Formulas & Use Definitions Flashcards

1
Q

Planned Value (PV)

A

PV = EV-SV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Schedule Variance (SV)

A

SV = EV-PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Earned Value (EV)

A

EV = CV+AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Actual Costs (AC)

A

AC = EV-CV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Variance (CV)

A

CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Estimate At Completion (EAC)

A

EAC = AC + ETC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Estimate to Complete (ETC)

A

ETC = EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

EAC accepting performance to date, but staying within budget

A

EAC = AC + BC - EV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

EAC accepting performance to date will continue into the future (work continues at current CPI)

A

EAC = BAC/CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

TCPI using BAC (assuming budgeted cost)

A

EAC = (BAC - EV)/(BAC-AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

TCPI using EAC (assuming deviation from budget)

A

EAC = (BAC-EV)/(EAC-AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Schedule Performance Index (SPI)

A

SPI = EV/PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Cost Performance Index (CPI)

A

CPI = EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Budget at Completion (BAC)

A

BAC = PV (at project completion) or BAC at point in time = PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Communication Channels

A

n(n-1)/2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

EAC assuming varied schedule performance (both SPI and CPI not equal to 1)

A

EAC =AC + [(BAC - EV)/(CPI * SPI)]

17
Q

Triangular Distribution (used when triangular estimate or triangular distribution)

A

tE = (tO + tM + tP)/3

18
Q

Beta Distribution (assumes normal distribution)

A

tE = (tO + 4tM + tP)/6

19
Q

Standard Deviation

A

(Std Dev = tP - tO)/6 = sq root of project variance

Std Dev +/- 3 sigma = 99.73% probability

20
Q

EMV

A

Sum of (Cost x probability)

21
Q

Total Float

A

Late Start - Early Start (LS - ES)

22
Q

Early Finish calculated by:

A

ES + Duration - 1

23
Q

Late Start calculated by:

A

Late Finish - duration + 1

24
Q

Initial Risk Rating

A

Probability x Impact

25
Q

Current Risk Rating

A

CRR= [IRR+(Likelihood of mitigation * impact of mitigation)]/2

26
Q

BAC

A

BAC = EAC * CPI

27
Q

Point if Total Assumption (PTA)

A

PTA = [(ceiling price - target price)/Buyer’s share ratio] + target cost

Target price = target cost + profit

28
Q

Net Present Value (NPV)

A

NPV = Future values / (1+r)^n

29
Q

EV with SV & PV

A

EV = SV + PV

30
Q

EV with CPI & AC

A

EV = CPI * AC