Formulas Flashcards

1
Q

ETC = EAC-AC

A

Estimate to Complete= Estimate at Completion - Actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

n(n-1)/2

A

Number of Communication Channels

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

CPI = EV/AC

A

Cost Performance Index= Earned Value/ Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

CV = EV-AC

A

Cost Variance = Earned Value - Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Definitive Range

A

Rom Range (-25% to + 75%)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

EAC = AC+(BAC-EV)/(CPI*SPI)

A

Estimate at Completion = Actual Cost + (Budget at Completion- Earned Value) / (Cost performance index* Schedule Performance Index)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

EAC = AC+BAC-EV

A

Estimate at Completion= Actual Cost + Budget at Completion - Earned value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

EAC = AC+ETC

A

Estimate at Completion = Actual Cost + Estimate to Complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

EAC = BAC/CPI

A

Estimate at Completion= Budget at Completion / Cost Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Float LF-EF

A

LF-EF- Late Finish - Early Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Float LS-ES

A

LS-ES Late Start - Early Start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

FLOAT SLACK

A

To calculate float, we always start late LS-ES or LF-EF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

PERT Estimation = (O + 4M + P)/6

A

most likely, Pessimistic, Optimistic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

ROM Rough Order of Magnitude

A

Rom Range (-25% to + 75%)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

SPI = EV/PV

A

Schedule Performance Index= Earned Value/ Planned Value or present Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

STD DEVIATION = (P-O)/6

A

most likely, Pessimistic, Optimistic

17
Q

SV = EV-PV

A

Schedule Variance = Earned Value - Planned Value or present Value

18
Q

TCPI = (BAC-EV)/ (BAC-AC)

A

To-Complete Performance Index = (Budget at Completion- Earned Value) /(Budget at Completion- Actual Cost)

19
Q

Three Point Estimating

A

Triangular Distribution = ML + P + O / 3 (Most Likely + Pessimistic + Optimistic) / 3

20
Q

VAC = BAC-EAC

A

Variance at Completion=Budget at Completion -Estimate at Completion