Project Management Formulas Flashcards

1
Q

Formula for CV (Cost Variance)

A

EV - AC

EV: Earned Value
AC: Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Formula for SV (Schedule Variance)

A

EV - PV

EV: Earned Value
PV: Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Formula for CPI

A

EV / AC

EV: Earned Value
AC: Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Formula for SPI

A

EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Formula for EAC (Estimate at Completion)

A

BAC / CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Formula for ETC (Estimate to Completion)

A

EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Formula for EV (Earned Value)

A

BAC x percent complete

BAC: Budget at Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What does EV mean?

A

budgeted cost of work accomplished

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does PV mean?

A

budgeted cost of work planned/scheduled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What does AC mean?

A

Actual cost of work accomplished

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does BAC mean?

A

original baseline budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does ETC mean?

A

Estimate to completion

How much to complete remaining work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does EAC mean?

A

Estimate at completion

estimated cost at the completion of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

formula for EAC if future variances will NOT be similar

A

(AC + BAC - EV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly