Project Lifecycles Flashcards
1
Q
Predictive
A
Fixed requirements
Activities performed once for the entire project
Single delivery
Goal to manage cost
2
Q
Iterative
A
Dynamic requirements
Activities repeated until correct
Single delivery
Goal is correctness of solution
3
Q
Incremental
A
Dynamic requirements
Activities performed once for a given increment
Frequent smaller deliveries
Goal is speed
4
Q
Agile
A
Dynamic requirements
Activities repeated until correct
Frequent small deliveries
Goal is value via frequent deliveries and feedback