Project Management 3351 - Midterm Flashcards

1
Q

project management is an application of skills that ensures a project is delivered: (3 things)

A

on time, on budget, to specs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What 4 areas define a project?

A

temporary, defined purpose, time frame, resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the 3 constraints in “The Triple Constraint”

A

scope, schedule, budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are ITPM roles?

A

project stakeholders, project manager, project sponsor, technical experts, subject matter experts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the difference between a project portfolio and program?

A

portfolio - collection of project managed collectively to align with organization strategy
program - collection of projects within a portfolio whose activities are coordinated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which of the following is considered a major attribute?

  • deliverable
  • lessons learned
  • stage gate
  • time frame
  • baseline plan
A

time frame

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

which of the following variables an influence selection of IT projects?

  • culture
  • environment
  • politics
  • strategy
  • all
A

all

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

the triple constraint suggest that stakeholders and sponsors must communicate effectively?

A

false

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

the triple constraint refers to:

A

scope, budget, schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

having subject matter experts on the dev team is better than teaching technical experts the subject matter

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

assumptions are what help determine scope, schedule and budget when assessing project risk

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what is a “challenged project”?

A

a project that was completed over budget, over schedules and did not meet all specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what is an “impaired project”?

A

a project that is cancelled before completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

according to the CHAOS study most IT project are completed on time but over budget?

A

false

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

what are the two main aspects of the socio-technical approach?

A
  • business and organizational aspects must be addressed as well (not just technical)
  • end users and stakeholders should be involved early to ensure a vested interested in the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

what is the premise behind the value-driven approach to it projects?

A

decision whether or not to invest in IT should be based on the value its completion adds to the organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

what defines the project management approach to IT projects

A

predefined processes, resource control, communication systems in place

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

what is the knowledge management approach?

A

lessons learned, best practices, shared knowlege

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

According to the CHAOS study how many projects were cancelled before completion? complete but challenged?

A

31%, 53%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

what are the common phases of the project life cycle ?

A

define project goal, plan project, execute project plan, close project, evaluate project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

what is the deliverable for the define project goal phase?

A

a business case

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

the project charter clarifies the projects goal and objectives in terms of what?

A

scope, schedule, budget, quality objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

what is the deliverable for the project charter phase?

A

project charter & plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

what are the deliverable for the execute and control the project phase?

A

requirement doc, software testing doc, design doc, software system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

what is the deliverable for the close project phase?

A

final report and presentation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

what are the four areas of focus for the evaluate project success phase?

A

first) project manager - what went well with the team, what could have been done better
second) evaluation between pm and individual team members
third) outside party review of project, pm and project team
fourth) project evaluation in terms of value added

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

what are phase exits, stage gates and kill points?

A

phase-end reviews of key deliverables, with immediate actions resulting from them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

what is fast tracking?

A

starting next phase before approval is obtained for current phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

what are the system development life cycle stages?

A

requirement elicitation, analysis, system design, object design, implementation, testing, delivery, maintenance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

what is the SDLC?

A

software design life cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

what phase does the SDLC fall into within the gerater project life cycle?

A

execute and control the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

how are project management processes and product-oriented processes connected?

A

project management processes support all activities involved in the product oriented process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

what happens when only project management processes are focused on?

A

the projects scope is not well defined and a quality system is difficult to achieve due to lack of expertise

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

what happens when only the product oriented processes are focused on?

A

work isn’t completed on time, budget isn’t set, and specifications are forgotten or not met

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

what are the 5 PMBOK project management process groups?

A

initiating, planning, executing, controlling, closing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

what are the 7 processes of PRINCE2?

A

start project, initiate project (more detail), direct project, control stage, manage project delivery, manage stage boundaries, close project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

what are the 7 PRINCE2 themes to aid with project goal achievement?

A

business case, organization, risk, quality, planning, change, describe the progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

what are the 7 PRINCE2 Universal guiding principles?

A

business case driven, product focus, lessons learned, manage the stage, adapt to project, manage by exception, accountability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

what are the four stages of learning cycles?

A
  1. understand and frame problem
  2. plan
  3. act
  4. reflect and learn
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

what 3 criteria are used to assess team learning?

