Project Management Formulas Flashcards
Formula for CV (Cost Variance)
EV - AC
EV: Earned Value
AC: Actual Cost
Formula for SV (Schedule Variance)
EV - PV
EV: Earned Value
PV: Planned Value
Formula for CPI
EV / AC
EV: Earned Value
AC: Actual Cost
Formula for SPI
EV / PV
Formula for EAC (Estimate at Completion)
BAC / CPI
Formula for ETC (Estimate to Completion)
EAC - AC
Formula for EV (Earned Value)
BAC x percent complete
BAC: Budget at Completion
What does EV mean?
budgeted cost of work accomplished
What does PV mean?
budgeted cost of work planned/scheduled
What does AC mean?
Actual cost of work accomplished
What does BAC mean?
original baseline budget
What does ETC mean?
Estimate to completion
How much to complete remaining work
What does EAC mean?
Estimate at completion
estimated cost at the completion of the project
formula for EAC if future variances will NOT be similar
(AC + BAC - EV)