Project Finance Flashcards

1
Q

Guidance on cost reporting

A

RICS Guidance Note on Cost Reporting 1st Edition 2015

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How do you communicate the financial status of a project to the Client?

A

Through monthly cost reports and valuations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the contents of a cost report?

A

a. Cover sheet
b. Issue sheet/QA
c. Contents page
d. Executive summary
e. Basis and assumptions
f. Exclusions
g. Contract summary
h. Provisional sums
i. Variations instructed
j. Anticipated variations
k. Valuation summary
l. Cashflow
m. Back cover
n. Summary sheet/appendices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why do we use a cost report?

A

An explanation of each section of the cost report and how this will impact the cost to the client will give
them a better understanding of the costs of the project to date and movements in the period. This in
turn leads to better decision making in regards to scope, specification and programme. This
increases the likelihood of controlling costs within budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How should a cost report be communicated?

A

a. Should be presented by the Quantity Surveyor in person

b. Presenting solely by email or post should be avoided

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is the cost report used in informing decision making?

A

a. Shows the forecast final cost of the project
b. Identifies contractor progress
c. Can highlight any issues with the contractor
d. Can be used to adjust client held contingency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why do we use a forecast final cost?

A

a. This allows the client to see what the potential outturn cost of the project is so that the client can make
the funds available if necessary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How do you ensure the forecast final cost is accurate?

A

a. By agreeing variations when possible and the use of a rolling final account for the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a rolling final account?

A

a. The process of agreeing variations as the project progresses

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What financial and narrative information did you provide the client?

A

a. Financial – provisional sum expenditure, variation value, valuation amount, payment due
b. Narrative – actual cashflow progress against forecast

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How would you produce a cashflow?

A

b. At an early stage:
i. S-curve
ii. Lower levels of expenditure at the start and end (site set up and reduced number of trades
etc. )
iii. Used from a formula, driven by previous, similar schemes
iv. Time and cost curve
v. From this, monthly/period expenditure can be forecast
c. At a later stage (more detailed):
i. Project programme – start and end date
ii. Adjustment for cyclical events and shutdowns
iii. Public holidays
iv. Retention percentage
v. Rectification period
vi. Certification period
vii. Sectional completion and partial possession
viii. Currency
ix. Variations
x. Fees
xi. PS expenditure
xii. Advanced payments
xiii. Materials on/off site
d. Clearly state basis, assumptions, exclusions and dates on all cashflows
e. Split the contract sum down in line with the current programme, usually by package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Why might works on site be below a cashflow?

A

a. Site conditions and adverse weather
b. Re-sequencing of works since the contract cashflow was produced
c. Materials off site not being claimed for
d. Slower than anticipated progress
e. Supply chain issues
f. Cashflow not being accurate initially

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why might works on site be above a cashflow?

A

a. Front loading
b. Working ahead of programme
c. Resequencing
d. Materials being stockpiled/claimed for early
e. Acceleration
f. Over claiming due to financial issues with a contractor/sub contractor
g. Cashflow not being accurate initially

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How would you cost a change?

A

a. Initial design sketch and specification was issued by the CA
b. Contacted suppliers of the bespoke items for an idea of cost
c. Once the drawings were produced:
i. Understood the abortive works that were required
ii. Measured the new works
iii. Priced both add/omit costs
d. This gave an E/O cost for the change
e. £175k – mainly driven from feature joinery unit and headboard

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the different types of provisional sums?

A

a. Defined:
i. Works that are not completely designed
ii. Has been allowed for in programme (prelims)
b. Undefined:
i. Works that have not been defined to a level enough to allow for pricing into programme to be
made

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is change control?

A

a. Administrative process that implements the contract mechanisms for instructing change
b. Must adhere to the contract terms for notification and approval be the identified parties
c. Should be a streamlined process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Why is change control important?

A

a. Critical part of a well audited project
b. All changes should go through this process so that the employer feels that they are able to make an
informed decision
c. Prevents the contractor going ahead and acting on changes that they believe they have been
instructed to do but later find out the employer didn’t want them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

How do JCT contracts define change?

