Project Documents and Processes Flashcards

1
Q

Activity attributes

A

Detailed information about each individual activity (Define activities)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Activity list

A

List of all the activities on the project. (Define activities)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Assumption log

A

List of all project assumptions and constraints. (Develop project
charter)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Basis of estimates

A

Describes how schedule, cost, and resource
estimates were developed. Also includes their
confidence level and ranges. (Estimate activity
duration, estimate
costs, estimate
activity resources)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Change log

A

Lists and describes the status of the change requests
that is being processed or have been processed
through the perform integrated change control
process (Perform integrated
change control)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cost estimates

A

Cost of each individual activity. (Estimate costs)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost forecasts

A

A prediction of how much the project will cost when
it completes based on the current work. (Control Costs)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Duration Estimates

A

Amount of time needed to complete each activity on the project. (Estimate Activity durations)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Issue log

A

List of all issues on the project. Could include history type, description, priority, status, and resolution (Direct and manage project work)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Lessons Learned register

A

List of all lessons learned throughout the project (Manage Project knowledge)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Milestone list

A

Description of all milestones on a project (Define activities)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Physical resource assigments

A

Assignments of the physical resources to the activities or work packages ( Acquire resources)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Project calendars

A

A calendar view of what takes place on a day-to-day basis (Develop Schedule)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Project communications

A

Communicate in on the project by following the communications management plan (Manage Communications)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Project Schedule

A

A detailed breakdown of the work that needs to be done to complete the project will include a bar chart, milestone chart, and schedule network diagram (Develop Schedule)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Project schedule network diagram

A

A sequencing diagram that shows the relationships amongst the activities and the sequence in which they will be performed, but also shows the critical path. (Sequence activities)

17
Q

Project scope statement

A

A detailed description of the project or phase deliverables (Define scope)

18
Q

Project team assignments

A

Assignment of the project team members to the work packages or activities (Acquire resources)

19
Q

Quality control measurements

A

Results of the activities done in the “control quality” processes to determine if the quality standards or policies were met (Control quality)

20
Q

Quality metrics

A

An attribute that will be used to measure the project or to deliverable to verify that it has met the quality requirements and/or standards (Plan quality management)

21
Q

Quality report

A

A report which generally includes information about quality issues on the project and recommendations on how to improve the processes on the project (Manage quality)

22
Q

Requirements Documentation

A

Description of all requirements from the project stakeholders (Collect Requirements)

23
Q

Requirements traceability matrix

A

A table that traces the origin of the requirements (Collect requirements)

24
Q

Resource breakdown structure

A

Categorization and type of the project resources (Estimate activity resources)

25
Q

Resource calendars

A

Shows the availability of resources for the project, both physical and HR. (Acquire resources)

26
Q

Resource requirements

A

Description of the number and type of resources needed to complete each work package or activity. (Estimate activity resources)

27
Q

Risk report

A

A list of all positive and negative risks on a project, along with responses. (Identify risks)

28
Q

Risk Report

A

A description of the overall project risks. (Identify risks)

29
Q

Schedule data

A

The information that is used to create the schedule includes who made it, assumptions, and constraints. (Develop schedule)

30
Q

Schedule forecasts

A

A prediction of when the project may be completed based on the current progress of the work.

31
Q

Stakeholder register

A

A list of all stakeholders which can include categorization, impact, and communication requirements (Identify stakeholders)

32
Q

Team charter

A

The team’s guidelines on a project include values, decision-making process, acceptable behavior, code of conduct, and etiquette. (Plan resource management)

33
Q

Test and evaluation documents

A

Used to help evaluate the project deliverables when completed (Manage quality)