Formulas Flashcards
ETC = EAC-AC
Estimate to Complete= Estimate at Completion - Actual cost
n(n-1)/2
Number of Communication Channels
CPI = EV/AC
Cost Performance Index= Earned Value/ Actual Cost
CV = EV-AC
Cost Variance = Earned Value - Actual Cost
Definitive Range
Rom Range (-25% to + 75%)
EAC = AC+(BAC-EV)/(CPI*SPI)
Estimate at Completion = Actual Cost + (Budget at Completion- Earned Value) / (Cost performance index* Schedule Performance Index)
EAC = AC+BAC-EV
Estimate at Completion= Actual Cost + Budget at Completion - Earned value
EAC = AC+ETC
Estimate at Completion = Actual Cost + Estimate to Complete
EAC = BAC/CPI
Estimate at Completion= Budget at Completion / Cost Performance Index
Float LF-EF
LF-EF- Late Finish - Early Finish
Float LS-ES
LS-ES Late Start - Early Start
FLOAT SLACK
To calculate float, we always start late LS-ES or LF-EF
PERT Estimation = (O + 4M + P)/6
most likely, Pessimistic, Optimistic
ROM Rough Order of Magnitude
Rom Range (-25% to + 75%)
SPI = EV/PV
Schedule Performance Index= Earned Value/ Planned Value or present Value