Project Integration Management Flashcards

1
Q

What includes the high level requirements and risks, and the preliminary project budget and schedule?

A

Project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What gives authority to the PM to allocate resources to a project?

A

Project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the inputs to make the business charter?

A
  1. business documents (use case)
  2. OPAs
  3. enterprise environmental factors
  4. agreements - MSA, MOU
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are data gathering tools that can be used to make the project charter?

A

data gathering - focus groups, interviews, brainstorming

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What occurs during developing the project management plan?

A

Process of defining, preparing, and coordinating all plan

components and consolidating them into an integrated project management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the project management plan?

A

how project will be executed, monitored/controlled, and closed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the 4 baselines in the project management plan?

A
  1. scope
  2. schedule
  3. cost
  4. performance measurement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How is the project management planned changed?

A

through the formal change request process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is PMIS?

A

project management information technology systems, tools such as sheduling software, work authorization systems,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly