Formulas & Use Definitions Flashcards
Planned Value (PV)
PV = EV-SV
Schedule Variance (SV)
SV = EV-PV
Earned Value (EV)
EV = CV+AC
Actual Costs (AC)
AC = EV-CV
Cost Variance (CV)
CV = EV - AC
Estimate At Completion (EAC)
EAC = AC + ETC
Estimate to Complete (ETC)
ETC = EAC - AC
EAC accepting performance to date, but staying within budget
EAC = AC + BC - EV
EAC accepting performance to date will continue into the future (work continues at current CPI)
EAC = BAC/CPI
TCPI using BAC (assuming budgeted cost)
EAC = (BAC - EV)/(BAC-AC)
TCPI using EAC (assuming deviation from budget)
EAC = (BAC-EV)/(EAC-AC)
Schedule Performance Index (SPI)
SPI = EV/PV
Cost Performance Index (CPI)
CPI = EV/AC
Budget at Completion (BAC)
BAC = PV (at project completion) or BAC at point in time = PV
Communication Channels
n(n-1)/2