Ch. 15 Project Management Flashcards
the process of organizing, planning, and monitoring an effort consisting of various constraints
Project Management
Characteristics of project management:
Many projects do not finish on schedule or budget
Time delays frequently occur.
Budget overruns are common-place
Many projects fall short of planned technical content
Some projects are canceled before completion
how is project management different from management of more traditional activities?
has limited time framework and unique set of activities involved, which gives rise to a host of unique problems
a person who promotes and supports a project
project champions
a hierarchical listing of what must be done during a project
work breakdown structure (WBS)
A Project is
Interrelated set of activities
Each activity has a definite starting/ending point
Some tasks can be conducted in parallel
Activity
The smallest unit of a project
network diagram convention in which nodes designate activities
has a starting node, S, which is actually not an activity but is added in order to have a single starting node
activities are referred to by a letter (or number) assigned to a node
activity-on-node (AON)
network diagram convention in which arrows designate activities
activities can be referred to by their endpoints or by a letter assigned to an arrow
activity-on-arrow (AOA)
Project management 3 points
Defining project goals
Planning project activities
Coordinating resources
A planning system for integrating schedules, costs, and resource allocation
Earned value analysis—
CAPM
critical path method
for planning and coordinating large projects
PERT
program evaluation and review technique
for planning and coordinating large projects
How are earliest start dates calculated?
They are computed by adding up the durations of tasks along the network paths from left to right
”
How is the earliest completion date calculated?”
Add the expected duration to the earliest start date
Define backward path analysis?
A way to calculate the latest start and completion for all tasks in a project network
The backward pass is done by starting with the project completion date (defined by the critical path), and then subtracting the task times from right to left along the paths in the network.
individual responsible for managing the overall effort
Project Manager
cross-functional group assigned to specific task functions
Project Team
structure used to organize and implement the project
Project Management System
Project life cycle
(1) initiating
(2) planning
(3) executing
(4) monitoring and controlling
(5) closing
initiating phase of a project:
goals, specifications, feasibility, tasks, responsibilities
planning phase of a project:
schedules, budgets, resources, risks, staffing
executing phase & monitoring/controlling phase of a project:
status reports, changes, quality, manage, monitor and control
closing phase of a project
train customer, transfer documents, release resources, reassign staff, lessons learned