Design Economics Flashcards

1
Q

What is the difference between an order of cost estimate and a cost plan?

A

A cost estimate is prepared earlier on in the design process typically between RIBA Work Stages 0 to
Stage 2.A cost plan is produced typically at each RIBA Work Stage from Stage 2 onwards.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the difference between cost and price?

A

Cost is the total price of labour, plant, materials and management deployed for a specific activity.

Price is the amount a purchaser or client will pay for an item or product and is made up of the cost plus the main contractor’s profit margin.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How do you proceed if the cost plan exceeds the project budget?

A

Analyse the costs to assess the source of the increase and identify whether any element of work is abnormally high against the cost estimate.

When the reason for the overspend is identified I would then look to propose value engineering options to my client and design team to bring the forecast back in line with the project budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is buildability?

A

Buildability is harnessing the contractor’s expertise and knowledge during the design stage to generate
ideas for effective and efficient methods of construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the advantages of buildability?

A

Buildability can result in better programming, sequencing and construction methods.
* A quicker more efficient programme can be achieved.
* Reduced capital and life cycle costs of the building can be obtained.
* The quality in the finished building’s performance and maintenance characteristics can be improved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a wall to floor ratio?

A
  • This shows the relationship between the wall area and floor area.
  • It is used to show the cost efficiency of the building.
  • The lower the ratio, the cheaper the building is to construct as there is less external envelope to
    construct in comparison to the floor area
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the most efficient shape?

A

In theory a building with a circular floor plate building would offer the most efficient design as there is
less wall to floor area.
* However a circular floor plate has a poor lettable floor area and is difficult to fit out therefore a square
floor plate is considered to be the most efficient

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How would you prepare an estimate for M&E works?

A
  • I would ask an M&E specialist surveyor to undertake the estimate.
  • For feasibility estimates the M&E amount would be included in the m2 or functional unit rate.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a section 106 agreement?

A

S106s are agreements between local authorities and developers that are negotiated in the context of
granting planning consent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is construction to ‘shell and core’?

A

Shell and core is the basic structure, services and envelope of the building.
* This normally includes the fit out of landlord and common areas for example the reception, toilets, lifts
& stair cores.
* Base services are typically terminated at entry points to each of the lettable floor plates however life
safety services infrastructure is normally provided.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a CAT A fit out?

A
  • CAT A is also known as a ‘developer’s fit out’.
  • This provides generic fit-out items to suit most developers for example life safety elements and basic
    fittings such as suspended ceiling tiles, raised floors, carpets, lighting and power distribution to floor
    plates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a CAT B fit out?

A
  • A CAT B fit out overlays the CAT A provision with bespoke elements that are specific to the needs of
    the building’s user to enable the tenant to occupy and use the space.
  • This would typically include partitions, power distribution to floor boxes, data cabling, artwork and
    branding, upgrading CAT A finishes and toilet finishes.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Where could you find the definitions for these?

A

The British Council of Offices (BCO) fit out guide

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is BWIC?

A

Builders Work in Connection and is usually set as a percentage of the services cost.
BWIC accounts for the Main Contractor to perform any drilling, fixing, cutting and penetrations to
enable the services installation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is an order of cost estimate?

A
  • Under NRM this is described as the determination of the possible cost of a building early in design
    stage in relation to the employer’s fundamental requirements.
  • This takes place prior to preparation of a full set of working drawings or bills of quantities and forms
    the initial build-up to the cost planning process
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the purpose of an order of cost estimate?

A
  • To establish if the proposed building project is affordable and, if affordable, to establish a realistic cost
    limit.
  • The cost limit is the maximum expenditure that the client is prepared to spend on the proposed
    building project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is the format of a feasibility estimate or order of cost estimate?

