Develop Project Charter
Inputs
- Project Statement of Work
- Business Case
- Agreements
- Enterprise Environmental Factors
- Organizational Process Assets
Develop Project Charter
Tools & Techniques
- Expert Judgement
- Facilitation Techniques
Develop Project Charter
Outputs
- Project Charter
Develop Project Management Plan
Inputs
- Project Charter
- Outputs from other processes
- Enterprise environmental assets
- Organizational process assets
Develop Project Management Plan
Tools & Techniques
- Expert Judgment
- Facilitation Techniques
Develop Project Management Plan
Outputs
- Project Management Plan
Direct and Manage Project Work
Inputs
- Project Management Plan
- Approved Change Requests
- Enterprise Environmental Assets
- Organizational Process Assets
Direct and Manage Project Work
Tools & Techniques
- Expert Judgement
- Project management information system
- Meetings
Direct and Manage Project Work
Outputs
- Deliverables
- Work Performance Data
- Change Requests
- Project Management Plan updates
- Project document updates
Monitor and Control Project Work
Inputs
- Project Management Plan
- Schedule Forecasts
- Cost Forecasts
- Validated Changes
- Work Performance Information
- Enterprise Environmental Assets
- Organizational Process Assets
Monitor and Control Project Work
Tools & Techniques
- Expert Judgement
- Analytical Techniques
- Project Management Information System
- Meetings
Monitor & Control Project Work
Outputs
- Change Requests
- Work Performance Reports
- Project Management Plan
- Project document updates
Perform Integrated Change Control
Inputs
Perform Integrated Change Control
Tools & Techniques
- Expert Judgment
- Meetings
- Change Control tools
Perform Integrated Change Control
Outputs
- Approved Change Requests
- Change Log
- Project Management Plan updates
- Project documents updates
Close Project or Phase
Inputs
Close Project or Phase
Tools & Techniques
- Expert Judgement
- Analytical Techniques
- Meetings
Close Project or Phase
Outputs
- Final Product, service, or result transition
- Organizational Process Assets updates
- Project Statement of Work
- Business Case
- Agreements
- Enterprise Environmental Factors
- Organizational Process Assets
Develop Project Charter
Inputs
- Expert Judgement
- Facilitation Techniques
Develop Project Charter
Tools & Techniques
- Project Charter
Develop Project Charter
Outputs
- Project Charter
- Outputs from other processes
- Enterprise environmental assets
- Organizational process assets
Develop Project Management Plan
Inputs
- Expert Judgment
- Facilitation Techniques
Develop Project Management Plan
Tools & Techniques
- Project Management Plan
Develop Project Management Plan
Outputs
- Project Management Plan
- Approved Change Requests
- Enterprise Environmental Assets
- Organizational Process Assets
Direct and Manage Project Work
Inputs
- Expert Judgement
- Project management information system
- Meetings
Direct and Manage Project Work
Tools & Techniques
- Deliverables
- Work Performance Data
- Change Requests
- Project Management Plan updates
- Project document updates
Direct and Manage Project Work
Outputs
- Project Management Plan
- Schedule Forecasts
- Cost Forecasts
- Validated Changes
- Work Performance Information
- Enterprise Environmental Assets
- Organizational Process Assets
Monitor and Control Project Work
Inputs
- Expert Judgement
- Analytical Techniques
- Project Management Information System
- Meetings
Monitor and Control Project Work
Tools & Techniques
- Change Requests
- Work Performance Reports
- Project Management Plan
- Project document updates
Monitor & Control Project Work
Outputs
Perform Integrated Change Control
Inputs
- Expert Judgment
- Meetings
- Change Control tools
Perform Integrated Change Control
Tools & Techniques
- Approved Change Requests
- Change Log
- Project Management Plan updates
- Project documents updates
Perform Integrated Change Control
Outputs
Close Project or Phase
Inputs
- Expert Judgement
- Analytical Techniques
- Meetings
Close Project or Phase
Tools & Techniques
- Final Product, service, or result transition
- Organizational Process Assets updates
Close Project or Phase
Outputs