A

a. The alteration or modification of the design, quality or quantity of the works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

How should a variation be valued?

A

a. All variations should be sanctioned in writing
b. Should be the amount agreed by the employer and contractor
c. Where not agreed, the valuation rules apply – Clauses 5.6-5.10
d. Variation quotation:
i. Must be produced by the contractor unless, within 7 days of receipt of the instruction they
disagree with the application of procedure
ii. Contractor has the right be present at measurement
e. Valuation rules:
i. Measurable work:

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

You mentioned that you presented the cost report to the client and their accountants – isn’t there a risk with
this?

A

a. No, the Client’s accountants formed part of the Client team and as such, advising them was advising
the Client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is a change under the JCT SBC?

A

a. The alteration or modification of the design, quantity or quality of the works
b. The imposition by the employer of any additional obligations or restrictions, specifically access to site
c. How is it valued?
i. The employer and contractor agree the value of a variation
ii. Parties exchange information and calculation
iii. Where the value hasn’t been agreed, the variation is to be valued in line with the valuation
rules
d. Valuation rules:
i. Reflect a sliding scale of how closely the varied work resembles what is in the contract
ii. Rules:
1. Where work is of a similar character, works can be valued in line with contract rates,
including a fair allowance for changes in prelims etc.
2. Fair rates and prices – where it is not of a similar character. No definitive method
3. Daywork:
a. Records need to be prepared by the contractor recording labour, plant and
materials used
b. These are then submitted to the CA for review
c. Add on OHP etc.
d. Examples includes opening up for inspections, repair etc, not major works
4. Contractor quotations:
a. Set out in schedule 2
b. Contractor has right to refuse, if instructed to do so, the QS will value in line
with the valuation rules
c. Conditions:
i. Sufficient information must be provided to enable the preparation of a
quotation
ii. Prescriptive time periods for preparation, review and acceptance
iii. The quotation must include the value of the varied work and effects
on any other work
iv. Supporting calculations should be submitted with appropriate
reference to the valuation rules
v. Any requirements for an EOT
vi. Any amounts to be paid in lieu of ascertaining loss and expense
vii. Method statement and resource requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Heads of claim under loss and expense?

A

a. Prolongation costs (time related)
b. General disruption
c. Finance charges
d. Loss of profit
e. Wasted management time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is the purpose of a change control procedure?

A

a. Alert all parties to the existence and nature of any potential change
b. Provides a structured means of reporting the potential implications of the change on costs,
programme and other criteria
c. Provide a basis for the decision to approve or reject the proposed change and inform the adjustment
of the budget, programme and other criteria
d. Trigger the issue of an EAI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is the difference between change control and design development?

A

a. Change control is a deviation from the employers requirements and contractors proposals
b. Design development provides the detail required to facilitate construction based upon the design
information included in the contract documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Talk me through the change control procedure on one of your projects:

A

a. Greenwich – set out within the Project Execution Plan
b. Change request by employer:
i. CRF form:
1. Description of the change
2. Reason for change
3. Provides sufficient information to allow for costing of the change
4. Issued to the contractor, CM and CMT
ii. Within 14 days of receipt by contractor, they are to provide:
1. Impact on time
2. Impact on cost
3. Impact on design
iii. Employer has 14 days to review and decide if they wish to proceed
iv. If rejected, they re-draft or stop
c. Change request by the contractor:
i. Same timescales but instigated by the contractor
d. All put on change control register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What is on a change control register?

A

a. CFF nr
b. Date raised
c. Date to be done by
d. Description
e. Cost
f. Programme
g. Comments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

How are costs kept up to date?

A

a. Contractor submits a weekly dashboard to the client
b. Covers:
i. Health and safety
ii. Project risks
iii. Programme review
iv. Change control
v. Cash flow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Talk me through the process of agreeing design submissions and CDP on your project:

A

a. Status A:
i. Proceed with no comments
b. Status B:
i. Proceed with minor comments
c. Status C:
i. Not approved
d. 14 day design review period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

How do you ensure effective control of costs on a project?

