Project Management - Post Midterm Flashcards

1
Q

5 Project Management Phases

A
  1. Initiating
  2. Planning
  3. Executing
  4. Controlling
  5. Closing
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Gantt Chart

A

Shows the required time for each activity and when each activity occurs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Flow Diagram

A

Show precedence more clearly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Critical Path

A

Longest path through the process flow diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Enumeration Method

A

Identify all paths between the start node and the end node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Critical Activity

A

Any task in a project or process that directly affects the overall duration or timely completion of that project.

If it’s delayed, the entire project is delayed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Delaying a non-critical activity may not lead to a delay in the total completion time of the project. Is this true?

A

TRUE because a non-critical activities have slack (or float) — extra time they can be delayed without affecting the total project duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Botleneck

A

Determines the process capacity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Ways to short and activity

A
  1. Investing more money
  2. Adding a new technology
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Crash Time Of An Activity

A

A new possible theoretical flow time

Minimum possible time to complete the activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Crash Cost

A

Price to complete the activity if the flow time is shortened to the crash time.

Cost to complete the activity in the shortest time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Cost Slope

A

The extra cost we pay to shorten the
flow time of an activity per time unit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Cost Slope Formula

A

NormalTime−CrashTime/CrashCost−NormalCost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Crashing Activities

A
  1. Crash the cheapest critical activity first
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When to Crash an Activity

A

When you need to reduce the project duration

If it is worth the cost

Some activities cant be crased - If the table shows “NA” for crash time or crash cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Precedence

A

Shows which activities must be completed before others can begin.