A
  • This can be presented on a cost per m2, functional unit or elemental basis.
  • It may also be presented as a range for example £700-£850/m2.
  • This may consist of element rates for the main elements of the building for example Substructure,
    Frame, External Walls, Upper Floors & Roof.
  • Any site abnormal costs or enabling works are also considered.
  • Other inclusions are Preliminaries, Contingency, Inflation and location factor adjustments
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is a functional unit? `

A
  • A functional unit is a unit of measurement that considers the prime use of the building.
  • For example in the construction of a hotel or hospital the functional unit may be presented as a cost
    per bedroom or cost per bed.
  • In a retail estimate the functional unit would be presented as the net lettable retail space.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Where would you get your rates from for a preliminary estimate?

A
  • Previous similar projects and historical cost data such as previous tender submissions or a contract sum
    analysis.
  • Other sources may include estimating price books such as Spons or Laxtons, the Building Cost
    Information Service or specialist contractors.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What information do you need to be able to carry out an order of cost estimate?

A
  • Building Location.
  • The type of building.
  • Floor area or number of functional units.
  • Storey height.
  • Whether raised access floors or deep suspended ceiling are envisaged.
  • Initial floor plans, roof plans, elevations and sections.
  • Requirements for refurbishment to existing buildings and enabling works.
  • Indication of specification and quality.
  • Indicative programme, procurement and contract strategy.
  • Budget & cashflow constraints.
  • Site conditions, probable ground conditions.
  • Indicative M&E design intent, availability of utility services and the sustainability strategy.
  • Details of professional fees, development costs, VAT and treatment of inflation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is a cost plan?

A
  • The cost plan presents the estimated cost of the development into an elemental or functional format.
  • It shows how the design team proposes to distribute the funds available on the different elements of
    the proposed building.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is the purpose of a cost plan?

A
  • It is used by the cost consultant to control the development of the design.
  • It identifies the client’s agreed cost limit and how the money is to be allocated to the different elements
    of the building.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

When would you do one?

A
  • A formal cost plan is typically issued between RIBA Work Stage 2 to Stage 4.
  • At stage 2 the Concept Design is made available and the cost plan may be produced at a fairly high
    level. The Cost Plan may be broken down into the different elements of the building based on an
    outline specification and Architectural concept drawings.
  • At stage 3 the Spatial co-ordination of the building is undertaken, the schedule of accommodation may
    be adjusted and the cost plan is updated to reflect this accordingly.
  • At stage 4 the technical design is made available and cost plan updated to reflect the Architect and
    Engineering technical designs. Specialist subcontractor designs may also be made available to support
    with refinement of the project costs.
  • The cost plan at Stage 4 will typically form the basis of a pre-tender estimate to compare tender
    submission against although this is no longer referenced within the RIBA Plan of Work
24
Q

What are the principal components of a cost plan?

A
  • Construction costs.
  • Preliminaries.
  • Contractor’s OH&P.
  • Contingency.
  • Inflation.
  • Assumptions.
  • Exclusions.
  • Area Schedule.
  • List of Drawings & Specifications adopted
25
Q

Name the main elements of an elemental estimate

A
  • Substructure.
    o Excavation.
    o Disposal.
    o Foundations.
  • Superstructure.
    o Frame.
    o Upper floors.
    o External walls.
    o Roof.
    o Internal finishes.
    o Services.
    o External works.
26
Q

What is usually excluded from a cost estimate?

A
  • Professional fees.
  • VAT.
  • Client decant costs.
  • Loose fixtures and fittings.
  • Inflation.
  • Site acquisition costs.
  • Section 106 Agreement.
  • Removal of asbestos.
27
Q

Why is VAT excluded?

A
  • Because different clients will incur different levels of VAT, for example charities may not be subject to
    VAT.
  • We would not be in a position to know the correct rate unless informed of it
28
Q

What is contingency?

A

A sum included within the estimate to cover unknown expenses or unmitigated risks during the project

29
Q

How is contingency assessed?

