Project management Flashcards
The project sponsor:
a. drives project tasks in the closing phase
b. approves major milestones
c. has to run project marketing activities
d. needs to define the project team
The project sponsor:
b. approves major milestones
What are key duties of the project manager during the “performing” phase (according to Tuckman Model)?
a. Communication, Risk Management, Coordination
b. Structuring, Communication, Delegation, Coordination
c. Stakeholder Management, Delegation, Planning, Quality Management
d. Structuring, Risk Management, Controlling
What are key duties of the project manager during the “performing” phase (according to Tuckman Model)?
b. Structuring, Communication, Delegation, Coordination
Agile projects:
a. increase the ability to react to changes
b. aim to reduce communication to a minimum
c. are only relevant for IT/ Digitalization topics
d. focus on a lessons learned session at the very end of the project
Agile projects:
a. increase the ability to react to changes
The communication plan:
a. ideally considers the single best communication path to stakeholders
b. is based on the team charter
c. needs to cover at least recipient, frequency, medium and content of communication measures
d. is owned by the project sponsor
The communication plan:
c. needs to cover at least recipient, frequency, medium and content of communication measures
Project planning requires the following steps and sequence:
a. Defining the work, specifying duration and effort, determining dependencies and resources, clarifying activity ownership
b. Defining the work, determining dependencies and resources, specifying duration and effort, assigning budget positions
c. Defining the work, assigning responsibilities, determining dependencies and resources, assigning budget positions
d. Defining the work, assigning budget positions, specifying duration and effort, clarifying activity ownership
Project planning requires the following steps and sequence:
a. Defining the work, specifying duration and effort, determining dependencies and resources, clarifying activity ownership
Project risks:
a. need to be avoided as good as possible
b. are owned by the project manager
c. should be evaluated by impact and probability
d. shall we closed after planning stage
Project risks:
c. should be evaluated by impact and probability
Project is a(n)…???
Project is a(n)…
- *unique** endeavor with a clear goal that needs to be achieved by
- *interrelated tasks** in a fixed period of time with limited cost and
- *resources** and influenced by risks
Portfolio is a…???
Portfolio is a…
set of projects with similar characteristics
Program is a…?
Program is a…
set of projects focusing on the same, overarching goal
What are the 5 phases of the Tuckman team development model?
What are the 5 phases of the Tuckman team development model?
- Forming
- Storming
- Norming
- Performing
- Transforming
What are the core phases of a projects (according to PMI)?
What are the core phases of a projects (according to PMI)?
Initiating - Planning - Executing - Monitoring & controlling - Closing