Project Finance Flashcards
What is a cash flow?
The net balance of cash moving into and out of a business at a specific point in time
i.e. A view of expenditure over a programme
What are the two main types of cash flow?
Company - organisational cash flow
Project - particular to a construction contract or project
What is profit?
The balance that remains when all of a business’s operating expenses are subtracted from its revenues
What is cash flow forecasting?
A forecast used to inform the employer of when their monetary commitments under the contract will be.
i.e. money moving in and out of the business
What is a company cash flow forecast used for?
- To review and analyse the predicted incoming and outgoing cash for a set period of time
- Business and resource planning
- Analysing the financial health of companies.
What is a project cash flow forecast used for?
- Inform the Client of when their monetary commitments under the contract will be.
- Ensures that the employer has an accurate assessment of what needs to be paid to the contractor and at what periods
- Used as a method of establishing progress & any serious deviations from the original forecast could represent problems/delays to the contract or even financial difficulty for the contractor.
What are the considerations when preparing a project cash flow forecast?
Pre-Contract
1. Consider what period to forecast for – just DDS phase? Whole lifecycle?
2. At the early stages, valuations from previous similar projects to ascertain ‘best fit’ profile
3. Prepare a resource utilisation forecast for internal resources
4. Consider any land, planning, equipment, materials, plant etc. costs.
Post-Contract
5. Use the project programme to determine when costs contained within the activity schedule are likely to be incurred
What is an accrual?
Accounting entries for the expenses/revenue for which payment hasn’t yet changed hands (recording costs when they are incurred not when they are billed) to keep records of revenue and expenses that have not been received or incurred
How would you graph a cashflow forecast?
By plotting % of value of work completed / projected to be complete (y=axis) against time (x-axis). In preparing a forecasted graph, you have a baseline to work with which can be used to track progress.
The graph will likely take an ‘s-curve’ shape.
What is a cost report?
Informs the client of a construction project of the likely outturn cost at a specific point in time. It reflects the current position of the project & the Anticipated Final Cost.
What would you include in a cost report?
a) Executive Summary (inc. original contract sum)
b) Financial Summary (inc. contingency spend profile, spend to date and anticipated final total)
c) Project Manager’s Instructions (inc. anticipated)
d) Agreed CE’s
e) Notified early warnings
f) Cash Flow Forecast vs. Actual Spend
g) Risk Register
h) Claims
i) Opportunities Register
What is the difference between cost management and cost control?
- Cost Management - Total concept for managing & controlling cost on a project from start to finish to ensure contract sum remains within budget. Helps design team prepare design based on cost.
- Cost Control - Part of the cost management process & occurs post contract
Why is project cost control important?
- Helps manage the delivery of the project within the approved budget
- Risks can be identified faster as well as opportunities for potential cost savings
- Monitor the effectiveness and efficiency of site operations and provide feedback to estimating teams for future projects.
Used to provide the best possible estimate of:
* Established project cost to date.
* Anticipated final cost of the project.
* Future cash flow.
What is contingency?
Costs that are held in reserve to deal with unforeseen circumstances. These costs will be added to the base cost estimate to arrive at the cost limit.
How do you arrive at a suitable contingency value?
- Carry out a workshop w/ various project team members to identify the likely risks on the project & produce a Risk Register
- Once risks are identified they are assessed in terms of probability & impact (T&C) to develop a contingency.
- Review regularly - close, remove, reassess, mitigative measures etc.