Project Documents Flashcards

1
Q

Activity attributes

A

Detailed information about each individual activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Activity list

A

List of all the activities on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Assumption log

A

List of all project assumptions and constraints.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Basis of estimates

A

Describes how schedule, cost, and resource
estimates were developed. Also includes their
confidence level and ranges.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Change log

A

Lists and describes the status of the change requests
that is being processed or have been processed
through the perform integrated change control
process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cost estimates

A

Cost of each individual activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost forecasts

A

A prediction of how much the project will cost when
it completes based on the current work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Duration estimates

A

Amount of time needed to complete each activity on
the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Issue log

A

List of all issues on the project. Could include
history type, description, priority, status, and
resolution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Lessons learned register

A

List of all lessons learned throughout the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Milestone list

A

Description of milestones on a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Physical resource
assignments

A

Assignments of the physical resources to the
activities or work packages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Project calendars

A

A calendar view of what takes place on a day-to-day
basis on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Project
communications

A

Communicate in on the project by following the
communications management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Project schedule

A

A detailed breakdown of the work that needs to be
done in order to complete the project. Will include a
bar chart, milestone chart, and the project schedule
network diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Project schedule
network diagram

A

A sequencing diagram that shows the relationships
amongst the activities and the sequence they will be
performed. But also show the critical path.

17
Q

Project scope
statement

A

A detailed description of the project or phase
deliverables

18
Q

Project team
assignments

A

Assignment of the project team members to the work
packages or activities

19
Q

Quality control
measurements

A

Results of the activities done in the “control quality”
processes to determine if the quality standards or
policies were met.

20
Q

Quality metrics

A

An attribute that will be used to measure the project
or to deliverable to verify that it has met the quality
requirements and/or standards

21
Q

Quality report

A

A report which generally includes information about
quality issues on the project and recommendations
on how to improve the processes on the project

22
Q

Requirements
documentation

A

Description of all requirements from project
stakeholders

23
Q

Requirements
traceability matrix

A

A table that traces the origin of the requirements

24
Q

Resource breakdown
structure

A

Categorization and type of the project resources

25
Resource calendars
Shows the availability of resources on the project both physical and HR
26
Resource requirements
Description of the number and type of resources needed to complete each work package or activity
27
Risk register
A list of all positive and negative risks on a project, along with responses
28
Risk report
A description of the overall project risks
29
Schedule data
The information that is used to create the schedule such as who made it, assumptions, and constraints.
30
Schedule forecasts
A prediction of when the project may be completed based on the current progress of the work.
31
Stakeholder register
A list of all stakeholders, which can include categorization, impact, and communication requirements
32
Team charter
Guidelines team should follow on a project. Includes values, decision-making process, acceptable behavior, code of conduct, and etiquette.
33
Test and evaluation documents
Manage quality
34