Project Management Flashcards

1
Q

Projects

A

Unique, one-time operations designed to accomplish
a specific set of objectives in a limited time frame
Examples: (Olympic games, producing a movie, software development, product development, ERP implementation)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Project Life Cycle

A

Definition
Planning
Execution
Delivery

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Project Manager

A

Project manager is ultimately responsible for the success or failure of the project

Must manage:
The work
the human resources
communication 
quality/time/costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Behavioral Issues

A

Behavioral problems can be created or exacerbated by decentralized decision making, stress of achieving project milestones on time & within budget, suprises

The team must be able to function as a unit
(interpersonal & coping skills are very important

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Avoiding Problems

A
Many problems can be avoided or mitigated by: 
-effective team selection 
– Leadership
– Motivation
– Maintain an environment of• Integrity
• Trust
• Professionalism
– being supportive of team efforts
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Work Breakdown Structure (WBS)

A
  • a hierarchical listing of what must be done during a project
    -establishes a logical framework for identifying that required actives for the project
    (identify the major elements of the project, identify the major supporting activities for each of the major elements, break down each major supporting activity into a list of the activities that will be needed to accomplish it.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

PERT & CPM

A

PERT (program evaluation & review technique) & CPM (critical path method) are two techniques used to manage large scale projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Network Diagram

A

Network diagram
— Diagram of project activities that shows sequential relationships by use of
arrows and nodes
— Activity on arrow (AOA)
— Network diagram convention in which arrows designate activities
— Activity on node (AON)
— Network convention in which nodes designate activities
– Activities
» Project steps that consume resources and/or time
– Events
» The starting and finishing of activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Deterministic Time Estimates

A

Deterministic
– Time estimates that are fairly certain
• Probabilistic
– Time estimates that allow for variation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Slack & Critical Path

A
slack can be computed one of two ways:
- slack= LS-ES
- slack= LF-EF
Critical Path
-the critical path is indicated by the activities with zero slack
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Using Slack times

A

Knowledge of slack times provides managers with information for planning allocation of scarce resources
— Control efforts will be directed toward those activities that might be most susceptible to delaying the project
— Activity slack times are based on the assumption that all of the activities on the same path will be started as early as possible and not exceed their expected time
— If two activities are on the same path and have the same slack, this will be the total slack available to both

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Time-Cost Trade-Offs

A

Activity time estimates are made for some given level of resources
• It may be possible to reduce the duration of a project by injecting additional resources
– Motivations:
• To avoid late penalties
• Monetary incentives
• Free resources for use on other projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Crashing

A

Crashing
– Shortening activity durations
• Typically, involves the use of additional funds to support additional personnel or more efficient equipment, and the relaxing of some work specifications
– Theprojectdurationmaybeshortenedbyincreasingdirect expenses, thereby realizing savings in
indirect project costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Crashing Decisions

A

To make decisions concerning crashing requires information about:
1. 2. 3.
Regular time and crash time estimates for each activity
Regular cost and crash cost estimates for each activity
A list of activities that are on the critical path — Critical path activities are potential candidates for crashing
— Crashing non-critical path activities would not have an impact on overall project duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Crashing: Procedure

A

General procedure:
1. 2. 3.

Crash the project one period at a time
Crash the least expensive activity that is on the critical path
When there are multiple critical paths, find the sum of crashing the least expensive activity on each critical path
If two or more critical paths share common activities, compare the least expensive cost of crashing a common activity shared by critical paths with the sum for the separate critical paths

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

PERT: Advantages

A

Among the most useful features of PERT:

  1. It forces the manager to organize and quantify available information and to identify where additional information is needed
  2. It provides the a graphic display of the project and its major activities
  3. It identifies
    a. Activities that should be closely watched b. Activities that have slack time
17
Q

Sources of Error

A

Potential sources of error:

  1. The project network may be incomplete
  2. Precedence relationships may not be correctly expressed
  3. Time estimates may be inaccurate
  4. There may be a tendency to focus on critical path activities to the exclusion of other important project activities
  5. Major risk events may not be on the critical path
18
Q

Project Management Software Advantages

A

Advantages include:

  • imposes a methodology & common project management terminology
  • provides a logical planning structure
  • may enhance communication among team members
  • can flag the occurrence of constraint violations
  • automatically format reports
  • can generate multiple levels of summary & detail reports
  • enables “what if” scenarios
  • can generate a variety of chart types