A
  • Proactive risk and contingency management
  • Implementing a robust change control process
  • Management of provisional sums within budget
  • Regular cost reporting which is also forward looking
  • Rolling final account with closure process for financial impact of change
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Types of Contingency

A

Design Contingency – percentage of the concept budget allowed for programmatic and design changes over the course of the design process. This percentage should diminish as design goes from concept to contract document stage.
Construction Contingency – Percentage of the concept budget allowed for unforeseeable conditions encountered during the construction phase
Project Contingency – Design Contingency + Construction Contingency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

How is contingency calculated?

A
  • Calculated as a % for design and a % for construction. i.e. 5% for design and 8% for construction
  • Benchmarked against other similar schemes at early stage estimating
  • Priced from a risk register by identifying cost effects in terms of time, prelims, labour, OH&P, materials etc.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Change Control Process

A

A robust change management process is vital to ensure the financial success.
With any major construction project, it is important to establish the change control process at an early point within the feasibility stage. This process is summarised below:
- Establish the change control strategy
- Define the change control process
- Document the process as a project-specific procedure
- Establish a change control log
- Monitor and log changes
- Agree with the client or supplier as to whether the changes logged are acceptable or should be rejected
- Produce a cost reconciliation statement, summarising where the changes are included
- Report overall costs with agreed changes
The primary tool we use in respect to this is Early Warning System. This system facilitates the timeous recording of all elements of change and potential change in a consolidated single location, thereby allowing the extent of change to be easily identified at any given moment of time.
All those involved in the project should have the ability to flag yp potential change, in order to allow the project team to assess the likely outcome. To do so, a formal change request should be raised. The change request template should include, as a minimum, the following sections:
- The change request number
- The date raised
- A description of the change
- The cost and time implications
- Justification of the change
- An approved or authorised section
- A note of the type of change
- A distribution section
Regular meetings should be held to review any changes raised in that week / month. A decision can be made as to whether to approve each change as having:
- A financial impact
- No financial impact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What is a Cost Reconciliation Statement

A

The cost reconciliation statement should be sufficiently detailed to explain all significant movements of money during the course of the contract, including the funding source for changes. The software solution chosen to manage the change will influence the way the budgets are maintained. All records should be saved electronically, in order to establish an audit trail for change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Purpose of Financial Reporting

A

The purpose of financial reporting is to aid in the overall financial management of a project, by providing a profile of expected costs and an indication of when they will be incurred.
An accurate financial reporting system will provide the client with the information needed to ensure that the project remains affordable and that funds are available at the right time. It will compare the latest estimated out-turn cost with the previously approved budget and will ensure that the budget is not exceeded without justification .

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Why would a cash flow be below the target cash flow?

A

Why would a cash flow be below the target cash flow?

  • Site conditions
  • Adverse weather
  • Re-sequencing of works (perhaps due to procurement of sub-contractor)
  • Materials being stored off site (and not claimed for)
  • Project progressing slower than anticipated
  • Materials not being delivered on time
  • Cash flow not being accurate in the first place
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

How is a Provisional Sum Expended?

A

The architect / CA has to issue an Architects Instruction for its instruction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

How are Provisional Sums dealt with in Final Account?

A

The provisional sums are included in the contract and are deducted and the actual substituted.
The provisional sum is omitted from the adjusted Contract Sum and the value of the variation added back. A provisional sum is therefore only an allowance for work which may or may not be carried out.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

What is a Final Account?

A

Settling a final account can be a long drawn out process, bringing together all financial aspects of the contract. The goal is, of course, to agree a fair valuation of the works undertaken by the contractor and enable the contract administrator to issue the final certificate, thereby concluding the project works.
Reaching an agreement between parties may involve much negotiation and the final accounts prepared from these should be able to withstand the most stringent financial audit as it is legally binding.
Once agreed, the final accounts will necessitate the financial settlement with the contractor and the issuing of a final certificate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

What is a Rolling Account?

