Project Documents Flashcards

1
Q

Activity Attributes

A

Detailed information about each individual activity

Define Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Activity List

A

List of all the activities on the project

Define Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Assumption Log

A

List of all project assumptions and constraints

Develop Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Basis of Estimates

A

Describes how schedule, cost, and resource estimates were developed. Also includes their confidence level and ranges.

Estimate activity duration, costs, activity resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Change Log

A

Lists and describes the status of the change requests that is being processed or have been processed through the perform integrated change control process

Perform Integrated Change Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cost Estimates

A

Cost of each individual activity

Estimate Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost Forecasts

A

A prediction of how much the project will cost when it completes based on the current work.

Control Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Duration Estimates

A

Amount of time needed to complete each activity on the project.

Estimate Activity Durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Issue Log

A

List of all issues on the project. Could include history, type, description, priority, status, and resolution.

Direct and Manage Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Lessons Learned Register

A

List of all lessons learned throughout the project

Manage Project Knowledge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Milestone List

A

Description of milestones on a project

Define Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Physical Resource Assignments

A

Assignments of the physical resources to the activities or work packages

Acquire Resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Project Calendars

A

A calendar view of what takes place on a day-to-day basis on the project

Develop Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Project Communications

A

Communicate on the project by following the communications management plan

Manage Communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Project Schedule

A

A detailed breakdown of the work that needs to be done in order to complete the project. Will include a bar chart, milestone chart, and the project schedule network diagram.

Develop Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Project Schedule Network Diagram

A

A sequencing diagram that shows the relationships amongst the activities, the sequence they will be performed, and also shows the critical path.

Sequence Activities

17
Q

Project Scope Statement

A

A detailed description of the project or phase deliverables

Define Scope

18
Q

Project Team Assignments

A

Assignment of the project team members to the work packages or activities

Acquire Resources

19
Q

Quality Control Measurements

A

Results of the activities done in the “control quality” processes to determine if the quality standards or policies were met.

Control Quality

20
Q

Quality Metrics

A

An attribute that will be used to measure the project or deliverable to verify that it has met the quality requirements and/or standards.

Plan Quality Management

21
Q

Quality Report

A

A report which generally includes information about quality issues on the project and recommendations on how to improve the processes on the project.

Manage Quality

22
Q

Requirements Documentation

A

Description of all requirements from project stakeholders.

Collect Requirements

23
Q

Requirements Traceability Matrix

A

A table that traces the origin of the requirements.

Collect Requirements

24
Q

Resource Breakdown Structure

A

Categorization and type of the project resources

Estimate Activity Resources

25
Q

Resource Calendars

A

Shows the availability of resources on the project both physical and HR

Acquire Resources

26
Q

Resource Requirements

A

Description of the number and type of resources needed to complete each work package or activity

Estimate Activity Resources

27
Q

Risk Register

A

A list of all positive and negative risks on a project, along with responses.

Identify Risks

28
Q

Risk Report

A

A description of the overall project risks.

Identify Risks

29
Q

Schedule Data

A

The information that is used to create the schedule such as who made it, assumptions, and constraints.

Develop Schedule

30
Q

Schedule Forecasts

A

A prediction of when the project may be completed based on the current progress of the work.

Control Schedule

31
Q

Stakeholder Register

A

A list of all stakeholders, which can include categorization, impact, and communication.

Identify Stakeholders

32
Q

Team Charter

A

Guidelines team should follow on a project. Includes values, decisionmaking process, acceptable behavior, code of conduct, and etiquette.

Plan Resource Management

33
Q

Test and Evaluation Documents

A

Used to help evaluate the project deliverables when completed.

Manage Quality