Contract Practice Flashcards
What are principles of contract law
- offer
- acceptance
- capacity
- intent
- legality
what is meant by an offer
- A promise made by one party which matures into a Contract when accepted by the other party
- An invitation to treat does not turn into a contract ; it merely a stage in negotiations, inviting the other party to make an offer
what is meant by acceptance
- where a party agrees to the terms of the offer presented by another party creating a binding contract
- acceptance must be unconditional (e,g a signature on a contract of employment)
- negotiations are counter-offers, not acceptance
- Silence is not acceptance, unless it is clear acceptance was intended (as substantiated by the party’s conduct)
what is meant by consideration
- parties must exchange something of value for a contract to be binding
- for example, selling their house for £1 is valid consideration, selling your house for nothing is not
what is meant by capacity
- all parties must have the ability to understand the terms of and any obligations under the contract
- consent to the contract must be freely given (force, fraud, misrepresentation, inebriation renders the contract void)
- people under 18, under the influence of drugs or those suffering from mental health conditions generally lack the capacity to enter into contracts.
- the client/company must have the capacity to be able to deliver the work/pay for the work, e.g, I do not have the capacity to enter into a contract to deliver a £100m scheme because I am one person with £0 capital no labor, etc
What is meant by intent
- not all agreements between parties are contracts. It must be clear that the parties intended to enter into a legally binding contract
- the person who wants the agreement to be a contract must be prove the parties actually intended to enter into a legally binding contract
What is a letter of intent
- A letter from an employer to a Contractor indicating intention to enter into a formal written Contract for works described
- LOI’s are used to begin work before formal contract is executed
what are the three typical ways of a LOI will operate
- Comfort Letter
- Recognition of Contract
- Consent to Spend
What is a comfort letter
A comfort letter is a non-binding statement of the future intention of both parties
what do Comfort Letters recognizing the existence of Contract do
- Also referred to as a letter of acceptance, it is used by some forms of Contract (e.g. FIDIC) to formally execute the Contract. Generally such a letter will be issued following the agreement of the Contract and marks the completion of negotiations.
- In some cases it can act as an Interim Contractor on its own terms, which will govern the relationship between parties unless and unit a formal written Contract is executed??
What is an LOI with consent to spend
- Sometimes referred to as an ‘if’ Contratc
- Allows work to proceed up to a certain value whilst Contract is being finalized
- Creates a legally binding Contract between parties which pre-dates the principal Contract but will be superseded once principle Contract is executed
What is the HGRCA 1996
- Housing Grants, Construction and Regeneration Act 1996
- Applies to all contractors for ‘construction operations’ (incl consultants)
- Intended to ensure payments are made promptly throughout the supply chain and that disputes and resolved swiftly
what rights does the HGCRA give construction professional?
- right to be paid in interim, periodic or stage payments
- right to be informed of the amount due, or any amounts to be withheld
- right to suspend performance for non-payment
- The right to adjudication
what were the change the HGCRA in 2009
- LDEDCA2009, local democracy, economic development and construction act saw changes to HGRCA
- Includes all Contracts, including those not in writing
- Withholding notice replaced with pay less notice, altering how the sum to be paid is built up
List some the Forms of Contract in the JCT suite
- JCT Design and Build 2016
- JCT Standard Building Contract 2016
- JCT Intermediate Building Contract 2016
- JCT Minor works Contract 2016
- JCT Measured Contract 2016
Other forms of contract aside from JCT
- NEC3 ECC
- FIDIC Red Book (Conditions of Contract for Construction)
- FIDIC Yellow Book (Conditions of Contract for Plant; Design-Build)
- FIDIC Silver Book (Conditions of Contract for EPC Turnkey Projects)
What is assignment
- The benefit of a contract is transferred from one party to another, but the burden of the contract remains with the original party
- Contrast of Novation
What is novation?
- the process whereby both the benefit and the burden of a Contract are transformed from one party to another
- Requires consent from all parties, usually parties enter into tripartite novation agreement
what is a collateral warranty
a way of forming a direct contractual link between two parties with otherwise wouldn’t have a link, such as between a client and a subcontractor
what is a performance bond
A means of insuring the client against the Contractor failing to fufill their contractual obligation
why might you get a performance bond for a smaller contractor
they are more at risk of going solvent
less well established, probably are more dependent on credit and good cash flow.
how much is a typical performance bond worth
10% of Contract Sum
who issues performance bond
Banks/Insurance companies
what are the two variations of performance bonds
- Conditional: client has to prove that the contractor has not performed
- On demand: No pre-conditions needed to be met. Not often used, seen as too harsh
how long would you recommend a performance bond should stay in place
until the end of the Defects Liability Period
name insurances that you may come across in a construction contract
- Public Liability
- Professional Indemnity
- Employer’s Liability Insurance
- Contract Works Insurance
- terrorism insurance
- flood insurance
- Legal Indemnity Insurance
What is Contract Works Insurance
- non-standard insurance policy
- coverage for property damage and third-party injury or damage claims, the two primary types of risks on construction projects
what is Employer’s Liability Insurance
Covers compensation if employees are injured or become ill because of the work they do.
