Project Financial Control and Reporting Flashcards
what is the purpose of a cost report
- to inform the client of the likely out turn of cost for a construction project
- this can empower the client to make changes /secure funding/mitigate foretasted costs
what will a cost report include
- all costs incurred at the date of the report that are known and can be accurately valued
- all costs incurred that are known and can be accurately estimated
- forecast of costs that can be reasonably foreseen and estimated
- risk allowances necessary as can be reasonably foreseen
how often should a cost report be submitted
on a regular and frequent basis, e.g. once a month
what sub sections would you expect in a CONSTRUCTION cost report for a lump sum contract
- contract sum
- adjustments to variables
- adjustment of variations
- adjustment of fluctuations
- claims of loss and expense
- adjustment for risk allowance
where can you find information on cost reporting
RICS-Guidance Note-Cost Reporting 1st Edition 2015
what sub sections would you expect in a PROJECT cost report
- construction costs
- professional fees
- statutory fees and charges
- third party costs
- direct work costs
- land costs
- agency costs
- finance costs
- legal fees
what items in a contract sum can affect the out turn of the final account
- defined provisional sums
- undefined provisional sums
- provisional quantities
- prime costs sums
- daywork allowance
- contract instructions
- anticipated instruction/ early warnings
- loss and expense
- fluctuations
- risk allowances
who should the cost report be distributed to
- QS must take instruction from the client. It is confidential information
- if contractor had a copy, it could jeopardise the client’s bargaining position
how should provisional sum/prime costs/day work allowance/risk allowances be valued in a cost report at the ourset of a project
they should be reported at 100% of the amount defined in the contract sum
what is loss and expense
-Construction contracts will generally provide for the contractor to claim direct loss and/or expense as a result of the progress of the works being materially affected by relevant matters for which the client is responsible
what is final account
- the conclusion of the contract sum including all adjustments
- signifies the agreed value the Employer will pay the contractor
will final account typically include VAT, interest on overdue payments, LADs, or loss and expense
- Loss and expense, YES
- LADs, VAT and interest, NO
in JCT DB 2011 contract, which clause refers to the final account process
Clause 4.12
what is a rolling final account
- where all instructions and cost effects to a project are agreed and up-to-date at the point of the latest financial report
- final account statement if works were to complete with no further changes
when does preparation of a final account occur
throughout the contract period
what is change control
- the administrative process that implements the contract mechanism for instructing change
- must adhere to contract requirements for notification; approval of change
how would yo structure a final account
- contract sum/boq
- variable costs (provisional sum, prime cost sums, day work allowances)
- variations/contract instructions
- loss and expense
- fluctuations
- risk allowance
at final account, must all variations be instructed?
all changes should have a contract instruction, but it is not uncommon at final account state for some variations to not have received a formal instruction still
-it is good practice to ensure the architect/ca are aware of all variations
what is the final certificate
after the defects liability period is over, the final certificate is issued by the CA allowing the release of the remaining retention monies
-final account must be agreed before final certificate
when does half retention get released
half of the retention should be released upon practical completion in most standard contract forms
what happens to the retention release if the final account has not been agreed at practical completion?
- the employer is entitled to release half retention only up to the amount agreed thus far
- another payment certificate may be issued once FA is agreed
what happens if the FA is not agreed after defect liability period is over with regards to retention
the employer is entitled to release full retention up to the amount that has been agreed thus far
what happens if the contractor does not fix the defects during the defects liability period
- most standard forms of contract allow employer to use retention money to employ a different contractor to fix the defect
- the contractor is allowed to rectify the issue themselves first, and usually this is defined by a timescale after notification by the contract administrator