PMP Terms & Formulas Flashcards

1
Q

Budget at Completion (BAC)

A

Original budget of the project.

No formula

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Planned Value (PV)

A

Amount of money worth of work that should have been done on the project

PV=Planned % Complete x BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Earned Value (EV)

A

Amount of money worth of work you actually did on the project.

EV= Actual % Complete x BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Actual Cost (AC)

A

Amount of money you already spent on the project

No formula

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Variance (CV)

A

The difference between the work done and money spent This Value should be positive for under budget. (Negative values indicate over budget)

CV = EV-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cost Performance Index (CPI)

A

The rate of how we are spending to earnings on the project. (This value should be 1 or < for projects under budget)

CPI = EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Schedule Variance (SV)

A

The difference between the amount of work we should have done vs. amount done. This value should be positive for ahead of schedule. (Negative values indicate behind schedule)

SV = EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Schedule Performance Index (SPI)

A

The rate of how we are meeting the project schedule (value of 1 and < is ahead of schedule)

SPI = EV/PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Estimate at Completion (EAC)

A

Forecasting the total cost of the project at the end based on the current spending rate of the project.

EAC= BAC / CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate to Completion (ETC)

A

Forecasting the amount needed to complete the current project based on performance.

ETC = EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Variance at Completion (VAC)

A

The difference between the original budget and the new forecasted budget. This value should be positive for projects ending at or under budget.

VAC = BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

To-Complete Performance Index (TCPI)

A

The performance that needs to be met to finish the project within the budget.

TCPI = (BAC-EV) / (BAC-AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

PERT - Beta

A

(Optimistic + 4*Realistic + Pessimistic) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

PERT - Standard Deviation

A

(Pessimistic - Optimistic) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

PERT - Triangular Distribution

A

(Optimistic + Realistic + Pessimistic) / 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Communications Channels

A

N(N-1) / 2