Project Management Flashcards
EV
Earned Value
AC
Actual Costs
PV
Planned Value
CV
Cost Variance
SV
Schedule Variance
CPI
Cost Performance Index
SPI
Schedule Performance Index
EAC
Estimated Cost at Completion
BAC
Budgeted Cost at Completion
VAC
Variance at Completion
ECD
Estimated Completion Date
ECTC
Estimated Cost to Complete
SC
Scheduled Completion Date
CV=
EV-AC
SV=
EV-PV
CPI=
EV/AC
SPI=
EV/PV
VAC=
BAC-EAC
EAC1=
BAC-CV
EAC2=
BAC/CPI
ECD1=
SC-SV(time)
ECD2=
SC(time taken to perform work to date/time work should have taken)
Assumption 1:
Outstanding work will be completed at original budget at completion
Assumption 2:
Outstanding work will be completed at same cost factor observed in project so far
Stages of Project Control Analysis:
- Define work breakdown structure
- Identify and develop resource schedule
- Develop time-phased budget
- Develop actual cost of work performed
- Collect percentage complete and multiply by original planned budget to determine the value of the work completed (EV)
- Complete variance analysis
Gantt charts can be used for
effective communication in monitoring time performance across all levels
A tracking Gantt chart can be useful
- to track and trend schedule performance
- to add actual and revised time estimates
- to provide a quick overview of project status
Benefits of earned value analysis:
- Disciplined planning and risk management
- Good project visibility
- Objective and quantitative performance measurement
- Early indication of problems
- Ability to accurately predict project cost and schedule
Drawbacks of schedule variance:
- Does not show individual activity contribution on graphs
- Does not distinguish between critical and non-critical activities
- Directly concerned with schedule for spending money and not directly concerned with time-based schedule
- Can be difficult to visualise
If CV>0
underbudget
If CV<0
overbudget
If SV>0
ahead of schedule
If SV<0
behind schedule
Scope creep is
the cumulative effect of minor refinements to the original project scope
Scope creep is common early in projects because
- additional features are added
- new technologies are discovered
- poor design assumptions are found
Scope creep can be reduced by
having a well defined scope statement and stating the limitations on the project at the start
Advantages of scope creep:
Small changes could decrease time to market or reduce cost
Disadvantages of scope creep:
- Leads to delays or cost overruns
- Reduces team motivation
Baseline changes are
changes during the project life cycle that are inevitable
Examples of baseline changes are
changes in government policy, the economy, or unforeseen problems
Baseline changes should only be accepted if:
- the project will fail without the change
- the project will improve significantly because of the change
- the customer demands the change and will pay
It is important that information flow
is clearly mapped and stakeholders are informed
Engineers should value organisational strategy because:
- They must be able to make appropriate decisions and adjustments
- They must be able to be a successful advocate for themselves
Strategy decribes
how an organisation intends to compete with the resources available in the existing a perceived future environment
There are four steps to the implementations of an organisation’s strategy:
- Review and define “mission”, what the organisation intends to be
- Create long-range goals and objectives; specific, tangible and measurable actions
- Analyse and formulate strategies to reach these objectives
- Implement strategies through projects
A portfolio management system involves
- the classification of projects
- the criteria used to select them
- ensuring a good range of sources of project proposals are used
- the evaluation of those proposals
A portfolio management systems ensures
projects are aligned with strategic goals and prioritised suitably
Benefits of project portfolio management:
- Disciplined project selection process
- Ensures projects are aligned with strategic targets
- Projects prioritised on measurable, common criteria and not emotions and internal politics
- Supports a move towards fulfilling organisation’s strategy
Projects can be classified in three ways:
Compliance and emergency, operational, and strategic
Steps for determining whether to invest in a project:
- Define the project
- Define the stakeholders
- Define the decision criteria
- Calculate the economic benefits
- Estimate the economic costs
- Formulate the net benefit stream
- Complete cost-benefit analysis
- Complete sensitivity analysis
- Assess other benefits not included in CBA
- Report the findings
To complete cost-benefit analysis it is necessary to
convert into a common unit of measurement, most commonly money, this requires subjective judgements
If net present value > 0
Invest
If net present value < 0
Don’t invest
Net present value=
Cost for period 0 + the sum for periods 1 to t of ((cost for period t/(1 + discount rate for period t)^t)