All firms that employ staff are legally required to hold Employers liability Insurance
what is Public Liability Insurance
Provides cover against personal injury or death, loss o damage to property of third parties. e.g. the general public or sub contractors
what is professional indemnity insurance
Provides cover for negligence on part of service provider. Will ensure service providers will not be bankrupted by successful claim, and recompense to client to re-mediate consequences of negligence
what is legal indemnity insurance
- Provides recompense in the event that the policy holder incurs capital loss or expense dealing with a range of possible legal issues
- examples can be unforeseen rights of way issues over land that has been purchased, incurring costs to rectify
what is an advance payment
when a contract sum is paid in advance of the exchange (prior to works being done/ goods supplied)
why may a contractor request advance payment
if there are significant start up/ procurement costs, e.g. expensive items with long lead times
how might the client protect themselves when paying a Contractor in Advance
Secure a payment bond from the Contractor
what are the implications for paying for goods that the sub-contractor has ordered but have not yest been delivered to site?
Put the client at the risk in case that the supplier/sub-contractor goes insolvent, as they may never receive the materials
materials for the project have been sourced and delivered to site. Does the client pay for those materials
Yes, unless stated otherwise in the Contract. Payment is made regardless of whether Contractor has paid supplier
what is ‘retention of ownership’ in regards to materials
- this is clause that allows the supplier to hold ownership of materials until payment
- good for supplier as it encourages payment, improves cashflow
- bad for the client as if items are not affixed, as client may pay Main Contractor but Main may not pay supplier. Supplier could reclaim those items.
what is meant by fluctuations
- a mechanism to deal with inflation, particularly useful in long lasting projects
- accounts for the inflation of labour costs, transport, materials (escalation), overhead
how are fluctuation calculated
- using nationally published price indices
- payment is based on cashflow projections of material, then quarterly percentage assessments of inflation are added to projection
are all projects subject to fluctuations
No, only projects whereby it is stated within the Contract that fluctuation will be accounted for
What is retention
-Retention is a percentage (often 5%) of the amount certified as due to the contractor on an interim certificate, that is deducted from the amount due and retained by the client.
what are three types of fluctuations considered under JCT1
- Changes to statutory contributions, levies and taxes
- Changes to labour, materials, transport (sometimes referred to as escalation)
- Increase in head office/administrative costs
when does retention get released
-half released at practical completion, half upon certification of making good defects
who keeps the interest on the retention money
the client
what happens with the retention money the client keeps
The contract may state that the retention money is kept in a separate bank account
what issues do sub-contractors have with regard to retention
- causes cash flow problems
- release of retention can be delayed for reasons out of their control, e.g. defects liability period not ending due to other parties not remedying defects
- construction supply chain payment charter proposed abolishing retention by 2025
what is retention bond
- instead of holding back money, client receives bond valued at the same amount as would otherwise be retained
- This allows contractor to keep money, helping cashflow, but also protects the client as they can cash in on the bond if required
what are change procedures
a process that ensures potential changes to the deliverable of a project or the sequence of work in a project, are recorded, evaluated, authorized and managed
when should change procedures be introduced
change procedures may be tendered:
- after design freeze
- after tender documentation is released
- after project is tendered
- after the Contractor is appointed
what should change procedures ensure are defined
- reason for the change
- who is requiring the change
- consequences of change time/cost/quality/ who bears the cost
- risks associated with change
- Proposals to mitigate consequences
- alternatives to the proposed change
- time by which change must be instructed
what is variation
an alteration to the original scope of works in a construction contract
-this may be an omission, substitution or addition of works
why do variations occur
- client changes mind (design development or contract documents not stipulating what the client originally wanted in sufficient detail)
- geological anomalies
- statutory changes
- technological advances (changing client requirements)
what are express terms in a Contract
Express terms are those that have been explicitly agreed by both parties and can be oral or in writing
does a contractor have to carry out variations
If there are no express terms, contractor does not legally have to carry out variation
-contractor can continue to carry out works as per agreed at tender
how are variations valued
- contract rates
- if contract rate are not available (for example fr D&B contract that was tendered wit limited design info), the PQS and Contractor’s QS will negotiate to what is deemed reasonable and fair. Market testing, BCIS data and in-house data can be used by the PQS to review Contractor submissions
why do variations cause conflict
- Conflict over the value of the change
- Over whether the change is a client cost or Contractor Risk
- Often conflict occurs where there are gaps in the spec. Contractor may argue it is therefor a change, but Client is not bound to pay for things that a reasonable contractor must have understood to be done
- example: specification may not state every screw used to fix a radiator to the wall, but within the spec for a radiator, pattressing etc, a Contractor would reasonably be expected to assume the inclusion of the screws
what is an extension of time
where the client allows the Construction Period to be extended due to delays that are not the fault of the Contractor
how does the Contractor acquire an extension of time
Gives CA/EA written notice identifying the relevant event that caused the delay
-proposes adjusted completion date
what counts as a relevant event that can result in an EOT?
- variations
- weather
- terrorism
- force majeure
- strikes
- nominated sub-contractor delays
if the contractor can foresee a delay caused by a relevant event, what should they do
- they are required to prevent or mitigate the delay even if it is not their fault
- if they cannot avoid the delay, they can request an EoT
how should a contractor prepare for a claim of EoT?
- Provide good quality information
- Demonstrate link between breach and delay
- demonstrate delay against progress of the works, not programme
what are liquidated damage
-pre-determined damages set at the time the contract is entered in to, based on the actual loss the client is likely to incur if the Contractor fails to meet the completion date.
what are claims of loss and expense
the contractor can claim direct loss and/or expense as a result of relevant matter the client is responsible for