Project Finance Flashcards
What is a defined provisional sum?
works that are sufficiently well defined or detailed to allow the Contractor to make an allowance.
What is an undefined provisional sum?
Cost allowance for works or services which is not known at the date of Contract.
What is contingency?
An amount of money that is included to cover potential events not specifically accounted for.
Sometimes a percentage of the Build Contract price.
What is Golden Brick?
The point at which HMRC designates that a building is residential. Therefore zero rated for VAT purposes.
What are the JCT D&B 2016 Payment timescales?
IVD - One month from date of site possession
Due Date - 7 days from IVD
Payment Notice - 5 days from Due Date
Final Date for Payment - 14 days from the Due Date
Pay less notice - 5 days prior to the Final Date for Payment.
What is retention?
It provides security for current and future performance by withholding a percentage of money due to the Contractor