Project Financial Control Flashcards
How would you create a cashflow forecast?
- I would need to have access to the construction programme and contract sum analysis in order to
populate the cashflow. - The values associated with each element of construction could be forecasted at times to reflect their
installation within the programme. - I would split the works into the different packages as shown on the contract programme and include
individual s-curves for each package. - Obtaining drawdown schedules from specialist subcontractors and professional consultants can also
assist when populating the cashflow. - An alternative approach would be to utilise a previous cashflow from a similar scheme or to use
cashflow forecasting software although this may not be as accurate
If your construction budget was £2.5m and proposed construction
period was 25 weeks, would a forecast cashflow expenditure of
£100,000 per week be realistic?
- In reality this would not be very realistic as the cashflow expenditure per week is unlikely to have a flat
or regular profile. - In reality the expenditure is much more likely to have an S-curve profile where at the start of the
scheme, the expenditure per week will be fairly low as the site setup and enabling works are undertaken. - As the scheme progresses, items that are of higher value such as the steel frame and M&E installations
will be undertaken. The cost expenditure per week at this stage will be much higher than at the start of
the scheme. - As the scheme draws to a close, minor finishing items such as decoration and cleaning packages will be
undertaken again resulting in a lower expenditure cost per week.
What is the benefit of a cashflow forecast?
- A cashflow forecast allows the employer to gain an understanding of the financial requirements over
the duration of the project duration and setup any funding requirements for the scheme in advance. - It can also act as a check against valuations and provide an early indication of financial difficulties if the
actual expenditure is lagging behind the forecast
What would you include within a financial report?
- I would typically look to include reference to:
o a) Contract sum total.
o b) The value of Instructed variations.
o c) The value of potential future variations.
o d) Ongoing claims.
o e) Provisional Sum Adjustments.
o e) The anticipated final account total.
o f) The total of certified payments.
What is the purpose of a financial report?
- To report against budgeted values and act as a working cost check on the project budget.
- To give the Client an understanding of any savings or additional monies required.
- To report contract progress compared against pre-contract predictions.
What are variations?
Alterations or modifications to the design, quality or quantity of the contract works or to the site access
or working conditions.
Why might they arise?
- a) change to specification.
- b) discrepancies between contract documents.
- c) discrepancies with statutory requirements.
- d) errors and omissions.
- e) deficiencies in employer’s requirements.
What form must architects instructions take?
- It is best practice under the majority of contracts for instructions to be made in writing.
- The QS is not usually authorised to make additions to the contract sum for instructions that are not in
written form
What about oral instructions?
- The validity of oral instructions depends on whether the form of contract being used contains
mechanisms for them to be valid. - For example within the JCT Standard Building Contract (SBC):-
o Where the Contract Administrator issues an instruction otherwise than in writing, it shall be of
no immediate effect
o But the Contractor shall confirm in writing receipt of the verbal instruction within 7 days.
o If the Contract Administrator does not dissent by notice to the Contractor within 7 days from
receiving the contractors confirmation, it shall take effect as from the expiry of the latter 7 day
period. - In my opinion it is always best practice to follow up verbal instructions with written instructions as
soon as possible
Can the contractor object to a variation?
Some contracts allow the contractor to object to an instruction in special circumstances for example:-
* In the JCT Standard Building Contract the requirement to comply with a valid instruction is subject to
certain exceptions, where:-
o Where the instruction might affect the efficacy of the design of the Contractors Designed
Portion.
o Where the instruction might affect the contractor’s compliance with the CDM Regulations.
o Where the instruction may infringe patent rights.
o Where the instruction relates to a named specialist, and the contractor is unable to enter into a
contract with that firm
What can the architect do if the contractor does not comply with an instruction?
- This depends on the form of contract being used however under JCT Suites if the contractor does not
follow an instruction, the architect will be required to issue a ‘notice to comply’ to the contractor. - If the Contractor still fails to comply, the architect can instruct another party to carry out the work and
the contractor will be liable for any additional costs incurred. - In this circumstance it is important to record the costs and obtain a range of quotations.
What 3 methods are there for obtaining a cost for variations under JCT forms of contract?
This depends on the form of contract being used, under JCT SBC, quotations can be made by:-
o Agreement between the employer and contractor.
o A schedule 2 quotation.
o Valuation by the QS under the valuation rules
What are the time periods for Schedule 2 quotations under JCT SBC?
o The architect should request via issue of an AI.
o The contractor has 7 days to notify that they will not provide one.
o If not, they have 21 days to provide the quotation.
o The architect then has 7 days to confirm in writing the acceptance or rejection.
o The acceptance is called the ‘confirmed acceptance’.
What costs does the schedule 2 quotation contain?
- Value of the work.
- Any adjustment of time.
- Money in lieu of direct loss and expense.
- The fair and reasonable cost of preparing the quotation.
What costs is the contractor entitled to if the schedule 2 quotation is rejected?
The fair and reasonable cost of preparing the quote, as long as the quote itself was fair and reasonable.