Project Integration Management Flashcards
What includes the high level requirements and risks, and the preliminary project budget and schedule?
Project charter
What gives authority to the PM to allocate resources to a project?
Project charter
What are the inputs to make the business charter?
- business documents (use case)
- OPAs
- enterprise environmental factors
- agreements - MSA, MOU
What are data gathering tools that can be used to make the project charter?
data gathering - focus groups, interviews, brainstorming
What occurs during developing the project management plan?
Process of defining, preparing, and coordinating all plan
components and consolidating them into an integrated project management plan
What is the project management plan?
how project will be executed, monitored/controlled, and closed
What are the 4 baselines in the project management plan?
- scope
- schedule
- cost
- performance measurement
How is the project management planned changed?
through the formal change request process
What is PMIS?
project management information technology systems, tools such as sheduling software, work authorization systems,