A
  • The amount included should reflect the risks and unknown specific items associated with the project.
  • During the early design stages a contingency allowance can be included as an overall percentage of the
    cost estimate at around 5%-10%.
  • As more design information becomes available a risk register can be compiled and each item assigned a
    probability and cost impact. The total cost of risk register items can then be included as the project
    contingency
30
Q

What are the stages of the RIBA Plan of Work?

A

0- Strategic definition
1- Preparation and Brief
2- Concept design
3-Spatial coordination
4- Technical design
5- manufacturing and construction
6- handover
7- use

31
Q

How do you take account of inflation when preparing a cost estimate?

A
  • I take into account inflation through the use of Tender Price Indices and include adjustments for
    Construction Inflation and Tender Price Inflation.
32
Q

What time period would construction inflation be included for?

A

I would allow for Construction inflation from the anticipated start of the project to the mid-way point
of the project.

33
Q

What time period would tender price inflation be included for?

A
  • I would allow for Tender Price inflation from the estimate base date to the anticipated tender return
    date
34
Q

What is meant by the base date within a cost estimate?

A
  • The base date refers to the date on which rates and prices contained within a cost estimate are based
    on.
  • These are included for the basis of calculations for example if adjusting the rates for inflation in the
    future, the base date can be used as the starting point from which inflation would be adjusted.
35
Q

What does TPI stand for?

A

Tender Price Indices

36
Q

What do TPIs show?

A
  • They reflect changes in the level of tender prices over a period of time.
  • The price adjustments take into account the level of inflation depending on current and forecast market
    conditions.
37
Q

Where can you obtain tender price index information from?

A
  • The service I use to obtain Tender Price Indices is the Building Cost Information Service.
  • Larger cost consultancies also produce their own in-house tender price forecasts
38
Q

Why do you need to take account of location?

A
  • Inflation needs to be accounted for to anticipate the changes in the prices of labour, plant and materials.
  • We need to account for inflation from the date the cost estimate is produced to the anticipated start
    date of the project.
  • This is to ensure accuracy of the estimate for the client and to ensure the project remains within the
    cost limit that has been established
39
Q

What does BCIS stand for?

A

BCIS

40
Q

What is BCIS?

A
  • The BCIS provides construction cost and price information through publications, online services and
    price books.
41
Q

Where do you get cost information from?

A
  • Previous Tender Submissions.
  • Previous Contract Sum Analysis.
  • Benchmarks.
  • BCIS.
  • Building cost models.
  • SPONS and other price books such as Laxtons.
  • Specialist sub-contractors and suppliers
42
Q

What do you understand by the term VE?

A
  • VE stands for Value Engineering.
  • VE is an organised approach aimed at providing the necessary functions of the building taking into
    account the clients objectives at the lowest cost, without detrimental affects to quality, reliability,
    performance or delivery
43
Q

What do you understand by the term VM?

A
  • Value Management is the proactive process of defining what value means to a client and putting
    procedures in place to ensure that maximum value is delivered for the client, first time.
  • In comparison, Value Engineering forms one of the processes under Value Management and is a
    reactive procedure to bring the anticipated cost of the development back in line with the project budget
    when a potential overspend is identified.
44
Q

What is value, what does value mean?

A
  • Value is a measure of worth taking into account the overall usefulness and benefits that are delivered in
    relation to cost being paid for it.
  • Value is a complex concept and means different things to different clients.
  • For example a short term developer looking to sell a building on completion will place greater value on
    a cheaper out-turn cost whereas a developer occupier may place more importance on a higher quality
    building with lower operating costs.
45
Q

What happens during the VE process?

A
  • The design team will typically be brought together in a meeting including the Client, Quantity
    Surveyor, Architect, Engineers and potentially the Main Contractor and specialist subcontractors.
  • The team will pool together their expertise and suggest different value engineering proposals.
  • The chairperson of the meeting should monitor the proposals against the clients’ objectives around
    value.
  • It is the chairperson and teams responsibility to deliver increased value for money by offering cost
    effective solutions without compromising the overall usefulness of the building when considering the
    clients objectives.
46
Q

What are the phases of the VE process?

