Project Management Part 2 Flashcards

1
Q

developed by representatives of DuPont to assist in the management of industrial projects

A

Critical path method CPM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The focus of ________is to determine when a project should be completed and to schedule when each activity in the project must begin in order to keep the project on scheudule

A

CPM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

was developed by EU S Navy because many tasks required to complete a project had uncertain times

A

program evaluation and review technique PERT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

focuses on estimating the probability of completing a project by a given deadline

A

program evaluation and review technique PERT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

over the years the two techniques have blended together and I referred to collectively

A

PERT/CPM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

any project can be broken down into component activities

A

Time of activities

Order of activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

projects require

A

amounts of time accomplished in a specific order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The major differences between CPM and PERT

A

involve how the time element of the activities is determined

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Projects must have

A

both require a detailed network that clearly indicate the main activities and their precedent relationship

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Activity on node

A

a network design that portrays activities bynodes in a chart there are immediate predecessors and immediate successors of each activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Activity on ark

A

represents the project activities with arrows

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

After creating a network The next step in the CPM technique is to

A

determine the earliest time that each activity in the network can start and finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Forward Pass allows us to

A

determine the earliest time that each activity in the network can start and finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

this analysis determines the earliest time that the project itself can be completed

A

Forward Pass

How well did you know this?
1
Not at all
2
3
4
5
Perfectly