Materials Requirements Planning (MRP) Flashcards

1
Q

Dependent Demand

A
  • Demand for items that are subassemblies or component parts to be sued in the production of finished goods.
  • tends to be sporadic or “lumpy” (large quantities are used at specific points in time with little or no usage at other times)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Dependent vs. Independent Demand

A
  • Independent Demand (Stable Demand), random,continuous, can be forecast, not under the control of planners
  • Dependent Demand (lumpy Demand), dependent on our plans
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

MRP (Material Requirements Planning)

A
  • Computer based information system that translates master schedule requirements for end items into time-phased requirements for subassemblies, components, & raw materials.
  • MRP designed to answer three questions (WHAT,HOW,WHEN is needed?)
  • High suitability of MRP for dependent demand systems.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Overview of MRP

A
  • MRP Inputs: Master schedule (orders & forecasts), Bill of materials (design changes), & Inventory records (receipts & withdrawals)
  • MRP Processing: MRP computer programs
  • MRP Outputs: Primary reports (changes, order releases, planned-order schedules) Secondary Reports (exception reports, planning reports, performance control reports, inventory transaction)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

MRP Input: Master Schedule

A
  • states which end items are produced, when these are needed, and in what quantities.
  • should cover a period that is at least equivalent to the cumulative lead time (the sum of the lead times that are sequential phases of process require, from ordering of parts or raw materials to completion of final assembly)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cumulative Lead time

A
  • the sum of the lead times that are sequential phases of process require, from ordering of parts or raw materials to completion of final assembly
  • Procurement, fabrication, subassembly, assembly)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

MRP Inputs: Bill of Materials

A
  • a listing of all of the assemblies, subassemblies, parts and raw materials needed to produce one unit of a product
    -product structure tree
    (visual depiction of the requirements in a bill of the materials, where all components are listed by levels.)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Low - Level Coding

A

the sum of the lead times that are sequential phases of process require, from ordering of parts or raw materials to completion of final assembly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

MRP Inputs: Inventory Records

A
  • Includes information on the status of each item by time period called time buckets
  • information about.. (gross requirements, scheduled receipts, expected amount on hand)
  • Other details for each item such as (supplies, lead time, lot size policy, changes due to stock receipts and withdrawals, canceled orders & similar events)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

MRP Processing

A

MRP processing takes the end item requirements specified by the master schedule and “explodes” them into time- phased requirements for assemblies, parts, and raw materials offset by lead times

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Gross Requirements

A

total expected demand

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Scheduled receipts

A

open orders scheduled to arrive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Projected on hand (projected available balance)

A

expected inventory on hand at the beginning of each time period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Net Requirements

A

actual amount needed in each time period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Planned- Order receipts

A

quantity expected to received at the beginning of the period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Planned- order releases

A

planned amount to order in each time period

17
Q

MRP Pegging

A

The process of identifying the parent items that have generated a given set of material requirements for an item

18
Q

MRP Outputs: Primary

A

Primary Outputs – Planned orders
• A schedule indicating the amount and timing of future orders
– Order releases
• Authorizing the execution of planned orders
– Changes
• Revisions of the dates or quantities, or the cancellation of orders

19
Q

MRP Outputs: Secondary

A

Secondary Outputs
— Performance-control reports
— Evaluation of system operation, including deviations from plans and cost information
– e.g., missed deliveries and stockouts — Planning reports
— Data useful for assessing future material requirements – e.g., purchase commitments
— Exception reports
— Data on any major discrepancies encountered
– E.g., late and overdue orders, excessive scrap rates, requirements for nonexistent parts

20
Q

Lot Sizing Rules: (Lot-for-Lot (L4L) ordering

A
  • The order or run size is set equal to the demand for the period
  • Minimizes investment in inventory
  • It results in variable order quantities
  • a new setup is required for each run
21
Q

fixed period order

A

provides coverage for some predetermined number of periods

22
Q

MRP Benefits

A

Enables managers to easily
– determine the quantities of each component for a given order size
– To know when to release orders for each component
– To be alerted when items need attention
• Additional benefits
– Low levels of in-process inventories
– The ability to track material requirements
– The ability to evaluate capacity requirements
– A means of allocating production time
– The ability to easily determine inventory usage via backflushing
– Explodinganenditem’sBOMtodeterminethequantitiesofthe
components that were used to make the item
– Pegging enables better customer service

23
Q

MRP Requirements

A
  • a computer and the necessary software

- accurate and up to date (master schedules, bills of materials, inventory records)