every activity, its predecessor adn successor activities, and the exact amount of resources needed to complete each activity
control account
A WBS entry that considers the time, cost, adn scope measurements for that deliverable within the WBS. the estimated performance is compared against the actual performance to measure overall performance fro the deliverables within that control account. the specifics of a control account are documented in a control account plan
Contorl threshold
a predetermined range of acceptable variances, such as +/-10% off schedule. should the variance exceed the threshold, then project control processes and corrected actions will be enaccted
crashing
a schedule compression approach that adds more resources to activities on the critical path to complete the project earlier. when crashing a project, costs are added because the associated labour and sometimes resources cause cost increase
critical path
the path in the project network diagram that cannot be delayed, otherwise the project completion date will be late. there can be movre than one critical path. activities in the critical path have no float.
discretionary dependecies
these dependencies are the preferred order of activities. project managers should use these relationships at their discretion and should document the logic behind the decision. discretionary dependencies allow activities to happen in a preferred order because of best practices, conditions unique to the project work, or external events. also known as preferential or soft logic
early finish
the earliest a project activity can finish. used in the forward pass procedure to discover the critical path and the project float
early start
the earliest a project activity can begin. used in the forward pass procedure to discover the critical path and the project float
external dependenciers
as the name implies, these are dependencies outside of the project’s control. delivery of equipment from vendor, the deliverable of another project, or the decision of a committee, lawsuit or expected new law.
fast tracking
a schedule compression method that changes the relationship of activities. with fast tracking, activities that would normally be done in sequence are allowed to be done in parallel or with some overlap. fast tracking can be accomplished by changing the relation of activities from FS to SS or even to FF or by adding lead time to downstream activities. however, fast tracking does add risk to the project
finish to Finish
an activity relationship type that requires the current activity to be finished before its successor can finish
finish to start
An activity relationship type that requires the current activity to be finished before its successor can start.
fragnet
A representation of a project network diagram that is often used for outsourced portions of a project, repetitive work within a project, or a subproject. Also called a subnet.
Free float
This is the total time a single activity can be delayed without affecting the early start of its immediately following successor activities.
hard logic
Logic that describes activities that must happen in a particular order. For example, the dirt must be excavated before the foundation can be built. The foundation must be in place before the framing can begin. Also known as a mandatory dependency.