A
  • Information phase.
    o Understanding the clients objectives around value.
    o Defining the clients objectives and key criteria governing the project.
    o Understanding background decisions that have influenced the design development of the
    project.
  • Speculation phase.
    o Listing creative ideas to generate a lesser capital or life cycle cost.
    o Generating ideas to provide the necessary functions of the building at the most efficient price.
    o Judgement of each of the ideas is prohibited.
  • Evaluation Phase.
    o The criteria for evaluation of the ideas generated during the speculation phase are defined.
    o Each of the ideas are assessed against the evaluation criteria.
    o The ideas that are considered to offer the greatest potential cost savings and value
    improvement are retained.
    o The ideas considered not worthy or impractical are discarded.
  • Development Phase.
    o Ideas retained from the evaluation phase are developed and expanded into workable solutions.
    o This will include developing a description of the proposed design change with advantages and
    disadvantages.
    o Cost comparisons and design calculations will be undertaken as part of the development phase.
  • Presentation Phase.
    o The retained ideas are presented to the client in a written report.
    o A briefing or verbal presentation may also be provided to build the clients understanding.
    o The rationale and background on why the proposals are being recommended is explained.
    o As well as referencing monetary benefits, a wider communication of delivering the clients
    specific objectives should be provided.
    o Decisions are taken by the client and design team on what proposals are accepted or discarded
47
Q

Why is VM needed?

A
  • Each construction client has their own specific objectives and definition of what value means to their
    organisation.
  • Client organisations are sometimes made up of different working groups with contrasting priorities.
  • If agreements concerning the definition of value are not reached then chances of perceived failure of
    the project increases.
  • VM is needed to reach an agreement on what value is defined as and to reach a shared understanding
    on the objectives that are being sought
48
Q

What are life cycle costs?

A
  • The costs that will be incurred over a defined period of operating and maintaining a building or an asset
    including repair, maintenance, replacement, cleaning, decorating, services provision and disposal
49
Q

What are the advantages of life cycle costing?

A
  • Life cycle costing allows consideration of the long-term implications of a decision.
  • It enables informed decisions to be made on material selection.
  • Life cycle costing can result in lower operational, maintenance and replacement costs.
  • It can also be used to plan future maintenance requirements ensuring easier access and less disruption
    to the operation of the building.
50
Q

What are the disadvantages?

A
  • Future costs are optional and the costs of maintenance can always be deferred.
  • Components are not always replaced due to end of life which is impossible to assess at design stage.
  • The cost of defects caused by bad workmanship and design faults cannot be predicted.
  • It is hard to predict life spans, future inflation and maintenance requirements over long periods
51
Q

What costs should be considered in life cycle costing?

A
  • Capital costs.
  • Operational costs.
  • Maintenance costs.
  • Replacement costs.
  • Disposal costs.
52
Q

Where can you get information about maintenance costs?

A
  • Building Maintenance Cost Information Service (BMCIS) – part of BCIS.
  • From sub-contractors and suppliers.
53
Q

How does the payback period method work?

A

It judges an investment in terms of the time period over which the invested sum is returned in cost
savings.
* The increased expenditure on a higher quality component is viewed as the ‘investment’ and the savings
provided in the form of future costs is viewed as the ‘revenue’.
* The best option would be the one that repaid the investment in the shortest time

54
Q

What sort of materials is the payback period method used for?

A
  • This is often used to evaluate the options for incorporating sustainable technologies.
  • It is considered suitable for elements that have a very high initial capital cost but will ‘pay back’ this
    initial investment over a period of time in terms of reduced running costs.
55
Q

Why might a client accept higher capital costs?

A
  • For prestige reasons.
  • When considering that the replacement or repair may be inconvenient even if the solution is cheaper