A

Our rolling Final Account is issued monthly, ensuring the. Design team and client are fully aware of the intended out-turn cost of the scheme.
One of the primary post-contract tasks is to financially manage the Contractor in accordance with the terms of the contract. This can be done by progressive close-out of risk and agreement of variations / changes ensuring that the Final Account is agreed on a rolling basis with the Contractor.

40
Q

Why do you keep a Rolling Account?

A

This ensures that the ultimate Final Account can be agreed within a short period of time after Practical Completion has been achieved.
The aim is to ensure, with clear & regular communication, resolution of all commercial aspects of the project. The procedures identified about for cost and change control, together with good regular communication between all parties, will ensure swift agreement of the Final Account.
We negotiate with the Contractor to sign-off the cost of work as each element is complete. The advantage to the contractor is that he is paid in full for variations completed and agreed. The further advantage to the client is that there is a rolling Final Account which can be speedily agreed upon project completion with no surprises.
Monthly financial meetings at which contractor participation is encouraged as part of our approach, whereby we prepare a risk and opportunity register as a tool for post contract cost management control.
A rolling final account is part of the post contract cost control procedure therefore ensuring the client is aware of the financial commitments at all times. At the end of each project there will inevitably be final elements of work that either could not be resolved due to a disagreement of the content between the parties or due to delay in information from suppliers to resolve queries. A full detailed FA will be prepared to ensure full and final settlement is achiev

41
Q

What are risks on construction projects?

A
  • External risks: economic, legal, political
  • Procurement risks
  • Choice of contract
  • Financial risks: exchange rate, funding
  • Site risks: restricted, occupied site, planning difficulties, access, environment
  • Client risks: inappropriate consultant team, poor brief, incomplete design, poor co-ordination
  • Selection of appropriate contractor: inadequate selection process
  • Construction and delivery risks: weather, constructability, H&S, availability of resources
42
Q

NRM Risks

A
  • Employers change risks
  • Employers other risks
  • Construction risks
  • Design Development risks
43
Q

What is the purpose of a Cost Report?

A
  • To monitor and manage cost throughout the project

- To inform client on actual project cost against budget

44
Q

What can a cash flow show?

A
  • If a project is running ahead of programme
  • Is a project is running behind programme
  • Project is failing
  • Contractors are experiencing problems / possible liquidation
45
Q

What sub sections would you expect in a PROJECT cost report?

A
  • Statutory fees and charges
  • Third-party costs
  • Direct works costs
  • Land costs
  • Agency costs
  • Finance costs
  • Legal fees
  • Construction costs
  • Professional fees
46
Q

What items in a contract sum can affect the outturn of the final account?

A
  • Undefined PSUMs
  • Defined PSUMs
  • Provisional quantities
  • Prime cost sums
  • Daywork allowances
  • Contract instructions
  • Anticipated instructions/early warnings
  • Loss and expense
  • Fluctuations
  • Risk allowances
47
Q

What are provisional Quantities?

A

Provisional Quantities. Items or components of work for which exact requirements and quantities are not known at the time of tendering. Payment to the contractor is on the basis of the actual work carried out at rates agreed in the contract.

48
Q

How should PSUM/Prime Costs/Daywork allowances/risk allowances be valued in a cost report at the project’s outset?

A

They should be reported at 100% of the amount defined in the Contract Sum.

49
Q

What is loss and expense?

A

Where the contractor is entitled to be reimbursed by the client for loss and expense.

50
Q

How should loss and expense be reported in JCT SBC?

A

Separate to the variations.

51
Q

Will a final account typically include VAT, interest on overdue payments, LADs, or loss and expense?

A

Loss and expense YES

LADs, VAT and interest NO

52
Q

In JCT DB 2011 contract, which clause refers to the final account process?

A

Clause 4.12

53
Q

NEC variation clause?

A

60.1(1)

54
Q

NEC Final Account clause?

A

14.11 spells out the final account process and timescales.

55
Q

When does preparation of a final account occur?

A

Throughout the contract period

56
Q

Can provisional sums be expended without issuing a contract instruction?

