Project Management Flashcards
The four constraints of a project are: time, cost, scope and quality. What are the elements of a project plan used to plan and manage these 4 constraints?
schedule, budget, product backlog and change control procedures, quality plan
A milestone is a significant event during a project used to measure progress. A milestone is usually scheduled, but it doesn’t have to be.
True
Why is it necessary to identify the dependencies between project tasks?
To calculate the critical path through the schedule
&
To create schedules. Task dependencies limit the times when tasks can be scheduled.
Four analysts attend a design review meeting lasting 2 hours. One analyst didn’t make any meaningful contributes during the review. What was the duration of the meeting? How much effort was expended during the meeting? (Assume the standard definition of the term effort used when planning a project.)
2 hours; 8 hours
It doesn’t even matter if the analyst not making any comments did or didn’t prepare. He or she participated which represents 2 hours of effort. You can expend effort without getting results.
The slack time for all of the tasks on the critical path is zero.
True
There can be only one critical path in the schedule.
False
It is possible to calculate the critical path for a project knowing only the tasks, their dependencies and their duration estimates.
True
It is possible to calculate the critical path for a project knowing only the tasks, their dependencies and their effort estimates.
False
You can plan and schedule work at different levels of detail. What are the advantages of planning detailed tasks rather than broad objectives?
More control over the project (more tasks means more opportunities for feedback and course corrections that can be made sooner)
Better estimates of overall effort
More likely to meet deadlines because schedule slips are identified sooner
Which of the following are you least likely to find in a project charter?
Goals and objectives Rough schedule and budget estimates Project success criteria Detailed requirements Constraints and assumptions Major risks and obstacles to success
Detailed Requirements
Which of the following best describes the purpose of the project charter?
To define the expected project outcome
You need at least a rough schedule in order to do resource leveling.
True
Resource leveling is the practice of staffing with individuals at a similar skill level to make scheduling easier. (If individuals are at the same skill level they can be moved from one task to another without reestimating the time needed to complete the task.)
False
Staffing a project with individuals at the same skill level might make resource leveling easier, but resource leveling is not a staffing issue. Resource leveling is a process for leveling out the hills and valleys in a schedule (i.e. moving tasks around in the schedule and reassigning tasks so that work effort is evenly distributed among days and equitably among individuals) Note, resource leveling may also be needed to resolve conflicts for resources.
Example of resource leveling
A family planning a vacation makes an initial schedule of activities. Upon review they decide to move around a few of the planned activities in the schedule in order to better balance the number and duration of activities planned for each day.
In which of the following life cycle models are you more likely to find predictive planning? Waterfall Spiral Evolutionary Prototyping Code and fix
Waterfall