Project Integration Managment Flashcards
What is the Initiating Process for Integration Managment?
Develop Project Charter
What are the Outputs for Develop Project Charter?
- Project Charter
- Assumptions Log
What are the Planning Processes for Integration Managment?
Develop PM Plan
What are the Outputs for Develop PM Plan?
• PM Plan
What are the Executing Processes for Integration Managment?
Direct and Manage Project Work
Manage Project Knowledge
What are the Outputs for Direct and Manage Project Work?
• Deliverables
• Work Perf Data
• Issues Log
• Change Requests
• PM Plan Updates (4.2)
o Any Component
• Project Documents Update
o Activity List (6.2)
o Assumptions Log (4.1)
o Lessons Learned Register (4.4)
o Requirements Documentation
o Risk Register
o Stakeholder Register
• OPA Updates
What are the Outputs for Manage Project Knowledge?
- Lessons Learned Register (25)
- PM Plan Updates (4.2)
o Any Component
• OPA Updates
What are the Monitor and Controlling Processes for Integration Managment?
Monitor and Control Project Work
Perform Integrated Change Control
What are the Outputs for Monitor and Control Project Work?
• Work Perf Reports
• Change Requests
• PM Plan Updates (4.2)
o Any Component
• Project Documents Updates
o Cost Forecast
o Issues Log
o Lessons Learned Register (4.4)
o Risk Register
o Schedule Forecast
What are the Outputs for Perform Integrated Change Control?
• Approved Change Requests
• PM Plan Updates (4.2)
• Project Documents Updates
o Change Log
What are the Closing Processes for Integration Managment?
Close Project or Phase
What are the Outputs for Close Project or Phase?
• Final Product, Service or Result Transition
• Final Report
• OPA Updates
• Project Documents
o Lessons Learned