Pert diagrams
used for managing many large and complicated projects. Depends on statistics so not common in the design profession
WBS - work breakdown structure
tree like diagram or list of project tasks and subtasks with budgets and durations. Design professions have adopted this.
CPM - Critical path method
network diagram that graphically shows a project, predicts the time needed to complete and highlights critical tasks to maintaining schedule
0% Drawing Set
Drawing not started
25% Drawing Set
Drawing started, plans, sections, elevations and details still in progress
50% Drawing Set
Plans, sections, elevations, or details drawn but not dimensioned - no notes or material call-outs
90% Drawing Set
Drawing is complete but not submitted for quality-control check
100% Drawing Set
Drawing has been checked for quality control and comments on drawings have been corrected
specifications 0% 50% 90% 100%
0% - specification not started
50% - specification section has been started and is somewhere in progress
90% - specification complete but not checked for quality control
100% - specification checked for QC and corrected
Bar or Gantt Chart Schedule
oldest graphic schedule type. easy to set up, intuitive to read and understand, suitable for small and medium sized projects
Milestone List
A list of due dates for critical or contract-defined significant activities. Good for simple projects
Landscape Architects may be licensed under these two acts
Title Act and Practice Act
The order of the following RFP, Work Plan, S.O.S., Budget
RFP, Scope of Services, Work Plan, Budget
The order of bidding and supervising a construction process for a project:
Certification of payment, contract signing, addenda, bid tabulation, notice of award
Addenda Bid Tabulation Notice of Award Contract Signing Certification of Payment