A

No

57
Q

What is change control?

A

The administrative process that implements the contract mechanism for instructing change.

MUST adhere to contract requirements for notification & approval of change

58
Q

How would you structure a final account?

A

No firm defined format, but an example would be:

  1. Contract Sum (CSA of BoQ)
  2. Variable costs (PSUMS, PC Sums, Daywork allowances)
  3. Variations/Contract Instructions
  4. Loss and expense
  5. Fluctuations
  6. Risk allowance
59
Q

At final account, must all variations be instructed?

A

All changes should have a contract instruction, but it is not uncommon at final account stage for some variations to not have received a formal instruction still.

It is good practice to ensure the architect/CA are aware of all variations.

60
Q

What is the final certificate?

A

After the defects liability period is over, the final certificate is issued by the CA allowing the release of the remaining retention monies.

Final Account must be agreed before final certificate.

61
Q

When does half retention get released?

A

Half of the retention should be released upon practical completion in most standard contract forms.

62
Q

What happens to the retention release if the final account has not been agreed at PC?

A

The employer is entitled to release half retention only up to the amount agreed thus far.

Another payment certificate may be issued once FA is agreed.

63
Q

What happens if the FA is not agreed after the DLP is over with regards to retention?

A

The employer is entitled to release full retention up to the amount that has been agreed thus far.

64
Q

What happens if the contractor does not fix the defects during the DLP?

A

Most standard forms of contract allow the Employer to use retention money to employ a different Contractor to fix the defect.

The Contractor is allowed to rectify the issue themselves first, and usually this is defined by a timescale after notification by the CA.

65
Q

What are patent defects?

A

Can be discovered by reasonable inspection

66
Q

What are latent defects?

A

Cannot be discovered by reasonable inspection

67
Q

What are contra charges?

A

Where the Employer recovers costs from the Contractor that the Contractor has caused the Employer to incur.

68
Q

What would you do if there were 20 outstanding variations that were not instructed but agreed during the final account negotiation?

A

Issue an instruction wrapping up all of these outstanding works, with the instruction listing each variation as a sub-section/bullet point

69
Q

In JCT contract suite, how long does the Contractor have to provide information for the final account?

A

6 months

70
Q

What is value engineering?

A

Improve the value of products, by increasing functionality/quality and/or reducing cost.

71
Q

What is value management?

A

Gives a project a clear path to create value through the understanding of client objectives as well as the needs and wants of the stakeholders.

Value engineering used to reach these objectives.

72
Q

What is value for money?

A

Achieving value for money requires value management to understand objectives and client values, then using VE to decrease cost while maintaining functionality, or increase functionality greater than cost.

More value for less money.

73
Q

What are the two types of cash flow forecast relevant in construction?

A
  • Cash flow for a company

- Cash flow for a construction project

74
Q

How long will company cash flow period forecast?

A

A year

75
Q

What is the value of cash flow forecast for a company?

A
  • Resource and business planning

- Analysing the companies health

76
Q

What is the purpose of a construction project cash flow?

A
  • To project when payments are due to ensure finances are in place (alert bank/funder of drawdowns)
  • Construction cash flow will inform company’s cash flow
77
Q

What may be included in a Contractor’s cash flow?

A
  • Cash in from Employer
  • Cash out to sub-contractors
  • Cash out to suppliers
  • Retention monies in
  • Monies to their consultants
  • Tax payment
78
Q

What is an S curve?

A

Standard Curve

A generic cash flow forecast in the shape of an “S” typical of most projects

79
Q

Why would you ask for the contractor to produce their own cash flow based on the programme?

A

I will be more accurate than an S curve as it will account for anomilies relevant to the project, whereas the S curve is generic.

It is important to watch out for front-loading

80
Q

What is front loading?

A

This is where the contractor forecasts costs at the start of the project to be greater than they actually will be, in order to coerce the PQS into thinking higher payments are due early.

81
Q

What are the risks of over-payment?

A

This improves the contractor’s cash flow but leaves the client at risk, as they may be paying more than has actually been carried out.