A

speed, depth, breadth (impact)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

IT project methodology provides a strategic level plan for managing and controlling IT projects?

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

a business case is a deliverable that outline a projects goal and several alternatives or options

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

project management processes include scope, schedule, budget and quality

A

false

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

the sdlc is a deliverable from the project charter

A

false

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

the project charter is a key deliverable for the second phase

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

scope and schedule are examples of

A

project management objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

the correct sequence of the generic project life cycle is:

A

definition, planning, execution, closing, evaluation of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

which of the following is not a characteristic of prototyping?

  • iterative
  • deployed when developing high volume transaction processing system
  • deployed when requirements of new system are not well understood
  • RAD approach
A

deployed when…

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

what does MOV stand for?

A

measurable organizational value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

what 4 pillars support the MOV?

A

scope, schedule, budget, quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

what is the process for developing the MOV?

A
  • identify area of impact
  • identify desired value of the project
  • develop appropriate metric
  • set time frame
  • verify a get agreement from project stakeholders
  • summarize MOV
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

what are some questions to ask when identifying the desired value of the project?

A

better? faster? cheaper? do more?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

the MOV should be adjusted at each phase of a project to align with execution

A

false

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

the MOV should explicitly name what tech the project will require

A

false

55
Q

a projects scope is a list of resources available to the projects team

A

false

56
Q

project management processes recommended by PMBOK include scope, schedule, budget, and quality

A

false

57
Q

under PRINCE2 the project board is accountable for project’s success or failure

A

true

58
Q

what is the purpose of a business case?

A

to provide senior management with all information needed to make a decision regarding project funding

59
Q

what are the 3 steps to considering risk?

A

identification, assessment, response

60
Q

what is included in total cost of ownership?

A

direct costs (upfront)
ongoing costs
indirect costs

61
Q

what are examples of benefits of ownership?

A

increasing high value work, improving accuracy and efficiency, improving decision making, improving customer service, etc

62
Q

what is the focus of most financial models related to projects?

A

cash flow

63
Q

what is the formula for payback

A

initial investment / net cash flow

64
Q

what is the ROI formula

A

total expected profit / total expected costs

65
Q

does a business case provide a project budget?

A

false

66
Q

a business case provides a feasibility analysis

A

true

67
Q

a business case is the key deliverable for which phase?

A

1

68
Q

early identification of project team is a reason for recruiting a core team to develop the business case

A

false

69
Q

enhanced credibility is a reason for recruiting a core team to develop the business case

A

true

70
Q

alignment with organization goals is a reason for recruiting a core team to develop the business case

A

true

71
Q

a shared sense of ownership is a reason for recruiting a core team to develop the business case

A

true

72
Q

access to real costs is a reason for recruiting a core team to develop the business case

A

true

73
Q

determining whether employees will be able to adapt to planned change is __________ feasibility

A

organizational

74
Q

determining whether the proposed solution will work within the software architecture is a measure of _______ feasibility

A

technical

75
Q

TCO includes only direct/upfront costs and ongoing expenditures

A

false

76
Q

feasibility focuses on what can go wrong and what must go right

A

false

77
Q

feasibility focuses on whether or not an alternative is worth pursuing

A

true

78
Q

TBO should address the benefits of an alternative over its entire useful life

A

true

79
Q

all cash flows over the useful life of a project must be included in payback analysis

A

false

80
Q

payback analysis is often a failure due to what consideration that is failed to be taken into account/

A

the time value of money

81
Q

npv takes into account all relevant cash flows and a companys irr

A

true

82
Q

riskier project alternatives has lower breakeven points

A

false

83
Q

breakeven is always expressed in currency

A

false

84
Q

a scoring model uses weights and scores based on people judgements to evaluate qualitative items

A

true

85
Q

each phase ought to have at least one deliverable at the end

A

true

86
Q

a baseline plan defines what?

A

the scope, schedule and budget of a project

87
Q

a project that increases market share impacts what area of an organization

A

strategic

88
Q

a project that increases profit impacts what area of a business

A

financial

89
Q

a system developed using the projet life cycle methodology is called a legacy system

A

false

90
Q

a tangible and verifiable product of work is called a _____

A

deliverable

91
Q

what are the differences between a project charter and a project plan?

