Project Management Flashcards
Goals for project management
To reach the end of the project
To reach the end on budget
To reach the end on time
To reach the end safely
To reach the end error-free
To reach the end meeting everyone’s expectations
Goals
constitute the very purpose of project management and should be considered universal principles that do not change from project to project (and therefore should be achieved in every project).
Objectives
describe project-specific outcomes or results and states that objectives can be both quantifiable or measurable as well as subjective (e.g., aesthetic).
5 phases of project management
Start: the project begins
Planning: figuring out how to perform the work
Design: the project’s overall design is worked out
Production: preparation of construction documents and/or other deliverables based on the overall design
Closeout: the project work is completed
6 activities of project management
Defining
Defining the design project’s scope of work, budget, and schedule-in effect, determining the project objectives.
Planning
Planning the work effort so that the project scope of work, budget, and schedule will be met.
Directing
Directing the design team so that the project objectives will be met while staying within budget and on schedule.
Coordinating
Coordinating the efforts of the design team so that interdisciplinary information flows smoothly and at the right time.
Monitoring
Monitoring the design team’s work product and progress against the project objectives, budget, and schedule.
Learning
Learning from the project: what went right, what went wrong, and how to improve performance on the next project.
Project Work Plan
A Project Work Plan (PWP) is an organizational framework to plan how and in what sequence project work will occur.
The PWP therefore takes the scope of services (outlined in the contract documents and client agreement) and divides this scope into specific tasks and clarifies how and when this work will be accomplished by the design team. The PWP will also establish the project communication procedures/hierarchy and the reporting structure, as well as safety, accounting and quality control procedures (e.g. CAD standards). Finally, the PWP provides the design project’s management team with a high-level plan of the project work so that they can assess whether the project has been properly planned and—as the project progresses—if the project work is being completed in reference to its stated goals
Objective of PWP: Definition of project objectives
Recall that objectives are defined by Ramroth as project-specific results. Project objectives, therefore, can be defined through determining:
What needs to be done
When it needs to be done
Who will do it and how much it will cost
Objective of PWP: Identification of the project team
What disciplines are needed to accomplish the project? (e.g. architect, civil engineer, structural, mechanical, etc.)
Are these disciplines available within the design firm, or will outside consultants be needed? Will the landscape architect be an outside consultant?
How will the scope of work be established between these various parties?
How will information be disseminated within the project team?
Objective of PWP: Breakdown of the project into task budgets
every “task” has three elements, and they are as follows:
An objective (with a measurable outcome)
A duration (the length of time required to complete the objective)
A level of effort (the number of labor hours budgeted to accomplish the objective)
Objective of the PWP: Development of the project schedule
The project schedule is critical to effective project management. It applies a timeline to the tasks developed in step 3 of the Project Work Plan and tells the project team when deliverables are due throughout the course of the project. The project schedule also functions as a benchmark against which project progress can be compared to determine if the project is on-schedule. Project schedules should always be created around major project milestones and conform to the dates/timelines established in the design contract
Objective of the PWP: Establishment of the project QC
ensure that the project is as complete and accurate as possible. In the context of quality control, completeness and accuracy are defined both in reference to the client’s project objectives and the contract as well as any requirements set forth by governmental review agencies.
QC during the construction phase is addressed through the following means:
Submittals and samples of prefabricated/manufactured products provided to the designer for review and approval
Mockups of elements constructed on site to serve as a reference for larger scale work conducted on the site
Materials testing to ensure installation quality
Direct observation of installation work (e.g. watching the landscape contractor install plant material)
Objective of the PWP: Identification of other project-specific procedures and standards
The last component of a Project Work Plan is a catch-all category intended to cover any content not covered in the prior five sections. As such, there is no definitive statement for what might be found under “other project-specific procedures and standards”, but within the context of landscape architectural practice, this category could include a project work safety plan that outlines safety procedures, required equipment and communication protocols required during field work or visits to a construction site. This section might also cover elements of CAD/drafting standards in addition to that found in the quality control program, as well as invoicing procedures, templates/standard formats for meeting minutes, telephone calls and other correspondence
Project Schedule: Milestone List
A milestone list is the most basic form of project schedule and can be used to quickly and simply convey a basic project timeline. Milestone lists are often used in small projects, and they often appear in Request for Proposal (RFP) documents. As such, milestone lists are used to convey a broad schedule for complex projects, with the milestone list transforming into a bar/Gantt chart or CPM schedule as the project progresses.
Project Schedule: Bar Chart
Bar or Gantt charts are the most common graphic schedule used in the design profession largely because they are easy to create and update and—from clients to the general public to other designers—they are easily understood. Bar charts are effective in small and medium-scale design projects and are also used in conjunction with CPM schedules in larger, complex projects.
Project Schedule: Critical Path Method
Critical Path Method (CPM) schedules are somewhat similar in appearance to bar charts, however—unlike bar charts—CPM schedules identify tasks that are project-critical. In other words, CPM schedules illustrate the relationships and interdependencies between various tasks and graphically highlight the most important tasks. Tasks are generally considered to be critical when NOT meeting the task deadline will directly and irreversibly impact the overall project schedule. CPM schedules are therefore used on large, complex projects that require extensive coordination between various tasks and disciplines