If the Contractor stops working/goes into liquidation, the Employer may lose out as they have paid for more than they have received.

82
Q

What is the most accurate form of measurement of works completed on site to date?

A

Not judging by the cash flow forecast, but by visiting the site and conducting an assessment

83
Q

What are the benefits of requesting company cash flow forecasts before employing consultants/contractors?

A
  • Predict how the company will be performing in the future

- Gauge whether they will be able to cope with the additional works

84
Q

What should you look for in a company cash flow of a tendering contractor?

A
  • Overdraft size
  • How often they use their overdraft
  • If their overdraft was removed, what effect would that have
  • Is it bringing in as much money as it is spending?
85
Q

What are the four types of payment mechanism in contruction contracts, and which are the most/least accurate?

A
  • Stage payments (highest accuracy of cash flow forecast, but lowest accuracy of value of work done to date)
  • Milestone payments
  • Payment against activity schedule
  • Valuation of work done to date on site (lowest accuracy of cash flow forecast, but highest accuracy of value of work done to date)
86
Q

What legislation tries to improve construction cash flow?

A
  • The Housing Grants, Regeneration and Construction Act 1996

- The Local Democracy, Economic Development and Construction Act 2009

87
Q

How does the HGRCA 96 improve cash flow in construction?

A
  • Right to interim, periodic or staged payments
  • Contracts must include mechanism for communicating what is due, when & final date for payment
  • Pay less notice must be communicated early
  • Contractor may suspend performance for no payment
  • Prohibiting pay that is linked to payment in a different contract
  • Statutory right to refer disputes to adjudication
88
Q

What is the DHSS Expenditure Forecasting?

A

The DHSS Expenditure Forecasting was created
by KW Hudson for the Department of Health and
Social Security for forecasting expenditure on
capital projects

89
Q

What is the difference between a risk and an issue?

A

An issue is something that’s happening now that is or will soon jeopardise the delivery of the projects objectives.

A risk may turn into an issue. When the probability of a risk reaches 100%, it is an issue.

An issue cannot turn into/be a risk, as it is already happening.

90
Q

Risk management can be divided into two phases. What are these?

A

Risk analysis - identification and assessment

Risk management - mitigation and control

91
Q

What’s a CIL?

A

A levy applied by Local Authorities on new developments to cover costs for infrastructure to the area. Areas under 100m2 exempt.

Full details on govt. website for inclusions/exclusions

92
Q

What is handed over at PC?

A
  • H&S file
  • O&M manual
  • Building log book
  • As built drawings
  • User guide
93
Q

NEC Compensation Event Notification Periods

A

Contractor must provide a Quotation within 3 weeks

PM must respond within 2 weeks

Contractor has 8 weeks to notify

If no response within one week, the contractor can notify, Pm has a further 2 weeks to respond.

94
Q

What Are the NEC W clauses

A

Dispute resolution procedure (used in the United Kingdom when the Housing Grants, Construction and Regeneration Act 1996 applies).

W1-
W2-(for use on UK projects where the parties are parties to a construction contract and are subject to the Construction Act 1996).

95
Q

What are the NEC X Clauses

A
Option X1 Price adjustment for inflation 
Option X2 Changes in the law 
Option X3 Multiple currencies 
Option X4 Parent company guarantee 
Option X5 Sectional Completion 
Option X6 Bonus for early Completion 
Option X7 Delay damages 
Option X12 Partnering 
Option X13 Performance bond 
Option X14 Advanced payment to the Contractor Option X15 Limitation of the Contractor’s liability for his design to reasonable skill and care 
Option X16 Retention 
Option X17 Low performance damages 
Option X18 Limitation of liability 
Option X20 Key Performance Indicators (not used with Option X12)
96
Q

What are the NEC Y Clauses

A
Option Y(UK)1 Project Bank Account 
Option Y(UK)2 The Housing Grants, Construction and Regeneration Act 1996 
Option Y(UK)3 The Contracts (Rights of Third Parties) Act 1999
97
Q

Option Z x

A

Option Z Additional conditions of contract