A

a project charter acts as a sort of contract between the pm and the organization sponsoring the project - it outlines project infrastructure and resources, summarizes budget and schedule

a project plan is a tactical plan detailing how the project resources will be used in order to develop a budget and schedule

92
Q

a project charter serves as a ________ between _______ and ________

A

contract, project manager, projet sponsor

93
Q

a project charter documentes a projects _____, summarized the details of _________, show explicit ________ to the project

A

MOV, the project plan, committment

94
Q

things that should be included in charter:

A

identification, stakeholders, description, mov, scope, schedule, budget, quality issues, resources, assumptions, risk, administration, acceptance, approval, references, terminology

95
Q

a project charter and project plan make up the projects strategic plan

A

false

96
Q

the project sponsor is responsible for creating the project charter

A

false

97
Q

the project charter and project plan should be delopped side by side (at the same time

A

true

98
Q

the project charter + project plan are a _____ plan?

A

tactical

99
Q

things that must go right in order for the project plan to be completed are what?

A

assumptions

100
Q

a kickoff meeting is held to develop the project plan

A

false

101
Q

what is a baseline plan

A

an approved project plan

102
Q

what are the benefits of a kick off meeting?

A

bring closure to planning phase, signal initiation of next phase, energizes stakeholders

103
Q

why must the MOV be finalized during the project planning phase?

A

because any changes afterwards will require the plan to be fundamentally revised

104
Q

define “scope”

A

product or services to be provided by the project - includes all project deliverables

determines what is part of the projects team work and what is not

105
Q

what is the baseline plan used for primarily?

A

a benchmark for success

106
Q

what are the steps in the scope management process?

A

initiation, planning, definition, verification, change control

107
Q

what is project oriented scope?

A

deliverables that support the management and development of the project itself

108
Q

what are product oriented scope?

A

deliverables that support the actual application system solution

109
Q

what are the headers for a deliverable definition table?

A

deliverable, structure, standards, approval needed by, resources required

110
Q

what can be developed once deliverables have been defined through a DDT?

A

a deliverable structure chart (DSC)

111
Q

what does the deliverable structure chart define?

A

detailed work packages

112
Q

what is a context dataflow diagram (DFD)

A

a modeling tool used to refine scope boundaries - high level representation of a system depicting all inflows and outflows of data and information between system and external entities

113
Q

what are the items on the scope verification checklist

A

MOV, deliverables, quality standards, milestones, review and acceptance

114
Q

what is scope grope?

A

scope poorly defined - can’t get a handle of the scope of the product

115
Q

what is scope creep?

A

adding to the scope without considering impact on resources

116
Q

what is scope leap?

A

huge sudden changes in scope

117
Q

a projects scope is a list of resources?

A

false

118
Q

scope planning is an area of scope management, where authority and resources commit to developing the scope management plan

A

FALSE

119
Q

scope change control protects the scope boundary form expanding

A

true

120
Q

no new features can be addded once the scope has been officialy defined

A

false

121
Q

scope statement documents clients needs and expectations

A

true

122
Q

the scope includes both what is and is not part of the pojrect teams work

A

true

123
Q

project scope is a statement detailing the features and functions that must support the it solution

A

false

124
Q

project scope is statement detailing the deliverables and activities that support the it solution

A

true

125
Q

actors are the people or external systems that are elements of a DFD

A

false

126
Q

context level data flow diagrams are an example of a __________ oriented scope definition tool

A

product

127
Q

a tangible verifiable work product is called a?

A

deliverable

128
Q

a significant event or achievement is called a?

A

milestone

129
Q

what is the risk of too little details in WBS

A

overly optimistic schedule and buget

130
Q

what ist he risk of too much detail in WBS

A

micromanagement

131
Q

what six characteristics must an activity possess to be considered complete?

A

measurable status, bounded, deliverable, time/cost can be estimated, acceptable duration, independent work assigments

132
Q

what is one way to ensure the the WBS has the approriate level of detail?

A

involve the people who do the work in the development

133
Q

the WBS is subdivided into smaller components called ?

A

work packages