Project Cost Management Flashcards
1
Q
What are the Planning Processes for Project Cost Man?
A
- 1 Plan Cost Mgmt
- 2 Estimate Costs
- 3 Determine Budget
2
Q
What are the Outputs for Plan Cost Man?
A
7.1 Plan Cost Mgmt
• Cost Man Plan
3
Q
What are the Outputs for Estimate Costs
A
7.2 Estimate Costs
• Cost Estimates
• Basis of Estimates
4
Q
What are the Outputs for Determine Budget
A
7.3 Determine Budget
• Cost Baseline
• Proj Funding Req
5
Q
What are the M & C processes for Project Cost Man?
A
7.4 Control Costs
6
Q
What are the Outputs for Control Costs?
A
7.4 Control Costs
• Cost Forecasts