Design Economics & Cost Planning Flashcards
What is the RIBA?
The plan of works is a guidance document which organises the process of managing and designing building projects and administering building contracts into a number of key stages.
What are the different stages of the RIBA plan of work 2013?
a. Stage 0 – Strategic definition
b. Stage 1 – Preparation and brief
c. Stage 2 – Concept design
d. Stage 3 – developed design (Spatial Coordination 2020)
e. Stage 4 – technical design
f. Stage 5 – construction
g. Stage 6 – closeout and handover
h. Stage 7 – in use
How does the 2020 plan of work differ to the 2013 plan of work?
- RIBA Sustainable Futures Group project strategy section replaces the Green Overlay to provide advice on sustainability outcomes and show the value of undertaking aftercare activities during Stage 6
- Replacing the BIM Overlay is a section looking at the increasing complexity of information requirements. Although the pencil or CAD are still used on many projects, more have matured around UK level 2 BIM processes and are nudging towards the challenges of using next generation digital deliverables.
- The 2020 Plan of Work responds to feedback on how Stage 2 works and particularly to different approaches to the timing of planning applications. It acknowledges adjustments required at the Stage 3 and 4 interface, depending on the procurement strategy.
- The Plan of Work reinforces the intention that Stage 4 includes all the design information required for manufacturing and construction. Stage 4 is the most complex to navigate because the procurement strategy dictates when information for the design team and specialist subcontractors will be produced.
- The final core change is ensuring clarity between the Stage 2 and 3 gateways. It acknowledges that Stage 2 is about getting the architectural concept right and having it signed off by the client and key project stakeholders, while incorporating strategic engineering items and closing the brief. Stage 3 is not about changing the concept. It is about design studies for portions of the building, detailed engineering analysis, adding detail to project strategies and getting the cost plan right.
6.
At which stages are different cost estimates issued?
b. Elemental Cost Plans:
i. Stage 2
ii. Stage 3
iii. Stage 4
c. Pre Tender Estimate – stages 2/3/4 depending on procurement route
Where would you find guidance on what is required in each type of estimate?
a. NRM 1 – order of cost estimating and cost planning for capital building works
What would you expect to find in an order of cost estimate?
a. Floor area method (£/m2 GIA), functional unit method (£/key) and elemental method (£/sq.ft frame)
b. Information required:
i. Location of the site
ii. Area schedule and unit mix
iii. Level of fit out required
iv. Storey heights
Provide some examples of costs for different elements:
0 Facilitating Works 1.1 Substructure £16 10 2.1 Frame 41 41 2.2 Upper Floors 2.3 Roof 3 2.4 Stairs and Ramps 1.5 2.5 External Walls 55 50 2.6 Windows and External Doors 2.7 Internal Walls and Partitions 7 2.8 Internal Doors 3.1 Wall Finishes 3.2 Floor Finishes 3.3 Ceiling Finishes 4.1 Fittings Furnishing and Equipment Services Generally 50 44 Lifts BWIC On Costs
How do you ensure accurate cost estimating?
a. All issued work goes through stringent QA process
b. Checked against benchmarked data
What is net to gross ratio?
Net to gross ratio is the proportion of net internal area against gross internal area (usable against total
internal)
What is a good net to gross ratio on a typical floorplate?
a. Residential – 80%
b. Commercial – 75%
i. Can be up to 85% on single tenant and single core
c. Student resi – 70% per floor
How would you improve net to gross in a residential building?
a. Reduction in party wall thickness
b. Rationalise column layouts to include within external/party walls
c. Reduction in corridor/circulation space
d. Increase number of apartments per core
What is wall to floor ratio?
a. The amount of façade area to internal area (GIA)
What is a good wall to floor ratio?
The lower the better – anywhere around 0.4 is realistic
How would you improve wall to floor ratio?
a. Reduce articulation
b. Utilise bolt on balconies rather than inset
c. Choose a circular shape – although cost may be higher
d. Reduce storey heights
What is the most efficient shape of a building?
a. Circle – lowest wall to floor ratio
b. May have higher costs though due to producing a circle
Why is a low wall to floor important?
a. Façade is generally one of the most expensive packages, reducing the amount of this to internal,
usable space is important in increasing the value of the building
b. Can be circa 25% of shell and core cost
What is solid to glazed ratio?
a. The proportion of solid façade against glazed – the more solid there is, the lower the cost and also the
lower the solar gain
How do modular efficiencies compare to traditional?
a. Net to gross internally of a module is generally higher due to lack of internal structure – around 90-
95%
b. GEA to GIA efficiencies poor due to external thicknesses – 90%
c. Site wide GEA:GIA:NIA lower due to thicker dividing walls
d. Wall to floor usually low due to less articulation
What subsection of IPMS 3 is closest to NIA?
a. Option 2
CAT A:
a. Floors
b. Ceilings
c. Paint
CAT B:
a. Meeting rooms
b. IT cabling
What affects currency?
a. Interest rates
b. Trade deals
c. Political stability
d. Inflation
e. Current account status
What packages are most impacted by currency?
a. Façade
b. Stone
Typical exclusion:
a. VAT
b. Inflation beyond issue of the estimate
c. S106/S278/CIL
d. Commuted payments
e. Over sailing rights
f. Land acquisition costs
g. Professional fees
Typical assumptions
a. Procurement route
b. Tender strategy
c. Basedate for estimate
d. Interest rate allowances
e. Design information used
What is CIL?
a. Community infrastructure levy
b. Planning charge introduced by the planning Act 2008 to help local authorities deliver infrastructure as
a tool to support development
c. Focuses more on borough wide works rather than S106 which is for immediate vicinity
What is earned valued management?
a. A technique adopted by project managers to measure the progress of a project in a defined and
objective matter and assess whether resources are being used effectively
b. Compares three measures to see if the project is ahead or behind its budgets for time and/or cost
c. Measures used are:
i. The planned value of work over time (the agreed programme and cost plan)
ii. The earned value of works completed
iii. The actual cost of works completed